In: Finance
NPV Your division is considering two projects with the following cash flows (in millions):
|
NPV of both Project at different discount rate is calculated in excel and screen shot provided below:
At 5% discount rate NPV of project A is $3.29 and NPV of project B is $0.97, At 10% discount rate NPV of project A is $1.00 and NPV of project B is $0.06, and At 15% discount rate NPV of project A is -$0.96 and NPV of project B is -$0.0.75,
IRR calculation does not use discount rate. So IRR of all project is calculated in excel and screen shot provided below:
IRR of project A is 12.46% and IRR of project B is 10.34%.
c.
At 10% discount rate NPV of project A is $1.00 and NPV of project B is $0.06. If both project is mutually exlusive then Project A should be accepted because NPV of project A is higher than NPV of project B.
d.
At 15% discount rate NPV of project A is -$0.96 and NPV of project B is -$0.0.75. Since, both project has negative NPV at 15% discount rate, so both project should be rejected. So Neither of project is accepted at 15% discount rate.