Question

In: Statistics and Probability

Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North...

Problem 4

Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North California facility, they make tables. All parts of the table are purchased except for the tabletop that is fabricated at the plant. Tables are made to order for dealers who FAX orders into the sales department. Orders are processed from the order database on FIFO basis.

The first step in the process is to cut the top ¾ pressboard. It takes one worker 20 minutes to cut each top. Four workers work in the cutting work center each with his own cutting equipment. At the same time the plastic laminate that goes on top of the table (the finished surface) is cut from stock. There are four other workers each with their own equipment in this work center. It takes one worker 30 minutes to cut this material.

The next step is to glue the plastic laminate to the pressboard top. The contact cement is applied to the top surface of the pressboard and the bottom surface of the laminate. There is one worker who applies the glue to both surfaces. It takes him 5 minutes to apply the glue. After the glue has been applied the two pieces are lined up and pressed together. There is one worker who does that and it takes her 6 minutes to complete that step. After pressing together, the assembled top must be set aside for 30 minutes to allow the glue to dry. There is unlimited space in this drying area.

The finished tabletop is then attached to the leg assembly that is purchased from a nearby metalworking firm. It takes a team of two workers working together for 10 minutes to attach the leg assembly to the tabletop. There are two such teams in this assembly area.

Finally the table is packed and shipped by one team of two workers working together who take 4 minutes to pack and ship one finished table.

  1. Draw a process flow diagram for the material flow at frank’s manufacturing plant including all work centers and their capabilities, inventory and information flow.

Time for each unit(minutes)

Service rate (units/hour)

# servers

Capacity (units/hour)

Cutting board

20

3

4

12

Cutting plastic

30

2

4

8

Glue

5

12

1

12

Press

6

10

1

10

Dry

30

2

Infinite

Infinite

Assemble

10

6

2

12

Shipping

4

15

1

15

  1. What is the Bottleneck in Frank’s plant? Explain (Short answer)
  2. How many tables can be produced in an 8 hour days?
  3. What are the Cycle and the throughput Times for this process?
  4. If one additional worker and tools were added to the bottleneck, how many tables could the line produce in an 8 hour day?

Solutions

Expert Solution

a) The flow diagram will be as below with below details of each operation, like its lead time, service rate and capacity etc.

Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min Assembly - 10 min
Cutting Board -20 min Cutting Plastic - 30 min Glue - 5 min Press - 6 min Dry - 30 min Shipping - 4 min
Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min Assembly - 10 min
Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min
Dry - 30 min
Infinite
Service Rate Units/Hour 3 2 12 10 2 6 15
Servers 4 4 1 1 infinite 2 1
Capacity (Unit/Hour) 12 8 12 10 infinite 12 15

b) Bottleneck in the process = the operation with lowest capacity per hour = Cutting plastic operation is with lowest capacity per hour = 8 units per hour.

c) Number of tables can be produced in an 8 hour days = 8 hour * capacity per hour = 8 * 8 = 64 nos.

The Cycle time of the process = highest lead time of the operations = Plastic Cutting operation = 30 minutes / 4 server = 7.5 minutes.

d) The throughput Times for this process = Total lead time for making one table = 105 minutes., as below

Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min Asembly - 10 min
Cutting Board -20 min Cutting Plastic - 30 min Glue - 5 min Press - 6 min Dry - 30 min Shipping - 4 min
Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min Assembly - 10 min
Cutting Board -20 min Cutting Plastic - 30 min Dry - 30 min
Dry - 30 min
Total
Through put Time 20 30 5 6 30 10 4 105

e) If one additional worker and tools were added to the bottleneck, then capacity at bottleneck will be as below

  • The server at bottle neck will be 5, then service rate 2 unit per hour, then capacity = 2 * 5= 10 units per hour.
  • Then number of tables could the line produce in an 8 hour day = 8 * 10 = 80 tables.

Related Solutions

Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
Scholastic Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
SquerDeal Mfg manufactures tables and desks, which are sold in sets of 4 chairs to tables...
SquerDeal Mfg manufactures tables and desks, which are sold in sets of 4 chairs to tables to bussiness, school, and public facilities. They reported the fallowing financial information for last year: Direct Labor 20,000hrs @$15/hr, production Manager Salary $80,000, Factory Rent $60,000, Equipment Maintenance$5,000(considered a variable expense), Equipment Depreciation $25,000, Production for the year 35,000 units, Total Revenue $12,000,000, Total table and chairs set sold during the period 30,000, Operating Income under absorption costing (after non-production expenses) $5,000,000 what would...
School Days Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units which are...
School Days Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units which are sold to public school systems throughout the midwest. The controller of the company’s Desk Division is currently preparing a budget for the third quarter of the year. The following sales forecast has been made by the division’s sales manager.      July 5,000 desk-and-chair sets   August 6,000 desk-and-chair sets   September 7,500 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5...
Discount Furniture Pty Ltd manufactures a variety of desks, chairs, tables and shelf units which are...
Discount Furniture Pty Ltd manufactures a variety of desks, chairs, tables and shelf units which are sold to public school systems throughout Queensland. The accountant of the company’s School Desk Division is currently preparing a budget for the first quarter of 2018. The following sales forecast has been made by the division's sales manager.           January 
   5,000 desk and chair sets           February 
   6,000 desk and chair sets           March 
   7,500 desk and chair...
Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the...
Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the customer requirements. They have a workshop facility where the table is fabricated and a painting facility where the final finishing and painting of the table is done. The company follows a Job Order scheduling process where each job is scheduled using appropriate priority rules. During a particular period, the company receives six different orders from six different customers. The six orders with the respective...
Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the...
Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the customer requirements. They have a workshop facility where the table is fabricated and a painting facility where the final finishing and painting of the table is done. The company follows a Job Order scheduling process where each job is scheduled using appropriate priority rules. During a particular period, the company receives six different orders from six different customers. The six orders with the respective...
WoodGrain Technology makes home office furniture from fine hardwoods. The company uses a job-order costing system...
WoodGrain Technology makes home office furniture from fine hardwoods. The company uses a job-order costing system and predetermined overhead rates to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Preparation Department is based on machine hours, and the rate in the Fabrication Department is based on direct labor-hours. At the beginning of the year, the company’s management made the following estimates for the year:        Department Preparation Fabrication Machine-hours 84,000 36,000 Direct labor-hours 30,500 58,200 Direct...
WoodGrain Technology makes home office furniture from fine hardwoods. The company uses a job-order costing system...
WoodGrain Technology makes home office furniture from fine hardwoods. The company uses a job-order costing system and predetermined overhead rates to apply manufacturing overhead cost to jobs. The predetermined overhead rate in the Preparation Department is based on machine hours, and the rate in the Fabrication Department is based on direct labor-hours. At the beginning of the year, the company’s management made the following estimates for the year:        Department Preparation Fabrication Machine-hours 83,000 36,000 Direct labor-hours 34,500 58,800 Direct...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT