Question

In: Economics

Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the...

Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables
according to the customer requirements. They have a workshop facility where the table is
fabricated and a painting facility where the final finishing and painting of the table is done. The
company follows a Job Order scheduling process where each job is scheduled using appropriate
priority rules. During a particular period, the company receives six different orders from six different
customers. The six orders with the respective processing time are listed in table 1. The orders
are listed in the sequence in which the orders are received. Considering the finite capacity
scheduling method, determine the most appropriate job sequence which will maximize the number
of jobs that can be completed on time. Discuss the reasons for the selection of the sequence. If
all the jobs could not be finished on time, what appropriate measures could be taken to solve the
problem?

Job Time at the workshop
facility (Days)
Time at painting
facility (Days)
Days remaining till
due date

Jobs Time at workshop
facility (Days)
Time at painting
facility (Days)
Days remaining till
due date
A 2 5 12
B 2 6 10
C 3 3 12
D 5 4 9
E 5 7 10
F 5 3 11

Table 1 : Details given

Solutions

Expert Solution

Hey

The answer of the following question is given below as follows :

So this question is related with the N-job 2 Machine so we will apply Johnson's rule that will give the suitable sol.

So According to the Johnson's rule we selecte the highest processing time activity. If that time requires at 1st m/c. Place at start and if that time requires at 2nd m/c. Place at last.

So in the question we know that we have two facilities ie

1) Workshop facility

2) Painting facility.

Max. Time required for Job B at machine ( facility 2) so place it in the last.

Like this.

___ ___ ____ _____ ____ B

Now the next max. Is 6 days for job C at the facility 2 so place it at 2 last place.

___ ____ ____ _____ ____ C B

Now next max.is 5 days for A,E&F for job A,E&F at facility 2. So select these activities which requires min. Time of facility 1 which is 2 days for A&F.

___ ____ A. F. C. B

now next will be for 5 days which have the required time at facility 1 is 3 days is job E.

___ E A F C B

AND SO ON

D E A F C B.

TABLE ON IMAGE

SO there is four jobs which cannot be finished on time.

Ans.i ) For this case we should place a parallel facility which will reduce the work completion time.

I hope I have served the purpose well.

Thanks


Related Solutions

Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the...
Urban Office LLC, a major office furniture manufacturer, and supplier, manufactures office tables according to the customer requirements. They have a workshop facility where the table is fabricated and a painting facility where the final finishing and painting of the table is done. The company follows a Job Order scheduling process where each job is scheduled using appropriate priority rules. During a particular period, the company receives six different orders from six different customers. The six orders with the respective...
A furniture supplier, Acme Chairs, Inc., manufactures a Basic office chair and a Deluxe office chair....
A furniture supplier, Acme Chairs, Inc., manufactures a Basic office chair and a Deluxe office chair. Each Basic chair costs $25.00 to manufacture, and each Deluxe office chair costs $40.00 to manufacture. Acme Chairs wishes to determine the optimal production quantities per day for each chair model in order to minimize overall total cost. The production of each chair requires three types of materials: Wood, Primer, and Paint. The amount of material available per day to manufacture the chairs is...
A furniture manufacturer specializes in wood tables. The tables sell for $ 140 per unit and...
A furniture manufacturer specializes in wood tables. The tables sell for $ 140 per unit and incur $ 49 per unit in variable costs. The company has $ 14,560 in fixed costs per month. The company desires to earn an operating profit of $ 8,190 per month. ​(Abbreviation used; CM​ = contribution​ margin.) 10. Calculate the required sales in units to earn the target profit using the equation method. 11. Calculate the required sales in units to earn the target...
Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North...
Problem 4 Frank’s Fine Furniture makes tables, desks, bookcases, and other office furniture. At the North California facility, they make tables. All parts of the table are purchased except for the tabletop that is fabricated at the plant. Tables are made to order for dealers who FAX orders into the sales department. Orders are processed from the order database on FIFO basis. The first step in the process is to cut the top ¾ pressboard. It takes one worker 20...
Porter Company manufactures furniture, including tables. Selected costs are given below: 1.The tables are made of...
Porter Company manufactures furniture, including tables. Selected costs are given below: 1.The tables are made of wood that costs $100 per table. 2.The tables are assembled by workers, at a wage cost of $40 per table. 3.Workers assembling the tables are supervised by a factory supervisor who is paid $38,000 per year. 4.Electrical costs are $2 per machine-hour. Four machine-hours are required to produce a table. 5.The depreciation on the machines used to make the tables totals $10,000 per year....
Roper Furniture manufactures office furniture and tracks cost data across their process. The following are some...
Roper Furniture manufactures office furniture and tracks cost data across their process. The following are some of the costs that they incur. Classify these costs as fixed or variable costs, and as product costs or period costs: Wood used to produce desks ($125.00 per desk) Production labor used to produce desks ($15 per hour) Production supervisor salary ($45,000 per year) Depreciation on factory equipment ($60,000 per year) Selling and administrative expenses ($45,000 per year) Rent on corporate office ($44,000 per...
SHOW STEP BY STEP SPREADSHEET MODEL A furniture manufacturer produces two types of tables – country...
SHOW STEP BY STEP SPREADSHEET MODEL A furniture manufacturer produces two types of tables – country and contemporary – using three types of machines. The time required to produce the tables on each machine is given in the following table: Machine Country Contemporary Total Machine Time Available Per Week Router 2.5 3.0 1,000 Sander 3.5 5.5 2,000 Polisher 2.0 1.0 1,500 Country tables sell for $395 and contemporary tables sell for $515.   Management has determined that at least 25% of...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
Scholastic Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc., manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold...
Scholastic Furniture, Inc. manufactures a variety of desks, chairs, tables, and shelf units that are sold to public school systems throughout the Midwest. The controller of the company’s Desk Division is currently preparing a budget for the second quarter of the year. The following sales forecast has been made by the division’s sales manager. April 10,000 desk-and-chair sets May 12,000 desk-and-chair sets June 15,000 desk-and-chair sets Each desk-and-chair set requires 10 board feet of pine planks and 1.5 hours of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT