In: Accounting
Below is a listing of inspection costs at one of Lockheed Martin's production facilities:
Units Produced | Inspection Costs | ||||||
April | 922 | $ | 17,912 | ||||
May | 983 | $ | 18,300 | ||||
June | 928 | $ | 17,965 | ||||
July | 912 | $ | 17,810 | ||||
August | 934 | $ | 17,994 | ||||
September | 919 | $ | 17,880 | ||||
October | 936 | $ | 18,032 | ||||
November | 876 | $ | 17,290 | ||||
December | 915 | $ | 17,838 | ||||
The controller of Lockheed Martin has determined that inspection costs are a mixed cost that depend on units of production.
Estimate the fixed cost per month of inspection using the high-low method. Your answer is closest to:
Calculation of Fixed cost is as follows: |
Total cost = Variable cost + Fixed cost |
Thus, Fixed cost = Total cost - Variable cost |
High Level activity: 983 units |
Fixed cost = Total cost - Variable cost |
= $ 18,300 - $ 9278.78275 |
= $ 9021.21725 |
Total Variable cost = activity level * Variable cost per unit |
= 983 * $ 9.43925 |
= $ 9278.78275 |
Thereofre Fixed cost is $ 9021.21725 |
or |
Low Level activity: 876 units |
Fixed cost = Total cost - Variable cost |
= $ 17,290 - $ 8268.783 |
= $ 9021.217 |
Total Variable cost = activity level * Variable cost per customer |
= 876 * $ 9.43925 |
= $ 8268.783 |
Thereofre Fixed cost is $ 9021.21725 |
Working note: |
Calculation of Variable cost per unit is as follows: |
Variable cost per unit = ( Total cost at high activity level - Total cost at low activity level ) / ( High activity level - low activity level ) |
In this case high activity level at May 983 units |
In this case low activity level at November 876 units |
Variable cost per unit = ( Total cost at high activity level - Total cost at low activity level ) / ( High activity level - low activity level ) |
= ( $ 18,300 - $ 17,290 ) / ( 983 - 876 ) |
= $ 1,010 / 107 |
= $ 9.43925 per unit |
Thus, Variable cost is $ 9.43925 per unit |