| As you might imagine the ABC Tank Manufacturing Company uses an activity-based costing system. ABC has given you the following data that is used in its activity-based costing system: |
| Overhead Costs | |||
| Wages and salaries | $ | 347,000 | |
| Other overhead costs | 197,000 | ||
| Total overhead costs | $ | 544,000 | |
| Activity Cost Pool | Activity Measure | Total Activity | |
| Direct labor support | Number of direct labor-hours | 14,000 | DLHs |
| Order processing | Number of orders | 480 | orders |
| Customer support | Number of customers | 105 | customers |
| Other | This is an organization-sustaining activity | Not applicable | |
|
Distribution of Resource Consumption Across Activities |
||||||||||
| Direct Labor Support | Order Processing | Customer Support | Other | Total | ||||||
| Wages and salaries | 10 | % | 30 | % | 15 | % | 45 | % | 100 | % |
| Other overhead costs | 25 | % | 10 | % | 20 | % | 45 | % | 100 | % |
|
Early in this year, ABC Tank completed an order for a special vertical envelopment tank for a new customer, Sky Tanks. This was the only order from this customer for the whole year. Below is some data concerning that order: |
| Data Concerning the Sky Tank Order | |||
| Selling price | $ | 290 | per unit |
| Units ordered | 100 | units | |
| Direct materials | $ | 267 | per unit |
| Direct labor-hours | 0.6 | DLH per unit | |
| Direct labor rate | $ | 21 | per DLH |
| Required: | |
| 1. |
Prepare a report showing the first-stage allocations of overhead costs to the activity cost pools. |
|
2. |
Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places.) |
| 3. |
Compute the overhead costs for the order from Sky Tank, including customer support costs. (Round your intermediate calculations and final answers to 2 decimal places.) |
| 4. |
Prepare a report showing the customer margin for Sky Tank. |
| Answer 1 | ||||||||||
| A report showing the first-stage allocations of overhead costs to the activity cost pools. | ||||||||||
| Activity Cost Pools | ||||||||||
| Total Cost | Direct Labor Support | Order Processing | Customer Support | Other | ||||||
| Wages and salaries | $347,000.00 | $34,700.00 | $104,100.00 | $52,050.00 | $156,150.00 | |||||
| Other overhead cost | $197,000.00 | $49,250.00 | $19,700.00 | $39,400.00 | $88,650.00 | |||||
| Allocated Overhead cost | $83,950.00 | $123,800.00 | $91,450.00 | $244,800.00 | ||||||
| Answer 2 | ||||||||||
| Compute the activity rates for the activity cost pools. | ||||||||||
| Activity rate for Direct Labor support = Allocated Overhead cost / Number of direct labor hours = $83,950 / 14000 DLHs = $6 per direct labor hour | ||||||||||
| Activity rate for Order Processing = Allocated Overhead cost / Number of orders = $123,800 / 480 orders = $257.92 per order | ||||||||||
| Activity rate for Customer Support= Allocated Overhead cost / Number of customers = $91,450 / 105 customers = $870.95 per customer | ||||||||||
| Answer 3 | ||||||||||
| Compute the overhead costs for the order from Sky Tank, including customer support costs. | ||||||||||
| Overhead Cost | ||||||||||
| Direct Labor support [100 units x 0.6 DLH per unit x $6] | $360.00 | |||||||||
| Order Processing [1 order x $257.92] | $257.92 | |||||||||
| Customer Support [1 customer x $870.95] | $870.95 | |||||||||
| Overhead costs for the order from Sky Tank | $1,488.87 | |||||||||
| Answer 4 | ||||||||||
| A report showing the customer margin for Sky Tank. | ||||||||||
| Sales [100 units x $290 per unit] | $29,000.00 | |||||||||
| Less : Costs | ||||||||||
| - Direct Materials [100 units x $267 per unit] | $26,700.00 | |||||||||
| - Direct Labor cost [100 units x 0.6 DLH x $21] | $1,260.00 | |||||||||
| - Overhead cost | $1,488.87 | |||||||||
| Customer Margin | -$448.87 | |||||||||