In: Accounting
Bluefield has decided to use an ABC costing system and has identified the following detailed information about its cost pools and cost drivers: Activity cost pools Materials handling $56,000 Machine maintenance $17,640 Cost drivers Number of material moves 500 Number of machine hours 42,000 Required: 1. Calculate Bluefield’s activity rate for each cost pool. 2. Determine the amount of overhead assigned to Bluefield’s products if each has the following activity demands: Product A Product B Number of material moves 290 210 Number of machine hours 17,200 24,800
Calculate Bluefield’s activity rate for each cost pool. (Round your final answer for per material moves to nearest dollar amount and per machine hour to 4 decimal places.)
|
Determine the amount of overhead assigned to Bluefield’s products if each has the following activity demands: (Round intermediate calculations to 4 decimal places and your final answers to 2 decimal places.)
| Product A | Product B | ||
| Number of material moves | 290 | 210 | |
| Number of machine hours | 17,200 | 24,800 | |
Show less
|
3.
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows:
| Activity Cost Pools | Total Cost of Pool | Cost Driver | Estimated Cost Driver | ||
| Machining | $ | 195,920 | Number of machine hours | 63,200 | |
| Designing costs | 50,400 | Number of design hours | 6,000 | ||
| Setup costs | 69,776 | Number of batches | 490 | ||
Required:
1. Compute the activity rate for each activity.
2. Classify each activity as facility, product, batch, or unit level.
Compute the activity rate for each activity. (Round your answers to 2 decimal places.)
|
Classify each activity as facility, product, batch, or unit level.
|
| Bluefield | ||||||
| Activity cost pool | Cost | Cost drivers | Cost drivers units | Activity rate for each cost pool | ||
| Material handling | 56000 | Number of material moves | 500 | 112 | per Material Move | |
| Machine Maintenance | 17640 | Number of machine hours | 42000 | 0.42 | per Machine Hour | |
| 73640 | ||||||
| Cost drivers | Product A | Product A | Activity rate for each cost pool | Overhead cost A | Overhead cost B | |
| Number of material moves | 290 | 210 | 112 | 32480 | 23520 | |
| Number of machine hours | 17200 | 24800 | 0.42 | 7224 | 10416 | |
| 39704 | 33936 | |||||
| Gable Company | ||||||
| Activity Cost Pools | Total Cost of Pool | Cost Driver | Estimated Cost Driver | Activity rate for each activity | ||
| Machining | 1,95,920 | Number of machine hours | 63,200 | 3.1 | per Machine Hour | |
| Designing costs | 50,400 | Number of design hours | 6,000 | 8.4 | per Design Hour | |
| Setup costs | 69,776 | Number of batches | 490 | 142.4 | per Batch | |
| Classify each activity as facility, product, batch, or unit level. | ||||||
| Machining | unit level | |||||
| Design | product level | |||||
| Setup | batch level | |||||
| Hi mate, |
| I would be grateful to you if you can provide a thumbs up and write one beautiful comment. It will improve my rating and let me continue my journey here. |
| In case of doubt, please comment. I will consider myself fortunate if I can help you. |
| All the best for your bright future. |