In: Statistics and Probability
An analyst is preparing a report for the CEO of a company. Two
options for insurance, A and B, are available for purchase by the
company. There is an 80% chance an incident will be covered with
option A and 95% chance an incident will be covered if option B is
used. Option B is more expensive, however, and the analyst
estimates only a 30% chance the CEO will select it (the CEO will
select option A the other 70% of the time).
Use the following notation:
A— option A is purchased
B— option B is purchased
C— a given incident is covered
Q
Which of the following is the correct representation of the information that is provided to us?
P(A) = .70, P(B) = .30, P(C|A) = .80, P(C|B) = .95 |
P(A|C) = .70, P(B|C) = .30, P(C|A) = .80, P(C|B) =.95 |
P(A and C) = .70, P(B and C) = .30, P(C|A) = .80, P(C|B) = .95 |
P(A) = .70, P(B) = .30, P(A|C) = .80, P(B|C) = .95 |
P(A) = .70, P(B) = .30, P(A and C) = .80, P(B and C) =.95 |
Q
What is the probability that an incident will be covered?
P(C) = .70 * .80 + .30 * .95 = .845 |
P(C) = .30 * .95 = .2375 |
P(C) = .70 * .80 = .56 |
P(C) = .70 * .95 + .30 * .80 = .905 |
P(C) = .70 * .30 + .80 * .95 = .97 |
Q
A particular incident was covered. What is the probability that the CEO chose to purchase option A?
(0.70 * 0.80) / (0.70*0.80 + 0.30*0.95) = 0.66272 |
(0.70 * 0.80) / (0.80 + 0.95) = 0.32 |
(0.30 * 0.95) / (0.70*0.80 + 0.30*0.95) = 0.33728 |
0.70 * 0.80 = 0.56 |
0.80 |
Answer - 1: The correct given values are:
P(A) = .70, P(B) = .30, P(C|A) = .80, P(C|B) = .95
Option A is correct.
Answer - 2: P(C) = .70 * .80 + .30 * .95 = .845
Option A is correct.
Answer - 3: P(CEO to purchase option A) = (0.70 * 0.80) / (0.70*0.80 + 0.30*0.95) = 0.66272
Option A is correct.