In: Finance
You are considering a project that will supply an automobile production facility with 35,000 tonnes of machine screws annually for five years. To get the project started, you will need an initial investment of $1,500,000 in threading equipment. The project will last for five years. The accounting department estimates that annual fixed costs will be $300,000 and that variable costs should be $200 per tonne. The CCA rate for threading equipment is 20%. Accounting estimates a salvage value of $500,000 after costs of dismantling. The marketing department estimates that the auto makers will accept the contract at a selling price of $250 per tonne. The engineering department estimates you will need an initial net working capital investment of $450,000. You require a 15% return and face a marginal tax rate of 38% on this project.
a. What is the NPV for this project? Should you pursue this project?
b. Suppose you believe that the accounting department’s initial cost and salvage projections are accurate only to within ±15%; the marketing department’s price estimate is accurate only to within ±10%; and the engineering department’s net working capital estimate is accurate only to within ±5%. What is your worst-case scenario for this project? Your best-case scenario?
a) The Free Cashflow calculation is as given below
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Production Qty | 35000 | 35000 | 35000 | 35000 | 35000 | |
Selling Price | 250 | 250 | 250 | 250 | 250 | |
Variable Cost | 200 | 200 | 200 | 200 | 200 | |
Revenue | 8750000 | 8750000 | 8750000 | 8750000 | 8750000 | |
Total Variable cost | 7000000 | 7000000 | 7000000 | 7000000 | 7000000 | |
Total Fixed Cost | 300000 | 300000 | 300000 | 300000 | 300000 | |
Depreciation | 300000 | 240000 | 192000 | 153600 | 122880 | |
Profit Before Tax | 1150000 | 1210000 | 1258000 | 1296400 | 1327120 | |
Less Tax | 437000 | 459800 | 478040 | 492632 | 504305.6 | |
PAT | 713000 | 750200 | 779960 | 803768 | 822814.4 | |
Add: Depreciation | 300000 | 240000 | 192000 | 153600 | 122880 | |
Cost | 1500000 | |||||
After tax Salvage value | 496777.6 | |||||
NWC | 450000 | 450000 | ||||
Free Cashflows | -1950000 | 1013000 | 990200 | 971960 | 957368 | 1892472 |
NPV = -1950000 + 1013000/1.15 +990200/1.15^2+971960/1.15^3+957368/1.15^4+1892472/1.15^5
=$1806953.81
As the NPV is positive , the project should be pursued
b) The worst case scenario will ocur when Initial cost is on higher side and salvage value is on lower side, price is on the lower side and NWC is on the higher side
So , in the worst case scenario
Initial Cost = $1500000*1.15 = $1725000
Salvage value = $500000 * 0.85 = $425000
Price per unit = $250 *0.9 = $225
NWC = $450000*1.05 =$472500
Similarly, the best case scenario will ocur when Initial cost is on lower side and salvage value is on higher side, price is on the higher side and NWC is on the lower side
So , in the Best case scenario
Initial Cost = $1500000*0.85 = $1275000
Salvage value = $500000 * 0.1.15 = $575000
Price per unit = $250 *1.1 = $2725
NWC = $450000*0.95 =$427500
Other variables remaining the same