In: Accounting
Below is the cost information for June and July, 2020.
Physical Units |
Direct Materials |
Conversions Costs |
Total |
|
Beg. Work in Progress (July 1, 2020) |
250 |
$78,750 |
$77,813 |
$156,813 |
Transferred to Finished Goods |
725 |
|||
Ending Work in Progress (July 31, 2020) |
200 |
|||
Costs added July 2020 |
$271,875 |
$295,800 |
$567,675 |
The production manager informs you that the Beginning Work in Progress (July 1) was 90% complete as to direct materials and 75% complete as to conversion costs. He also estimates that the Ending Work in Progress (July 31) is 50% complete as to materials and 35% complete as to conversion costs.
Use the Five-Step Process for assigning costs. Spartans Inc uses the weighted average method for assigning costs. Clearly label and explain each step. Show all calculations.
Spartans Inc. | |||
Flow of Production | Physical Units | Raw Material | Conversion |
Work in Process Beginning | 250 | ||
Started during Period | 675 | ||
To account for | 925 | ||
Units Completed(100%) | 725 | 725 | 725 |
Work in Process Ending(200*50%),(200*35%) | 200 | 100 | 70 |
Equivalent Units | 925 | 825 | 795 |
Costs | Total | Transferred In | Conversion |
Work in Process beginning | $ 1,56,563.00 | $ 78,750.00 | $ 77,813.00 |
Costs added during the period | $ 5,67,675.00 | $ 2,71,875.00 | $ 2,95,800.00 |
Total cost to account for | $ 7,24,238.00 | $ 3,50,625.00 | $ 3,73,613.00 |
Cost per Equivalent unit=($724238/925),($350625/825),(373613/795) | $ 894.95 | $ 425.00 | $ 469.95 |
Assignment of costs | |||
Completed Units(725*894.95) | $ 6,48,841.26 | ||
Work in Process Ending | |||
Direct Material(100*$425) | $ 42,500.00 | ||
Conversion(70*$469.95) | $ 32,896.74 | $ 75,396.74 | |
Costs accounted for | $ 7,24,238.00 |