Question

In: Accounting

Q 18 Rice Processors Plc uses a standard costing system. Fixed production overhead is absorbed on...

Q 18

Rice Processors Plc uses a standard costing system. Fixed production overhead is absorbed on the basis of direct labour hours. The following data relate to a particular period of operation

Standard price of material/kg                                             GHS5.90

Actual material issued to production                                 4,110kg

Standard labour hours                                                      1,680

Actual direct labour hours                                                 1,760

Actual fixed overhead                                                      GHS5,620

The following variance were calculated at the end of the period

                                                                                         GHS

Direct material cost                                                    702(A)

Direct material usage                                                 531(F)

Direct labour efficiency                                             336(A)

Direct labour cost                                                        16 (F)

Fixed overhead cost                                                    92(F)

Required

  1. Calculate:

i standard quantity of materials

ii actual price of materials per kg

iii standard direct labour rate

iv actual direct labour rate

  1. State two benefits to be obtained from the installation of a standard costing system

Solutions

Expert Solution

i) Direct Material Usage Variance = (Standard Usage - Actual Usage) x Standard Price
$     531.00 = (SU - 4110) x $ 5.90
$        90.00 = SU - 4110
SU = 4200
ii) Direct Material Price Variance = (Standard Price - Actual Price) x Actual Usage
$ -1,233.00 = ($ 5.90 - AP) x 4110
$        -0.30 = $ 5.90 - AP
AP = $      6.20
Workings:
Direct Material Cost Variance = Direct Material Price Variance + Direct Material Usage Variance
$    -702.00 = Direct Material Price Variance + 531
$ -1,233.00 = Direct Material Price Variance
iii) Direct Labor Cost Variance = Direct Labor Rate Variance + Direct Labor Efficiency Variance
$    16.00 = Direct Labor Rate Variance + (- 336)
$ 352.00 = Direct Labor Rate Variance
Direct Labor Efficiency Variance = (Standard Hours - Actual Hours) x Standard Rate
$ -336.00 = (1680 - 1760) x Standard Rate
$ -336.00 = -80 x Standard Rate
$       4.20 = Standard Rate
iv) Direct Labor Rate Variance = (Standard Rate - Actual Rate) x Actual Hours
$ 350.00 = ($ 4.20 - AR) x 1760
$       0.20 = $ 4.20 - AR
AR = $      4.00

Related Solutions

Vermeillen Corporation uses a standard costing system in which variable manufacturing overhead is assigned to production...
Vermeillen Corporation uses a standard costing system in which variable manufacturing overhead is assigned to production on the basis of the number of machine setups. The following data pertain to one month's operations: Variable manufacturing overhead cost incurred: $70,000 Total variable manufacturing overhead variance: $4,550 Favorable Standard machine setups allowed for actual production: 3,550 Actual machine setups incurred: 3,500 The standard variable overhead rate per machine setup is: Multiple Choice $18.44 $21.30 $21.00 $20.00
Brookster Inc. used a standard costing system for its production process. Fixed overhead is allocated based...
Brookster Inc. used a standard costing system for its production process. Fixed overhead is allocated based on machine hours. Budgeted fixed overhead for the month was $16,910 for budgeted capacity of 8,900 machine hours. Actual fixed overhead was $17,500 for 1,800 units of output. The standard time allowed was 5 machine hours per unit of output. Required: (a) Compute SQ in total: (b) Compute the Standard Price for fixed overhead: (c) Compute the Fixed Overhead Spending Variance and Fixed Overhead...
ECO Plc Ltd. uses an activity based costing system to assign overhead costs to products. In...
ECO Plc Ltd. uses an activity based costing system to assign overhead costs to products. In the first stage, two overhead costs - Electricity expense and Water expense - are allocated to three activity cost pools - Grinding, Painting, and Other - based on resource consumption. Data to perform these allocations appear below: Overhead Costs: Electricity expense: $195,000 Water expense: $185,000 Distribution of Resource Consumption across Activity Cost Pools: Overhead Cost Activity Cost Pools Grinding Painting Other Electricity expense 0.40...
uses a standard cost accounting system and applies production overhead to products on the basis of...
uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.20 Standard fixed-overhead rate per hour: $12.20 Planned activity during the period: 17,000 machine hours Actual production: 11,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $156,110 Actual total overhead: $445,030 Actual machine hours worked: 23,300 Required: 1. Calculate the budgeted fixed...
Melton Products uses standard costing. It allocates manufacutring overhead (both variable and fixed) to products on...
Melton Products uses standard costing. It allocates manufacutring overhead (both variable and fixed) to products on the basis of standard direct manufacturing labor hours (DLH). Melton develops its manufacturing overbead rate from teh current annual budget. THe manufacturing overhead budget for 2018 is based on budgeted output of 720,000 units requiring 3,600,000 DLH. The company is able to schedule production uniformly throughout the year. A total of 66,000 output unuits requiring 315,000 DLH was produced during May 2018. Budgeted hours...
Garcia Manufacturing uses a job order costing system and applies overhead to production on the basis...
Garcia Manufacturing uses a job order costing system and applies overhead to production on the basis of direct labour hours. In 2013, costs and production data were estimated to remain the same as 2012 with total manufacturing overhead costs estimated to be $1,050,000, direct labour costs estimated to be $35 an hour, and direct labour hours to be 20,000. On January 1, 2013, Job No. 50 was the only job in process. The production data incurred prior to January 1...
Garcia Manufacturing uses a job order costing system and applies overhead to production on the basis...
Garcia Manufacturing uses a job order costing system and applies overhead to production on the basis of direct labour hours. In 2013, costs and production data were estimated to remain the same as 2012 with total manufacturing overhead costs estimated to be $1,050,000, direct labour costs estimated to be $35 an hour, and direct labour hours to be 20,000. On January 1, 2013, Job No. 50 was the only job in process. The production data incurred prior to January 1...
PROBLEM ONE The Kitty Manufacturing Company uses a standard absorption costing job costing system. Manufacturing overhead...
PROBLEM ONE The Kitty Manufacturing Company uses a standard absorption costing job costing system. Manufacturing overhead is allocated to products on the basis of standard direct labor hours. At the beginning of 20xx, Kitty adopted the following standards for its manufacturing costs: Direct materials           3 lb. @ $5 per lb. Direct labor                 5 hr @ $10 per hour Overhead: Variable           $5 per direct labor hour Fixed               $10 per direct labor hour The denominator level for total...
Happy Valley Pet Products uses a standard costing system thatapplies overhead to products based on...
Happy Valley Pet Products uses a standard costing system that applies overhead to products based on standard direct labour-hours allowed for actual output of the period. During the recent year, the following data were collected:Total budgeted fixed overhead cost for the year $ 40,000Actual fixed overhead cost for the year $ 38,000Budgeted standard direct labour-hours 10,000Actual direct labour-hours 12,000Standard direct labour-hours allowed for the actual output 9,000Required:1. Compute the fixed portion of the predetermined overhead rate for the year.2. Compute...
Haughton Company uses a job costing system for its production costs and a predetermined factory overhead...
Haughton Company uses a job costing system for its production costs and a predetermined factory overhead rate based on direct labor costs to apply factory overhead to all jobs. During the month of July, the firm processed three jobs: X13, X14, and X15, of which X13 was started in June. Account July 1 July 31 Iventories Direct Materials 38,300 ? Work - In - Process 44600 ? Finished Goods 0 0 COGS ? Direct Materials Purchased in July 73,000 Materials...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT