Question

In: Economics

assume that a dam cost 17 million to build in a year and that beginning in...

assume that a dam cost 17 million to build in a year and that beginning in the next year, the dam yields net benefits of 2 million per year for 10 years. If the discount rate is equal to 7 percent, what is the net present value of the dam? should it be built or not? What happens if the chosen discount rate is 2%? should the dam built, now?

Solutions

Expert Solution

Initial Cost = 17 million

Yearly benefit = $2 million

Time period = 10

Present Value = Current Value/(1+discount rate)number of year

When discount rate is 7%

Current value of 2 million at the end of first year = 200000/(1+0.7)1 = 1869159

Similarly, Current value of 2 million at the end of second year = 200000/(1+0.7)2 = 1746877

Calculating present value of all 10 years:

We find that the total present value of all net benefits is less than the initial cost of building the dam. Thus the dam should not be built.

When discount rate is 2%

Here we see that total present value of all net benefits is greater than the initial cost of building the dam. Thus the dam should be built.


Related Solutions

A company has beginning inventory of 17 units at a cost of $17 each on February...
A company has beginning inventory of 17 units at a cost of $17 each on February 1. On February 3, it purchases 27 units at $19 each. 21 units are sold on February 5. Using the FIFO periodic inventory method, what is the cost of the 21 units that are sold?
A bridge will cost (in the present) $280 million to build, will be completed by next year, and will start producing the benefits next year, $8 million per year.
8. A bridge will cost (in the present) $280 million to build, will be completed by next year, and will start producing the benefits next year, $8 million per year. It will cost $1 million a year to maintain (starting next year, too). It is expected that the bridge will last for long time. The market interest rate is 5%. Approximate (with the formula for a perpetuity) the present value of the bridge project (including the cost of construction, benefits,...
Q1. The initial cost of constructing a permanent dam (i.e., a dam that is expected to...
Q1. The initial cost of constructing a permanent dam (i.e., a dam that is expected to last forever) is $425 million. The annual net benefits will depend on the amount of rainfall: $18 million in a "dry" year, $29 million in a "wet" year and $52 million in a "flood" year. Meteorological records indicate that over the last 100 years there have been 86 "dry" years, 12 "wet" years, and 2 "flood" years. Assume the annual benefits, measured in real...
Williams & Sons last year reported sales of $17 million,cost of goods sold (COGS) of...
Williams & Sons last year reported sales of $17 million, cost of goods sold (COGS) of $12 and an inventory turnover ratio of 2. The company is now adopting a new inventory system. If the new system is able to reduce the firm's inventory level and increase the firm's inventory turnover ratio to 3 while maintaining the same level of sales and COGS, how much cash will be freed up? Do not round intermediate calculations. Round your answer to the...
The U.S. Department of Interior is planning to build a dam and construct a hydroelectric power...
The U.S. Department of Interior is planning to build a dam and construct a hydroelectric power plant. In addition to producing electric power, this project will provide flood control, irrigation, and recreational benefits. The estimated benefits and costs expected to be derived from the three alternatives under consideration are listed as follows: Design 1 - Initial invesment = $198 million - Annual recurring benefits = $37 million - Annual recurring costs = $15 million Design 2 - Initial investment =...
Inventory Management Williams & Sons last year reported sales of $17 million, cost of goods sold...
Inventory Management Williams & Sons last year reported sales of $17 million, cost of goods sold (COGS) of $12 and an inventory turnover ratio of 2. The company is now adopting a new inventory system. If the new system is able to reduce the firm's inventory level and increase the firm's inventory turnover ratio to 4 while maintaining the same level of sales and COGS, how much cash will be freed up? Do not round intermediate calculations. Round your answer...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,700,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 486500 $1,000,000 Estimated costs to complete 903,500 0 Billings during the year 455,000 1,245,000 Cash collections during the year 355,000 1,345,000 ) Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,820,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 518,000 $ 1,120,000 Estimated costs to complete 962,000 0 Billings during the year 410,000 1,410,000 Cash collections during the year 310,000 1,510,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,730,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 476,000 $ 1,030,000 Estimated costs to complete 884,000 0 Billings during the year 470,000 1,260,000 Cash collections during the year 370,000 1,360,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,900,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below: 2020 2021 Costs incurred during the year $ 420,000 $ 1,200,000 Estimated costs to complete 980,000 0 Billings during the year 450,000 1,450,000 Cash collections during the year 350,000 1,550,000 Assume that Beavis recognizes revenue on this contract over time according to percentage of completion....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT