In: Finance
NPV Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$17 $8 $8 $3 Project B -$26 $13 $10 $9 What are the projects' NPVs assuming the WACC is 5%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is 10%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' NPVs assuming the WACC is 15%? Round your answer to two decimal places. Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Project A $ million Project B $ million What are the projects' IRRs assuming the WACC is 5%? Round your answer to two decimal places. Project A % Project B % What are the projects' IRRs assuming the WACC is 10%? Round your answer to two decimal places. Project A % Project B % What are the projects' IRRs assuming the WACC is 15%? Round your answer to two decimal places. Project A % Project B % If the WACC were 5% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 20.19%.) If the WACC were 10% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 20.19%.) If the WACC were 15% and A and B were mutually exclusive, which would you choose? (Hint: The crossover rate is 20.19%.)
A) Computation of NPV of project A and project B:
NPV = Net present value of all future generated cash inflow - initial investment.
Net present value of all future cash flow =
1) when WACC is 5%:
Project A =
= 7.619047619 +7.256235828 +2.591512796 - 17
= 0.47
Project B =
=12.38095238+9.070294785+7.774538387-26
=29.22578862 -26
=3.23
2) when WACC is 10%
Project A :
NPV =
= 7.272727273+6.611570248+2.253944403-17
=16.13824195-17
=-0.86
Project B :
NPV=
= 11.81818182 + 8.26446281 +6.761833208 -26
= 0.84
3) when WACC is 15%
Project A:
NPV =
= 6.956521739 +6.049149338 + 1.972548697 - 17
= 14.97821977 -17
= -2.02
Project B:
NPV =
= 11.30434783 + 7.561436673 +5.917646092 -26
= -1.21
B) Internal Rtae of Return:
IRR = that state which equates the NPV of cash inflows with the initial investment.
therefore, Future cash inflows ( PVFn)= Initial Investment
computation of IRR:
Project A :
IRR = (8+8+3)(PVFn) = 17
(PVFn)=17/20
(PVFn)=0.85
The discounting rate of 5% for 3 years is 0.8638 and at 6 % its 0.8396
hence IRR for the project is
= 5.570%
Project B: (10+10+9) (PVFn)= 26
(PVFn)=26/29
(PVFn)=0.896551724
(PVFn) at the rate 3% for 2 year is 0.9151 and at the rate of 4% it is 0.8890
hence IRR=3.7088%
General Rule of acceptance:
If IRR > WACC - Accept the proposal
if IRR< WACC - Reject the proposal
1) when WACC is 5%
Project A - Accept the project since 5.57% is more than the WACC
Project B- Reject the project since 3.7088% as compaired to the weighted average cost to the firm.
2) when WACC is 10%
Project A - though IRR is less but it is more than project B hence should be given prefference
Project B- should not be accepted
3) when WACC os 15%
Project A - though IRR is less but it is more than project B hence should be given prefference
Project B - should not be accepted.