In: Accounting
A divisional manger, John James, expects to retire in three years. John is paid a fixed salary plus 10 percent of his division’s profits. Make the unrealistic assumption that John cares only about cash compensation. He can spend $200,000 on process improvements this year and that will yield $125,000 of cost savings for each of the following four years.
Use Excel and show all work—use formulas where useful
Required:
1.
Assuming Discounting factor to be 10 % |
Year | Cash Flow | Present Value Factor@10% | Discounted Cash Flows |
1 | 125000 | 0.909 | 113636.3636 |
2 | 125000 | 0.826 | 103305.7851 |
3 | 125000 | 0.751 | 93914.35011 |
4 | 125000 | 0.683 | 85376.68192 |
5 | 0 | 0.621 | 0 |
6 | 0 | 0.564 | 0 |
7 | 0 | 0.513 | 0 |
TOTAL | 4.868 | 396233.18 |
2.
NPV @ 10% | |
Particulars | Amount |
Cash Outflow | |
Cost of improvement | 200000 |
Cash Inflow | |
Note1 | 396233.18 |
Net Present Value | 196233.1808 |
(Inflow - Outflow) | |
As the NPV of the project is positive , james should accept the project.
3. If this project is not accepted company may loose annual savings of 125000 for each of the four years.
4. if project is accepted, cash flows for 4-7 years, for the new manager
Year | Cash Flow | Present Value Factor@10% | Discounted Cash Flows |
4 | 125000 | 0.683 | 85376.68192 |
5 | 0 | 0.621 | 0 |
6 | 0 | 0.564 | 0 |
7 | 0 | 0.513 | 0 |
TOTAL | 2.382 | 85376.68 |
I have explained everything step by step
Go through it once and everything will be cleared.
Hope you understand the concept
Please give positive feedback by giving thumsup
Thankyou