Question

In: Accounting

Use Table PV-1 and Table PV-2 to determine the present values of the following cash flows.

Use Table PV-1 and Table PV-2 to determine the present values of the following cash flows. 

(For all requirements, round PV factor to 3 decimal places, Intermediate and final answer to the nearest dollar amount.) 

 a.

 $15,000 to be paid annually for 10 years, discounted at an annual rate of 6 percent. Payments are to occur at the end of each year.

 b.

 $9,200 to be received today, assuming that the money will be invested in a two-year certificate of deposit earning 8 percent annually.

 c.

 $300 to be paid monthly for 36 months, with an additional "balloon payment" of S12,000 due at the end of the c. 36th month, discounted at a monthly interest rate of 1% percent. The first payment is to be one month from today.

 d.

 $25,000 to be received annually for the first three years, followed by $15,000 to be received annually for the d. next two years (total of five years in which collections are received), discounted at an annual rate of 8 percent. Assume collections occur at year-end.


Solutions

Expert Solution

Solution a:

Present value of cash flows = $15,000 * Cumulative PV factor at 6% for 10 period

= $15,000 * 7.360 = $110,400

Solution b:

As $9,200 is received today, therefore Present value of cash flows is = $9,200

Solution c:

Monthly Payments = $300

Ballon payment at the end of 36 months = $12,000

Monthly interest rate = 1.5%

Period = 36

Present value = ($300 * Cumulative PV Factor at 1.5% for 36 periods) + ($12,000 * PV Factor at 1.5% for 36th period)

= $300*27.661 + $12,000*0.585

= $15,318

Solution d:

Computation of Present value of cash flows
Period Cash flows PV factor Present Value
1 $25,000.00 0.926 $23,150.00
2 $25,000.00 0.857 $21,425.00
3 $25,000.00 0.794 $19,850.00
4 $15,000.00 0.735 $11,025.00
5 $15,000.00 0.681 $10,215.00
Present Value $85,665.00

Related Solutions

Question 1: What is the present value (PV) of the following series of cash flows at...
Question 1: What is the present value (PV) of the following series of cash flows at 10% and its IRR? Year 0: -2,000$ | Year 1: +800$ | Year 2: +600$ | Year 3: +700$ | Year 4: +500$ Question 2: Draw a present value (PV) profile of the following project and determine the IRR(s). Is the project acceptable at 10% cost of capital? Year 0: -4,000$ | Year 1: +10,200$ | Year 2: -6,300$ Observation: if you find cumbersome...
Questions 1 & 2 ask for cash flows only, no present values. Although they are a...
Questions 1 & 2 ask for cash flows only, no present values. Although they are a critical part of the problem, since the problem is a capital budgeting problem, they are not worth any points, and you have unlimited tries. Questions 3 & 4 require that you use the correct cash flows from 1 and 2 to determine the net present values of the two alternatives. You should use the present value tables in the Coursepack. ______________________________________________________ The Brisbane Manufacturing...
Determine the net present worth (NPW) of the cash flows given in table below for an...
Determine the net present worth (NPW) of the cash flows given in table below for an investment opportunity being presented to a company. MARR =10%. Year 0 1-10 11-15 16-25 26-30 Cash Flow -$100K 10K 20K -5K 30K
Present and Future Values of Single Cash Flows for Different Periods Find the following values, using...
Present and Future Values of Single Cash Flows for Different Periods Find the following values, using the equations, and then work the problems using a financial calculator to check your answers. Disregard rounding differences. (Hint: If you are using a financial calculator, you can enter the known values and then press the appropriate key to find the unknown variable. Then, without clearing the TVM register, you can "override" the variable that changes by simply entering a new value for it...
Present and Future Values of Single Cash Flows for Different Periods Find the following values, using...
Present and Future Values of Single Cash Flows for Different Periods Find the following values, using the equations, and then work the problems using a financial calculator to check your answers. Disregard rounding differences. (Hint: If you are using a financial calculator, you can enter the known values and then press the appropriate key to find the unknown variable. Then, without clearing the TVM register, you can "override" the variable that changes by simply entering a new value for it...
An investment costs $200,000. If the present value (PV) of all the future cash flows is...
An investment costs $200,000. If the present value (PV) of all the future cash flows is $175,000, which of the following statements is correct? a. The project should be rejected since the Profitability Index is less than 1. b. The project should be rejected since the NPV is $25,000. c. The project should be accepted since the Profitability Index is greater than 0 d. The project should be rejected since the NPV is -$175,000.
Consider the mixed streams of cash flows shown in the following? table 1)Find the present value...
Consider the mixed streams of cash flows shown in the following? table 1)Find the present value of each stream using a 16?%discount rate. 2)?Compare the calculated present values and discuss them in light of the undiscounted cash flows totaling ?$175,000 in each case 1   $52,500   $17,500 2   $43,750   $26,250 3   $35,000   $35,000 4   $26,250   $43,750 5   $17,500   $52,500 Totals   $175,000   $175,000
Present and Future Values of Single Cash Flows for Different Interest Rates Use both the TVM...
Present and Future Values of Single Cash Flows for Different Interest Rates Use both the TVM equations and a financial calculator to find the following values. Round your answers to the nearest cent. (Hint: Using a financial calculator, you can enter the known values and then press the appropriate key to find the unknown variable. Then, without clearing the TVM register, you can "override" the variable that changes by simply entering a new value for it and then pressing the...
Present and Future Values of Single Cash Flows for Different Interest Rates Use both the TVM...
Present and Future Values of Single Cash Flows for Different Interest Rates Use both the TVM equations and a financial calculator to find the following values. (Hint: If you are using a financial calculator, you can enter the known values and then press the appropriate key to find the unknown variable. Then, without clearing the TVM register, you can "override" the variable that changes by simply entering a new value for it and then pressing the key for the unknown...
Find the present value of the streams of cash flows shown in the following​ table. Assume...
Find the present value of the streams of cash flows shown in the following​ table. Assume that the​ firm's opportunity cost is 14​%. a. The present value of stream A is ​$ b. The present value of stream B is ​$ c. The present value of stream C is ​$ A B C Year Cash Flow Year Cash Flow Year Cash Flow 1 −$2,100 1 ​$11,000 1−5 ​10,000​/yr 2 ​$3,000 2−5 ​$5,100​/yr 6−10 ​$7,900​/yr 3 ​$4,100 6 ​$7,100 4 ​$6,100...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT