Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...

Required information

Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4

Skip to question

[The following information applies to the questions displayed below.]

Antuan Company set the following standard costs for one unit of its product.

Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00
Direct labor (1.6 hrs. @ $11.00 per hr.) 17.60
Overhead (1.6 hrs. @ $18.50 per hr.) 29.60
Total standard cost $ 67.20


The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month. Following are the company’s budgeted overhead costs per month at the 75% capacity level.

Overhead Budget (75% Capacity)
Variable overhead costs
Indirect materials $ 15,000
Indirect labor 75,000
Power

15,000

Repairs and maintenance 30,000
Total variable overhead costs $ 135,000
Fixed overhead costs
Depreciation—Building 24,000
Depreciation—Machinery 70,000
Taxes and insurance 17,000
Supervision 198,000
Total fixed overhead costs 309,000
Total overhead costs $ 444,000


The company incurred the following actual costs when it operated at 75% of capacity in October.

Direct materials (60,500 Ibs. @ $5.20 per lb.) $ 314,600
Direct labor (23,000 hrs. @ $11.10 per hr.) 255,300
Overhead costs
Indirect materials $ 41,500
Indirect labor 177,000
Power 17,250
Repairs and maintenance 34,500
Depreciation—Building 24,000
Depreciation—Machinery 94,500
Taxes and insurance 15,300
Supervision 198,000 602,050
Total costs $ 1,171,950

rev: 04_27_2020_QC_CS-209738

Problem 21-3A Part 1&2

Required:
1&2. Prepare flexible overhead budgets for October showing the amounts of each variable and fixed cost at the 65%, 75%, and 85% capacity levels and classify all items listed in the fixed budget as variable or fixed.

Solutions

Expert Solution


Related Solutions

Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.6 hrs. @ $11.00 per hr.) 17.60 Overhead (1.6 hrs. @ $18.50 per hr.) 29.60 Total standard cost $ 67.20...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.6 hrs. @ $11.00 per hr.) 17.60 Overhead (1.6 hrs. @ $18.50 per hr.) 29.60 Total standard cost $ 67.20...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, C2 [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (6 Ibs. @ $5 per Ib.) $ 30 Direct labor (2 hrs. @ $17 per hr.) 34 Overhead (2 hrs. @ $18.50 per hr.) 37 Total standard cost $ 101 The predetermined overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $14.00 per hr.) 25.20 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 78.50 The predetermined overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $13.00 per hr.) 23.40 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 76.70...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, C2 [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (6 Ibs. @ $5 per Ib.) $ 30 Direct labor (2 hrs. @ $17 per hr.) 34 Overhead (2 hrs. @ $18.50 per hr.) 37 Total standard cost $ 101 The predetermined overhead...
Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report...
Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, C2 [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (6 Ibs. @ $5 per Ib.) $ 30 Direct labor (2 hrs. @ $17 per hr.) 34 Overhead (2 hrs. @ $18.50 per hr.) 37 Total standard cost $ 101 The predetermined overhead rate ($18.50...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $13.00 per hr.) 23.40 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 76.70 The predetermined...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $13.00 per hr.) 23.40 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 76.70 The predetermined...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report...
Problem 08-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.8 hrs. @ $13.00 per hr.) 23.40 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 76.70 The predetermined...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT