In: Economics
The capital fund for the new investment at Systems Corporation is limited to $75,000 for next year. You have been asked to recommend one or more of three projects as economically acceptable for investment at the corporate MARR of 10% per year. What is the PW value of the project that should be selected?
Project |
Initial Investment,$ |
Annual NCF,$ per year |
Life in years |
Salvage Value$ |
A |
-25000 |
6000 |
4 |
4000 |
B |
-30000 |
9000 |
4 |
-1000 |
C |
-50000 |
15000 |
4 |
20000 |
ANSWER:
A) Present worth of project a = initial investment + annual cash flow(P/A,I,N) + salvage value(P/F,I,N)
where i = 10% and n = 4 years
pw of project a = -25,000 + 6,000(P/A,10%,4) + 4000(P/F,10%,4)
pw of project a = -25,000 + 6,000 * 3.17 + 4,000 * .683
pw of project a = -25,000 + 19,020 + 2732 = -25,000 + 21,752 = -3,248
B) Present worth of project b = initial investment + annual cash flow(P/A,I,N) + salvage value(P/F,I,N)
where i = 10% and n = 4 years
pw of project b = -30,000 + 9,000(P/A,10%,4) - 1000(P/F,10%,4)
pw of project b = -30,000 + 9,000 * 3.17 - 1,000 * .683
pw of project b = -30,000 + 28,530 -683 = -30,683 + 28,530 = -2,153
C) Present worth of project a = initial investment + annual cash flow(P/A,I,N) + salvage value(P/F,I,N)
where i = 10% and n = 4 years
pw of project c = -50,000 + 15,000(P/A,10%,4) + 20,000(P/F,10%,4)
pw of project c = -50,000 + 15,000 * 3.17 + 20,000 * .683
pw of project c = -50,000 + 47,550 + 13,660 = -50,000 + 61,210 = 11,210
The pw of the project that should be selected is $11,210 and the project that should be selected is project c.