Question

In: Economics

Three mutually exclusive projects are being consid ered by Sesame Street Productions (SSP). SSP U a...

Three mutually exclusive projects are being consid ered by Sesame Street Productions (SSP). SSP U a MARR of 8%. SSP has heard about your excellent analysis skills and wants you to help them make a decision. Using a B/C analysis, which project do you recommend to SSP? Assume all benefits and costs repeat for Project A.

Project A $300 Initial cost Annual benefits $200 Project life (years) 2 B/C ratio 1.19

Project B  $450 Initial cost Annual benefits $190 Project life (years) 4 B/C ratio 1.40

Project C $765 Initial cost ,Annual benefits $300 Project life (years) 4 B/C ratio 1.3

Solutions

Expert Solution


Related Solutions

1. Three mutually exclusive projects are being considered. The cash flows for each and corresponding rate...
1. Three mutually exclusive projects are being considered. The cash flows for each and corresponding rate of return are list below. MARR = 8% can any project eliminated? Using functional notation to solve for the incremental rate of return. 1 2 3 0 -20000 -25000 -29000 1 2000 2500 3000 2 5000 6200 7000 3 8000 9900 11000 4 11000 13600 15000 ROR 9% 8.7% 7.4% 2. Which project must you choose based on the information provided below using conventional...
Three mutually exclusive​ earth-moving pieces of equipment are being considered for several large building projects in...
Three mutually exclusive​ earth-moving pieces of equipment are being considered for several large building projects in India over the next five years. The estimated cash flows for each alternative are given below. The construction​ company's MARR is 18% per year. Which of the three​ alternatives, if​ any, should be​ adopted? Assume repeatability is appropriate for this comparison. Caterpillar Deere Case Capital investment ​$22,000 ​$26,400 ​$17,500 Net annual revenue ​$6,500 ​$9,000 ​$5,200 Salvage value ​$4,500 ​$5,000 ​$3,750 Useful life 4 years...
Three mutually exclusive projects are being considered: A B C First cost $1000 $2000 $3000 Uniform...
Three mutually exclusive projects are being considered: A B C First cost $1000 $2000 $3000 Uniform annual benefit 250 350 525 Salvage value 200 300 400 Useful life (years) 5 6 7 Assume identical replacements. (b)If 8% is the desired rate of return, which project should be selected?
Explain why, if two mutually exclusive projects are being compared, the project that generates most of...
Explain why, if two mutually exclusive projects are being compared, the project that generates most of its cash flows in the beginning of its life might have the higher ranking under the NV criterion if the required rate of return is high, whereas the project that generates most of its cash flows toward the end of its life might be deemed better if the required rate of return is low. Would changes in the firms required rate of return ever...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Year Project A Project B 0 ($100,000) ($100,000) 1 39,500 0 2 39,500 0 3 39,500 133,000 Based only on the information given, which of the two projects would be preferred, and why? Project A, because it has an even cash inflow stream. Project B, because it has a higher IRR. Indifferent, because the projects have equal IRRs. Include both in the capital...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow Proj A Project B 0 -$300,000 -$300,000 1 145,500 $150,000 2 145,500 -$ 40,000 3 145,500 $370,000 The firm’s cost of capital is 10 percent. Based only on the information given, What are the NPV for Project A and B? Which project do you choose based on the NPV? What are the payback periods...
There are three mutually exclusive alternatives being considered.  One of the three must be selected, so this...
There are three mutually exclusive alternatives being considered.  One of the three must be selected, so this is a set of three cost alternatives.  MARR is 15% and the life of each project is 12 years.  These projects are: Project I Capital Cost: $130,000 Revenue/Savings: 22,000 Expense/Cost: $12,000 Salvage: $25,000 Project II Capital Cost: $100,000 Revenue/Savings: $10,000 Expense/Cost: $15,000 Salvage: $20,000 Project III Capital Cost: $160,000 Revenue/Savings: $10,000 Expense/Cost: $20,000 Salvage: $40,000 please solve asap, thank you!
Four mutually exclusive projects are being considered for a new​ 2-mile jogging track. The life of...
Four mutually exclusive projects are being considered for a new​ 2-mile jogging track. The life of the track is expected to be 75 years, and the sponsoring​ agency's MARR is 9​% per year. Annual benefits to the public have been estimated by an advisory committee and are shown below. Use the​ B-C method​ (incrementally) to select the best jogging track.                                                                                                                           Alternative A B C D Initial cost ​$54,000 ​$55,000 ​$62,000 ​$145,000 Annual benefits ​$7,000 ​$8,500 ​$10,000 ​$19,000 ​B-C...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A...
Two projects being considered are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$50,000 -$50,000 1    15,000 0 2    15,000 0 3    15,000 0 4    15,000 0 5    15,000 90,000 1) Calculate NPV of each project if the required rate of return on these projects is 8 percent. 2) which would be chosen and why?
You are considering the following three projects. A & B are mutually exclusive while C is...
You are considering the following three projects. A & B are mutually exclusive while C is independent. Question: On one graph, plot the NPV profile for Both projects, A&B. please show how on excel Following are their expected cash flows year project A Project B Project C 0 -60,000.00 -40,000.00 -20,000.00 1 0 40,000.00 35,000.00 2                    82,000.00                    40,000.00                     30,000.00 3                    60,000.00                    20,000.00                        2,000.00 4 20,000.00 10,000.00 -40,000.00
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT