Question

In: Finance

Markman & Sons is considering Projects S and L. These projects are mutually exclusive, equally risky,...

Markman & Sons is considering Projects S and L. These projects are mutually exclusive, equally risky, and not repeatable and their cash flows are shown below. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the project with the higher IRR will also have the higher NPV, i.e., no conflict will exist.
NO EXCEL

r:

10.00%

Year

0

1

2

3

4

CFS

?$1,025

$650

$450

$250

  $50

CFL

?$1,025

$100

$300

$500

$700

Solutions

Expert Solution

For project S , NPV = 650/1.1+450/1.1^2+250/1.1^3+50/1.1^4 - 1025/1.1^0 = 159.79;

For project L, NPV = 100/1.1+300/1.21+500/1.331+700/1.4641-1025/1.1^0 = 167.61

Now let us calculate the Intermal Rate of Return (IRR) of project L. IRR = R1 + NPV1(R2-R1)/NPV1-NPV2

Let R1 =6% , R2 = 14%; NPV1 = 100/1.06 + 300/1.1236+500/1.191016+700/1.26247696 - 1025 = 286.34.

Hence NPV1=286.34 ; NPV2 = 100/1.14+300/1.2996+500/1.481544+700/1.68896016 -1025 = 45.51

Hence NPV2 = 45.51 Hence, IRR = 0.06+ 286.34*(0.14-0.06)/286.34-45.51 = 15.51%

Therefore, IRR for project L = 15.51%.

Let us now consider project S; Here NPV1 = 650/1.06 + 450/1.1236+250/1.191016+50/1.26247696 - 1025

= 613.21+400.5+209.9+39.6-1025= 238.21 = NPV1 ; NPV2 = 650/1.14+450/1.2996+250/1.481544+50/1.68896016 -1025 = 570.18+346.26+168.74+29.6-1025=89.78=NPV2 ; IRR of project S = 0.06 + 238.21(0.08)/148.43 = 18.84%

Hence PROJECT S has higher IRR OF 18.84% . At IRR rate NPV = 0. AT 10% rate of return NPV of project was = 159.79. Therefore 159.79 value will be foregone if project with higher IRR is considered.


Related Solutions

Current Design Co. is considering two mutually exclusive, equally risky, and not repeatable projects, S and...
Current Design Co. is considering two mutually exclusive, equally risky, and not repeatable projects, S and L. Their cash flows are shown below. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? The required...
. Douglas Controls, Inc. is considering two mutually exclusive, equally risky, and not repeatable projects, S...
. Douglas Controls, Inc. is considering two mutually exclusive, equally risky, and not repeatable projects, S and L. Their cash flows are shown below. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’...
ABC Company is considering investing in two mutually exclusive projects, L and S. The two projects’ forecasted cash flows are shown as below. WACC is 10%. Year 0 1 2 3 4 Project L CF ($) -1,000    700 500 200 0 Project S CF ($) -1,200 100 300 800 1,000 a. Calculate the NPVs for both projects. b. Calculate the IRRs for both projects. c. Calculate the Discounted Paybacks for both projects. [Draw a timeline] d. Based on your...
Douglas controls, Inc. is considering tow mutually exclusive, equallly risky, and not repeatable projects, S and...
Douglas controls, Inc. is considering tow mutually exclusive, equallly risky, and not repeatable projects, S and L. Thier cash flows are shown below. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note that...
Your company is choosing between the following non-repeatable, equally risky, mutually exclusive projects with the cash...
Your company is choosing between the following non-repeatable, equally risky, mutually exclusive projects with the cash flows shown below. Your cost of capital is 10 percent. How much value will your firm sacrifice if it selects the project with the higher IRR? k = 10% Project S: 0 1 2 3 | | | | -1,000 500 500 500 k = 10% Project L: 0 1 2 3 4 5 | | | | | | -2,000 668.76 668.76 668.76...
Consider project S and L, and their projected cashflows. Both projects are equally risky. (Assume cost...
Consider project S and L, and their projected cashflows. Both projects are equally risky. (Assume cost of capital is 10%) Expected after-tax cash flows Expected after-tax cash flows Year(t) Project S Project L 0(today) ($1,000) ($1,000) 1 500 100 2 400 300 3 300 400 4 100 600 Required; Find the NPV of each of the projects. Calculate the B/C ratio In each case state if we should accept the project or not and explain your answer.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.52 $260 $15 $10 Project L -$1,000 $0 $250 $380 $811.10 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR and NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $882.76 $260 $5 $5 Project L -$1,000 $0 $250 $400 $775.11 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $885.37 $250 $15 $15 Project L -$1,000 $5 $240 $380 $844.53 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the...
IRR AND NPV A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $896.53 $250 $5 $5 Project L -$1,000 $10 $260 $380 $821.65 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT