In: Accounting
As you might imagine the ABC Tank Manufacturing Company uses an activity-based costing system. ABC has given you the following data that is used in its activity-based costing system: |
Overhead Costs | |||
Wages and salaries | $ | 347,000 | |
Other overhead costs | 197,000 | ||
Total overhead costs | $ | 544,000 | |
Activity Cost Pool | Activity Measure | Total Activity | |
Direct labor support | Number of direct labor-hours | 14,000 | DLHs |
Order processing | Number of orders | 480 | orders |
Customer support | Number of customers | 105 | customers |
Other | This is an organization-sustaining activity | Not applicable | |
Distribution of Resource Consumption Across Activities |
||||||||||
Direct Labor Support | Order Processing | Customer Support | Other | Total | ||||||
Wages and salaries | 10 | % | 30 | % | 15 | % | 45 | % | 100 | % |
Other overhead costs | 25 | % | 10 | % | 20 | % | 45 | % | 100 | % |
Early in this year, ABC Tank completed an order for a special vertical envelopment tank for a new customer, Sky Tanks. This was the only order from this customer for the whole year. Below is some data concerning that order: |
Data Concerning the Sky Tank Order | |||
Selling price | $ | 290 | per unit |
Units ordered | 100 | units | |
Direct materials | $ | 267 | per unit |
Direct labor-hours | 0.6 | DLH per unit | |
Direct labor rate | $ | 21 | per DLH |
Required: | |
1. |
Prepare a report showing the first-stage allocations of overhead costs to the activity cost pools. |
2. |
Compute the activity rates for the activity cost pools. (Round your answers to 2 decimal places.) |
3. |
Compute the overhead costs for the order from Sky Tank, including customer support costs. (Round your intermediate calculations and final answers to 2 decimal places.) |
4. |
Prepare a report showing the customer margin for Sky Tank. |
Answer 1 | ||||||||||
A report showing the first-stage allocations of overhead costs to the activity cost pools. | ||||||||||
Activity Cost Pools | ||||||||||
Total Cost | Direct Labor Support | Order Processing | Customer Support | Other | ||||||
Wages and salaries | $347,000.00 | $34,700.00 | $104,100.00 | $52,050.00 | $156,150.00 | |||||
Other overhead cost | $197,000.00 | $49,250.00 | $19,700.00 | $39,400.00 | $88,650.00 | |||||
Allocated Overhead cost | $83,950.00 | $123,800.00 | $91,450.00 | $244,800.00 | ||||||
Answer 2 | ||||||||||
Compute the activity rates for the activity cost pools. | ||||||||||
Activity rate for Direct Labor support = Allocated Overhead cost / Number of direct labor hours = $83,950 / 14000 DLHs = $6 per direct labor hour | ||||||||||
Activity rate for Order Processing = Allocated Overhead cost / Number of orders = $123,800 / 480 orders = $257.92 per order | ||||||||||
Activity rate for Customer Support= Allocated Overhead cost / Number of customers = $91,450 / 105 customers = $870.95 per customer | ||||||||||
Answer 3 | ||||||||||
Compute the overhead costs for the order from Sky Tank, including customer support costs. | ||||||||||
Overhead Cost | ||||||||||
Direct Labor support [100 units x 0.6 DLH per unit x $6] | $360.00 | |||||||||
Order Processing [1 order x $257.92] | $257.92 | |||||||||
Customer Support [1 customer x $870.95] | $870.95 | |||||||||
Overhead costs for the order from Sky Tank | $1,488.87 | |||||||||
Answer 4 | ||||||||||
A report showing the customer margin for Sky Tank. | ||||||||||
Sales [100 units x $290 per unit] | $29,000.00 | |||||||||
Less : Costs | ||||||||||
- Direct Materials [100 units x $267 per unit] | $26,700.00 | |||||||||
- Direct Labor cost [100 units x 0.6 DLH x $21] | $1,260.00 | |||||||||
- Overhead cost | $1,488.87 | |||||||||
Customer Margin | -$448.87 | |||||||||