In: Accounting
Question #2: Which Should We Buy?
| 
 Machine A  | 
 Machine B  | 
|
| 
 Initial Cost  | 
 $150,000  | 
 $100,000  | 
| 
 Pre-Tax Operating Cost  | 
 $65,000  | 
 $57,500  | 
| 
 Expected Life (years)  | 
 8  | 
 5  | 
| 
 Machine A: Cash Flows  | 
||||||||||
| 
 Year  | 
 PV  | 
 0  | 
 1  | 
 2  | 
 3  | 
 4  | 
 5  | 
 6  | 
 7  | 
 8  | 
| 
 OCF  | 
||||||||||
| 
 Initial Cost  | 
||||||||||
| 
 Total Cash Flows  | 
||||||||||
| 
 Depreciation Tax Shield (Benefit)  | 
||||||||||
| 
 NPV  | 
||||||||||
| 
 EAC  | 
As per the information given in the question, answer is as below :
| Machine A | ||||||||||
| Year | PV | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| Initial Cost | $ (150,000) | $ (150,000) | $ - | $ - | $ - | $ - | $ - | $ - | $ - | $ - | 
| OCF | $ (346,770) | $ - | $ (65,000) | $ (65,000) | $ (65,000) | $ (65,000) | $ (65,000) | $ (65,000) | $ (65,000) | $ (65,000) | 
| Shield (Benefit) | $ 138,708 | $ - | $ 26,000 | $ 26,000 | $ 26,000 | $ 26,000 | $ 26,000 | $ 26,000 | $ 26,000 | $ 26,000 | 
| Depreciation Tax | $ 45,489 | $ - | $ 12,000 | $ 12,000 | $ 12,000 | $ 12,000 | $ 12,000 | $ - | $ - | $ - | 
| Total Cash Flow | $ (312,573) | $ (150,000) | $ (27,000) | $ (27,000) | $ (27,000) | $ (27,000) | $ (27,000) | $ (39,000) | $ (39,000) | $ (39,000) | 
| NPV | 5.3349 | - | 0.9091 | 0.8264 | 0.7513 | 0.6830 | 0.6209 | 0.5645 | 0.5132 | 0.4665 | 
| EAC | $ (58,590) | 
| Machine B | |||||||
| Year | PV | 0 | 1 | 2 | 3 | 4 | 5 | 
| Initial Cost | $ (100,000) | $ (100,000) | $ - | $ - | $ - | $ - | $ - | 
| OCF | $ (217,970) | $ - | $ (57,500) | $ (57,500) | $ (57,500) | $ (57,500) | $ (57,500) | 
| Shield (Benefit) | $ 87,188 | $ - | $ 23,000 | $ 23,000 | $ 23,000 | $ 23,000 | $ 23,000 | 
| Depreciation Tax | $ 30,326 | $ - | $ 8,000 | $ 8,000 | $ 8,000 | $ 8,000 | $ 8,000 | 
| Total Cash Flow | $ (200,456) | $ (100,000) | $ (26,500) | $ (26,500) | $ (26,500) | $ (26,500) | $ (26,500) | 
| NPV | 3.7908 | - | 0.9091 | 0.8264 | 0.7513 | 0.6830 | 0.6209 | 
| EAC | $ (52,879.75) | 
Since EAC of Machine B is lower, hence Machine B should be selected.