In: Accounting
35) The following aging information pertains to Jacobsen Co.'s accounts receivable at December 31, 2021:
Days Outstanding |
Amount |
Estimated % Uncollectible |
|||||||||||
0-30 |
$ |
420,000 |
2 |
% |
|||||||||
31-60 |
140,000 |
5 |
% |
||||||||||
61-120 |
100,000 |
10 |
% |
||||||||||
Over 120 |
120,000 |
20 |
% |
||||||||||
During 2021, Jacobsen wrote off $18,000 in receivables and recovered $6,000 that had been written off in prior years. Jacobsen's December 31, 2020, allowance for uncollectible accounts was $40,000. Using the balance sheet approach, what amount of allowance for uncollectible accounts should Jacobsen report at December 31, 2021?
A) $55,400.
B) $28,000.
C) $49,400.
D) $31,400.
Problem 1
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2020 and completed in 2021. Cost and other data are presented below:
2020 2021
Costs incurred during the year $ 450,000 $1,100,000
Estimated costs to complete 1,050,000 0
Billings during the year 400,000 1,400,000
Cash collections during the year 300,000 1,500,000
Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.
Required:
1. Prepare all journal entries to record costs, billings, collections, and profit recognition for
2020
2. Prepare all journal entries to record costs, billings, collections, profit recognition and
completion of the project for 2021
Solution:
35)
Days outstanding | Amount | Estimated % Uncollectible | Estimated amount uncollectible |
0-30 | $420,000 | 2% | $8,400 |
31-60 | $140,000 | 5% | $7,000 |
61-120 | $100,000 | 10% | $10,000 |
120+ | $120,000 | 20% | $24,000 |
Total | $494,000 |
Therefore the correct option is C: $49,400
Problem 1:
1)
2020 | |||
Date | Account title | Debit | credit |
2020 | Construction work in process | $450,000 | |
cash | $450,000 | ||
2020 | Accounts receivable | $400,000 | |
Billings on construction contract | $400,000 | ||
2020 | Cash | $300,000 | |
Account receivable | $300,000 | ||
2020 | Construction work in process | $90,000 | |
Construction expense | $450,000 | ||
Construction revenue | $540,000 |
2)
2021 | |||
Date | Account title | Debit | credit |
2021 | Construction work in process | $1,100,000 | |
cash | $1,100,000 | ||
2021 | Accounts receivable | $1,400,000 | |
Billings on construction contract | $1,400,000 | ||
2021 | Construction work in process | $160,000 | |
Construction expense | $1,100,000 | ||
Construction revenue ($1,800,000 -$540,000) | $1,260,000 | ||
2021 | Billing on construction contract | $1,800,000 | |
Construction work in process | $1,800,000 |
Working:
Percentage of work completed for 2020 = Expenditures Incurred from Inception to Date / Total Estimated Costs for the Contract
Total Estimated Costs for the Contract=$450,000+$1,050,000
=$1,500,000
Percentage of work completed for 2020 =$450,000/$1,500,000
=30%
Revenue recognized for 2020 = Total Contract price * percentage of completion
=$1,800,000*30%
=$540,000
Please give a Thumbs up ?. Thanks!!