In: Finance
Answer in a of 150 words or more. If there is a 10% cost overrun, what happens to the NPV and IRR? If sales are 10% higher than your original estimate, what happens to the NPV and IRR?
If there is 10% cost overrun, this will reduce operational cashflow. Considering other NWC and capital spending requirement same, if cashflows are reduced, hence, NOV will be reduced and IIR will also be reduced.
For 10% extra of sales revenue , cashflow will be increased and hence, NPV and IRR will also be increased.
To prove the above point let look at cashflow at normal scenario:
Base Case | ||||||||
Year0 | Year1 | Year2 | Year3 | Year4 | Year5 | Year6 | Year7 | |
Revenue | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | |
Operational Cost | $ 1,25,000.00 | $ 1,25,000.00 | $ 1,25,000.00 | $ 1,25,000.00 | $ 1,25,000.00 | $ 1,25,000.00 | $ 1,25,000.00 | |
Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
EBT | $ 1,64,282.50 | $ 1,56,632.50 | $ 1,61,882.50 | $ 1,65,632.50 | $ 1,68,302.50 | $ 1,68,310.00 | $ 1,68,302.50 | |
Tax @ 35% | $ 57,498.88 | $ 54,821.38 | $ 56,658.88 | $ 57,971.38 | $ 58,905.88 | $ 58,908.50 | $ 58,905.88 | |
Operational Cashflow | ||||||||
EBIT/EBT | $ 1,64,282.50 | $ 1,56,632.50 | $ 1,61,882.50 | $ 1,65,632.50 | $ 1,68,302.50 | $ 1,68,310.00 | $ 1,68,302.50 | |
+Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
-Tax | $ 57,498.88 | $ 54,821.38 | $ 56,658.88 | $ 57,971.38 | $ 58,905.88 | $ 58,908.50 | $ 58,905.88 | |
Total OCF | $ - | $ 2,32,498.88 | $ 2,29,821.38 | $ 2,31,658.88 | $ 2,32,971.38 | $ 2,33,905.88 | $ 2,33,908.50 | $ 2,33,905.88 |
Capital Spending | ||||||||
Initial Outlay | $ -7,50,000.00 | |||||||
Salvage | $ - | |||||||
Total Project Cashflow | $ -7,50,000.00 | $ 2,32,498.88 | $ 2,29,821.38 | $ 2,31,658.88 | $ 2,32,971.38 | $ 2,33,905.88 | $ 2,33,908.50 | $ 2,33,905.88 |
Cost of Capital | 12% | |||||||
NPV | 310785.15 | |||||||
IRR | 24% |
Now, there is cost overrun of of 10 % and NPV and IRR wil be lower than normal case:
Cost Overrun 10% | ||||||||
Year0 | Year1 | Year2 | Year3 | Year4 | Year5 | Year6 | Year7 | |
Revenue | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | $ 3,00,000.00 | |
Operational Cost | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | |
Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
EBT | $ 1,51,782.50 | $ 1,44,132.50 | $ 1,49,382.50 | $ 1,53,132.50 | $ 1,55,802.50 | $ 1,55,810.00 | $ 1,55,802.50 | |
Tax @ 35% | $ 53,123.88 | $ 50,446.38 | $ 52,283.88 | $ 53,596.38 | $ 54,530.88 | $ 54,533.50 | $ 54,530.88 | |
Operational Cashflow | ||||||||
EBIT/EBT | $ 1,51,782.50 | $ 1,44,132.50 | $ 1,49,382.50 | $ 1,53,132.50 | $ 1,55,802.50 | $ 1,55,810.00 | $ 1,55,802.50 | |
+Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
-Tax | $ 53,123.88 | $ 50,446.38 | $ 52,283.88 | $ 53,596.38 | $ 54,530.88 | $ 54,533.50 | $ 54,530.88 | |
Total OCF | $ - | $ 2,15,623.88 | $ 2,12,946.38 | $ 2,14,783.88 | $ 2,16,096.38 | $ 2,17,030.88 | $ 2,17,033.50 | $ 2,17,030.88 |
Capital Spending | ||||||||
Initial Outlay | $ -7,50,000.00 | |||||||
Salvage | $ - | |||||||
Total Project Cashflow | $ -7,50,000.00 | $ 2,15,623.88 | $ 2,12,946.38 | $ 2,14,783.88 | $ 2,16,096.38 | $ 2,17,030.88 | $ 2,17,033.50 | $ 2,17,030.88 |
Cost of Capital | 12% | |||||||
NPV | 233771.75 | |||||||
IRR | 21% |
Now we are analysing the same with 10 % extra revenue and both NPV and IRR will go up:
Revenue increased by 10 % | ||||||||
Year0 | Year1 | Year2 | Year3 | Year4 | Year5 | Year6 | Year7 | |
Revenue | $ 3,30,000.00 | $ 3,30,000.00 | $ 3,30,000.00 | $ 3,30,000.00 | $ 3,30,000.00 | $ 3,30,000.00 | $ 3,30,000.00 | |
Operational Cost | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | $ 1,37,500.00 | |
Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
EBT | $ 1,81,782.50 | $ 1,74,132.50 | $ 1,79,382.50 | $ 1,83,132.50 | $ 1,85,802.50 | $ 1,85,810.00 | $ 1,85,802.50 | |
Tax @ 35% | $ 63,623.88 | $ 60,946.38 | $ 62,783.88 | $ 64,096.38 | $ 65,030.88 | $ 65,033.50 | $ 65,030.88 | |
Operational Cashflow | ||||||||
EBIT/EBT | $ 1,81,782.50 | $ 1,74,132.50 | $ 1,79,382.50 | $ 1,83,132.50 | $ 1,85,802.50 | $ 1,85,810.00 | $ 1,85,802.50 | |
+Depriciation | $ 10,717.50 | $ 18,367.50 | $ 13,117.50 | $ 9,367.50 | $ 6,697.50 | $ 6,690.00 | $ 6,697.50 | |
-Tax | $ 63,623.88 | $ 60,946.38 | $ 62,783.88 | $ 64,096.38 | $ 65,030.88 | $ 65,033.50 | $ 65,030.88 | |
Total OCF | $ - | $ 2,56,123.88 | $ 2,53,446.38 | $ 2,55,283.88 | $ 2,56,596.38 | $ 2,57,530.88 | $ 2,57,533.50 | $ 2,57,530.88 |
Capital Spending | ||||||||
Initial Outlay | $ -7,50,000.00 | |||||||
Salvage | $ - | |||||||
Total Project Cashflow | $ -7,50,000.00 | $ 2,56,123.88 | $ 2,53,446.38 | $ 2,55,283.88 | $ 2,56,596.38 | $ 2,57,530.88 | $ 2,57,533.50 | $ 2,57,530.88 |
Cost of Capital | 12% | |||||||
NPV | 418603.89 | |||||||
IRR | 28% |
(Note : These figures are fictitious used for example purpose only - any other data will work)