What is the Multifactor productivity for the Blue Space Inc. if they have the following
data?
Units produced: 25,000
Standard price: $30/unit
Labor input: 500 hours
Cost of labor: $25/hour
Cost of materials: $10,000
Cost of overhead: 2x labor cost
VALUES
LABOR = 12500
MATERIAL = 10000
OVERHEAD = 25000
OUTPUT = 750000
PRODUCTIVITY = OUTPUT / TOTAL INPUT
PRODUCTIVITY = 750000 / (12500 + 10000 + 25000) = 15.79