Question

In: Accounting

QUESTION 3 For the below ME alternatives , which machine should be selected based on the...

QUESTION 3

For the below ME alternatives , which machine should be selected based on the PW analysis.

Machine A Machine B Machine C
First cost, $ 21,929 30000 10000
Annual cost, $/year   8,702               6,000            4,000
Salvage value, $                 4,000               5,000            1,000
Life, years 3 6 2

Answer the below questions :

A- PW for machine A=

---------------------------------------------------------------------------------------------

QUESTION 4

For the below ME alternatives , which machine should be selected based on the PW analysis.

Machine A Machine B Machine C
First cost, $ 15000 28,881 10000
Annual cost, $/year   8,994               6,000            4,000
Salvage value, $                 4,000               5,000            1,000
Life, years 3 6 2

Answer the below questions :

B- PW for machine B=

---------------------------------------------------------------------

QUESTION 5

  1. For the below ME alternatives , which machine should be selected based on the PW analysis.

    Machine A Machine B Machine C
    First cost, $ 15000 30000 12,373
    Annual cost, $/year   15,805               6,000            4,000
    Salvage value, $                 4,000               5,000            1,000
    Life, years 3 6 2

    Answer the below questions :

    C- PW for machine C =

D- Based on the PW value you got in the previous questions, which machine we should select? type you explanation below

-----------------------------

QUESTION 7

  1. for th below two machines and based on CC analysis which machine we should select?

    Machine A Machine B
    First cost, $ 28,321          100,000
    Annual cost, $/year   11,988               7,000
    Salvage value, $   5,755 -
    Life, years 3 infinite

    Answer the below question:

    A- the CC for machine A=

---------------------------------------------------

QUESTION 8

  1. For th below two machines and based on CC analysis which machine we should select?

    Machine A Machine B
    First cost, $ 22,294 117,224
    Annual cost, $/year   14,745 7,540
    Salvage value, $   5,001 -
    Life, years 3 infinite

    Answer the below question:

    B- the CC for machine B=

Solutions

Expert Solution

Question No.3

Assumed i = 10% per year

PW of Machine A

Year Cost Annual Cost Salvage Value Total Cost PVF @10% Present Value
0 $21,929.00 $21,929.00 1.0000 $    21,929.00
1 $   8,702.00 $   8,702.00 0.9901 $      8,615.84
2 $   8,702.00 $   8,702.00 0.9803 $      8,530.54
3 $   8,702.00 $    -4,000.00 $   4,702.00 0.9706 $      4,563.71
Total Cost $    43,639.09

PW of Machine A = $43,639.09

Question 4

Year Cost Annual Cost Salvage Value Total Cost PVF @10% Present Value
0 $28,881.00 $28,881.00 1.0000 $    28,881.00
1 $   6,000.00 $   6,000.00 0.9901 $      5,940.59
2 $   6,000.00 $   6,000.00 0.9803 $      5,881.78
3 $   6,000.00 $   6,000.00 0.9706 $      5,823.54
4 $   6,000.00 $   6,000.00 0.9610 $      5,765.88
5 $   6,000.00 $   6,000.00 0.9515 $      5,708.79
6 $   6,000.00 $    -5,000.00 $   1,000.00 0.9420 $         942.05
Total Cost $    58,943.63

PW of Machine B = $58,943.63

Question 5

Year Cost Annual Cost Salvage Value Total Cost PVF @10% Present Value
0 $12,373.00 $12,373.00 1.0000 $    12,373.00
1 $   4,000.00 $   4,000.00 0.9901 $      3,960.40
2 $   4,000.00 $    -1,000.00 $   3,000.00 0.9803 $      2,940.89
Total Cost $    19,274.28

PW of Machine C = $19,274.28

Based on PW Value Machine -C should be selected since the cost of Machine is less.

Please post the other Questions seperately, we can answer the same as well. All the best :)


Related Solutions

For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,265 Annual cost, $/year   14,021                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- PW for machine C =
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 22,421 30000 10000 Annual cost, $/year   8,497                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A=
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,937 Annual cost, $/year   13,944                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- AW for machine C =
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 15000 21,476 10000 Annual cost, $/year   8,095                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : B- PW for machine B=
For the below ME alternatives , which machine should be selected based on the PW analysis....
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 23,979 30000 10000 Annual cost, $/year   8,679                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- PW for machine A=
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10% Machine A Machine B Machine C First cost, $ 15,567 30000 10000 Annual cost, $/year   9,535                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : A- AW for machine A=
For the below ME alternatives , which machine should be selected based on the AW analysis....
For the below ME alternatives , which machine should be selected based on the AW analysis. MARR=10%. Machine A Machine B Machine C First cost, $ 15000 30000 11,564 Annual cost, $/year   10,709                6,000             4,000 Salvage value, $                  4,000                5,000             1,000 Life, years 3 6 2 Answer the below questions : C- AW for machine C =
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%.
For the below ME alternatives , which machine should be selected based on the PW analysis. MARR=10%.Machine AMachine BMachine CFirst cost, $              15000            30000          10,423Annual cost, $/year                 12,340               6,000            4,000Salvage value, $                 4,000               5,000            1,000Life, years 362Answer the below questions :A- PW for machine C =B- Based on the PW value you got in the previous questions, which machine we should select? type you explanation below 
Question 3c: Based on the ME, MSE and MAPE for the 3 different methods shown in...
Question 3c: Based on the ME, MSE and MAPE for the 3 different methods shown in the Rankings worksheet, which method would you recommend. Define a weakness and strength of each method, based on the ME, MSE and MAPE and total forecast of population for the year. 3 different methods chosen Regression HW Additive HW Multiplicative ME 20876 4222 -895 Mean Error, but not MAD RMSE 119540 102288 78353 MSE MAPE 3.30% 2.60% 1.91% MAPE Rank 3 2 1
For the mutually exclusive project alternatives shown below, determine which one (s) should be selected.Alternative...
For the mutually exclusive project alternatives shown below, determine which one (s) should be selected. Alternative                 present valueA 25000B 12000C 10000D 15000
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT