Question

In: Accounting

Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows: Project...

Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows:
Project A B
Initial investment $202,575 $251,438
Annual income $43,820 $43,660
Life of project 6 years 9 years
Salvage value $0 $0

Salarian Company uses the straight-line method to depreciate its assets.

(a)

Calculate the internal rate of return for each project. (For calculation purposes, use 4 decimal places as displayed in the factor table provided, e.g. 1.2512. Round answers to 0 decimal places, e.g. 15%.)

Click here to view PV table.
Internal rate of return
Project A %
Project B %
By accessing this Question Assistance, you will learn while you earn points based on the Point Potential Policy set by your instructor.

Solutions

Expert Solution

Correct Answer:

IRR

Project A

8%

Project B

10%

Working:

IRR = R1+( NPV1/(NPV1-NPV2) * (R2-R1)

Project A

Year

Cash Inflows

PVA factor at 5%

Present value

1-6

$ 43,820

$ 5.0757

$     2,22,417

(-) Initial Cost

$     2,02,575

Net Present Value (NPV1) @ 5%

$        19,842

Project A

Year

Cash Inflows

PVA factor at 10.%

Present value

1-6

$ 43,820

$ 4.3553

$ 1,90,849.25

Total

$ 1,90,849.25

(-) Initial Cost

$ 2,02,575.00

Net Present Value (NPV2) @ 10%

$ (11,725.75)

Project A

NPV1

$     19,842.17

NPV2

$   (11,725.75)

NPV1-NPV2

$     31,567.93

NPV1/(NPV1-NPV2)

$                0.63

R1

5.0%

R2

10.0%

R2-R1

5.0%

IRR

8%

Project B

Year

Cash Inflows

PVA factor at 5%

Present value

1-9

$ 43,660

$ 7.1078

$     3,10,327

Total

$     3,10,327

(-) Initial Cost

$     2,51,438

Net Present Value (NPV1) @ 5%

$ 58,889.49

Project B

Year

Cash Inflows

PVA factor at 10%

Present value

1-9

$ 43,660

$ 5.7590

$ 2,51,437.94

Total

$ 2,51,437.94

(-) Initial Cost

$ 2,51,438.00

Net Present Value (NPV2) @ 10%

$               0.06

Project Beta

NPV1

$     58,888.55

NPV2

$              (0.06)

NPV1-NPV2

         58,888.61

NPV1/(NPV1-NPV2)

$         1.00000

R1

5%

R2

10%

R2-R1

5%

IRR

10%

End of Answer.

Thanks


Related Solutions

Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows: Project...
Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows: Project A B Initial investment $215,545 $230,821 Annual income $41,400 $40,080 Life of project 7 years 9 years Salvage value $0 $0 Salarian Company uses the straight-line method to depreciate its assets. (a) Calculate the internal rate of return for each project. (For calculation purposes, use 4 decimal places as displayed in the factor table provided, e.g. 1.2512. Round answers to 0 decimal places, e.g....
Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows: Project...
Salarian Company is considering two capital expenditures. Relevant data for the projects are as follows: Project A B Initial investment $215,545 $230,821 Annual income $41,400 $40,080 Life of project 7 years 9 years Salvage value $0 $0 Salarian Company uses the straight-line method to depreciate its assets. (a) Calculate the internal rate of return for each project. (For calculation purposes, use 4 decimal places as displayed in the factor table provided, e.g. 1.2512. Round answers to 0 decimal places, e.g....
Iggy Company is considering three capital expenditure projects. Relevant data for the projects are as follows....
Iggy Company is considering three capital expenditure projects. Relevant data for the projects are as follows. Project Investment Annual Income Life of Project 22A $240,600 $17,220 6 years 23A 271,400 21,000 9 years 24A 284,100 15,700 7 years Annual income is constant over the life of the project. Each project is expected to have zero salvage value at the end of the project. Iggy Company uses the straight-line method of depreciation. Click here to view the factor table. (a) Determine...
Iggy Company is considering three capital expenditure projects. Relevant data for the projects are as follows....
Iggy Company is considering three capital expenditure projects. Relevant data for the projects are as follows. Project Investment Annual Income Life of Project 22A $240,600 $17,220 6 years 23A 271,400 21,000 9 years 24A 284,100 15,700 7 years Annual income is constant over the life of the project. Each project is expected to have zero salvage value at the end of the project. Iggy Company uses the straight-line method of depreciation. Click here to view the factor table. (a) Determine...
Marigold Company is considering three capital expenditure projects. Relevant data for the projects are as follows....
Marigold Company is considering three capital expenditure projects. Relevant data for the projects are as follows. Project Investment Annual Income Life of Project 22A $243,300 $16,860 6 years 23A 274,200 20,730 9 years 24A 280,500 15,700 7 years Annual income is constant over the life of the project. Each project is expected to have zero salvage value at the end of the project. Marigold Company uses the straight-line method of depreciation. Click here to view PV table. (a) Determine the...
Petram company is considering two alternative capital budgeting projects. Project A is an investment of $300,000...
Petram company is considering two alternative capital budgeting projects. Project A is an investment of $300,000 to renovate office facilities. Project B is an investment of $600,000 to expand diagnostic capabilities. Relevant cash flow data for the two projects over their expected two-year lives are as follows: Year 1 Year 2    Pr.     Cash Flow    Pr.        Cash Flow Project A 0.18 $     0 0.08 $    0 0.64 100,000 0.84 100,000 0.18 200,000 0.08 200,000 Project...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project....
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital...
Jack Engineering is considering two projects, Project Alpha and Project Beta system, in this year's capital budget. The projects are independent. The cash outlay for the Project Alpha is $44,860 and that for the Project Beta is $34,200. The firm's cost of capital is 14%. After-tax cash flows, including depreciation, are as follows: Year Project Alpha Project Beta 1 15,000 10,200 2 15,000 10,200 3 15,000 10,200 4 15,000 10,200 5 15,000 10,200 Required: Calculate the IRR for each project....
Please use Excel functions like PV A company is considering two capital budgeting projects. Each project...
Please use Excel functions like PV A company is considering two capital budgeting projects. Each project requires an initial outlay of $4,000,000. Cash inflows for each project are given in the table below. Each project has a life of 3 years. The company uses the NPV method to evaluate capital budgeting projects and its required rate of return is 9%. Here are the cash inflows from the projects. Project A         Project B         Year 1                                                 $1,900,000            0                Year 2                                                 $1,900,000           ...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT