Question

In: Finance

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of...

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of 1.5, the market is expected to have a 20% return and the risk-free rate is 5%. The forecasted free cash flows for the next 4 years for this project are $70,000 (FCF1), $100,000(FCF2), 0(FCF3), and $125,000 (FCF4). The project will cease to exist after that. TAMU has a debt/equity ratio of 2/3 and the applicable tax rate is 35%. The cost of debt (before taxes) can be calculated using TAMU’s currently issued bond which has a face value of $1000, yearly paid coupon rate of 10%, 20 years left to maturity and a current price of $1,196.36.

What is the cost of equity for TAMU Inc.?
       12.00%
       18.00%
       21.00%
       27.50%
Question 8. 8. Continued from Question 7, what is the pre-tax cost of debt (before taxes) for TAMU Inc.?
       9.76%
       8.00%
       11.65%
       7.50%
Question 9. 9. Continued from Question 7, what is TAMU’s WACC (after tax)?
       11.65%
       17.55%
       18.58%
       20.12%
Question 10. 10. Continued from Question 7, what is the NVP for this project?
       -$31,629
       -$15,184
       $14,446
       $28,170
Question 11. 11. Continued from Question 7, what is the IRR of the project?
       19.55%
       16.51%
       15.17%
       11.32%
Question 12. 12. Continued from Question 7, what is the MIRR of the project? Assuming that the positive cash inflow from undertaking this project will be reinvested at the after-tax weighted average cost of capital calculated in Question 9.
       14.17%
       17.28%
       19.78%
       20.86%

Solutions

Expert Solution

1)

cost of equity using CAPM model = risk free rate + beta ( expected return on market - risk free rate)

Cost of equity = 0.05 + 1.5 ( 0.2 - 0.05)

Cost of equity = 0.275 or 27.5%

2)

Face value = 1,000

Price = 1196.36

number of periods = 20

Coupon payment = 0.1 * 1000 = 100

Pre tax cost of debt using a financial calculator is 8.00%

Keys to use in a financial calculator: PV = -1196.36, FV = 1000, PMT = 50, N = 20 , CPT I/Y

3)

After tax cost of debt = pre tax cost of debt ( 1 - tax rate)

After tax cost of debt = 0.08 ( 1 - 0.35)

After tax cost of debt = 0.052 or 5.2%

Weight of equity = 1 / 1.66666 = 0.600002

weight of debt = 1 - 0.600002 = 0.399998

WACC = weight of debt * cost of debt + weight of equity * cost of equity

WACC = 0.399998* 0.052 + 0.600002* 0.275'

WACC = 0.0208 + 0.165001

WACC = 0.1858 or 18.58%

4)

NPV = present value of cash inflows - present value of cash outflows

NPV = -225,000 + 70000 / ( 1 + 0.1858)1 + 100,000 / ( 1 + 0.1858)2 + 0 + 125,000 / ( 1 + 0.1858)4

NPV = -$31,629

5)

IRR is the rate of return tha makes NPV equal to 0

-225,000 + 70000 / ( 1 + r)1 + 100,000 / ( 1 + r)2 + 0 + 125,000 / ( 1 + r)4 = 0

From the option let's try 11.32% as a:

-225,000 + 70000 / ( 1 + 0.1132)1 + 100,000 / ( 1 + 0.1132)2 + 0 + 125,000 / ( 1 + 0.1132)4 = 0

0 = 0

Therefore, IRR is 11.32%

5)

Future value of first cash flow = 70000 / ( 1 + 0.1858)3 = 116,716.5328

Future value of 2nd cash flow = 100,000/ ( 1 + 0.1858)2 = 140,612.64

Future value of 3rd cash flow = 0

Future value of 4th cash flow = 125,000 / ( 1 + 0.1858)0 = 125,000

Total future value = 125,000 + 140,612.64 + 116,716.5328 = 382,329.1728

Fv = PV ( 1+ r)n

382,329.1728 = 225,000 ( 1 + r )4

1.699241 = ( 1 + r )4

4th root of 1.699241 is 1.141731

1.141731 = 1 + r

0.141731 = r

MIRR is 14.17%


Related Solutions

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of...
7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of 1.5, the market is expected to have a 20% return and the risk-free rate is 5%. The forecasted free cash flows for the next 4 years for this project are $70,000 (FCF1), $100,000(FCF2), 0(FCF3), and $125,000 (FCF4). The project will cease to exist after that. TAMU has a debt/equity ratio of 2/3 and the applicable tax rate is 35%. The cost of debt (before...
We are evaluating a project that costs $870,000, has an 7-year life, and has no salvage...
We are evaluating a project that costs $870,000, has an 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $40, variable cost per unit is $25, and fixed costs are $880,440 per year. The tax rate is 31 percent, and we require a 15 percent return on this project. Requirement 3: Sensitivity of OCF (a) In addition...
We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage...
We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,700 units per year. Price per unit is $38.67, variable cost per unit is $23.80, and fixed costs are $851,000 per year. The tax rate is 22 percent, and we require a return of 10 percent on this project . a. Calculate the base-case operating cash...
3. Sandlewood Inc. has a project which has a beta of 1.24. As a market analyst,...
3. Sandlewood Inc. has a project which has a beta of 1.24. As a market analyst, you find the risk-free rate is 3.8% and the market rate of return is 9.2%. Which one of the below is the project's expected rate of return? a. 15.21% b. 11.41% c. 10.50% d. 14.61%
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000...
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000 in one year and an outflow of $51,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest %    What discount rate results in the maximum NPV for this...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000 in one year and an outflow of $57,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest % What discount rate results in the maximum NPV for this project?
You are evaluating a project that costs $69,000 today. The project has an inflow of $148,000...
You are evaluating a project that costs $69,000 today. The project has an inflow of $148,000 in one year and an outflow of $59,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest %    What discount rate results in the maximum NPV for this...
SafeElectrical is evaluating a project which will increase sales by $50,000 and costs by $30,000. The...
SafeElectrical is evaluating a project which will increase sales by $50,000 and costs by $30,000. The project will cost $150,000 and will be depreciated straight-line to a zero book value over the 10-year life of the project. The applicable tax rate is 34 percent. Net working capital is zero. What is the annual cash flow for this project? $3,300 $17,900 $20,000 $18,300 $28,200
Logic Legal Leverage (LLL) is evaluating a project that has a beta coefficient equal to 1.3....
Logic Legal Leverage (LLL) is evaluating a project that has a beta coefficient equal to 1.3. The risk- free rate is 3 percent and the market risk pre- mium is 6 percent. The project, which requires an investment of $405,000, will generate $165,000 after-tax operating cash flows for the next three years. Should LLL purchase the project? Excuse me, but I am stumped on this and the answer listed feels incorrect to me. Any thoughts?
We are evaluating a project that costs $1,675,000, has a six year life, and has no...
We are evaluating a project that costs $1,675,000, has a six year life, and has no salvage value. Assume that depreciation is straight line to zero over the life of the project. Sales are projected as 91,000 units per year, price is $35.95 per unit, variable cost is $21.4 per unit, fixed costs are $775,000 per year. Tax rate is 35% and discount rate is 11%. 1) calculate base-case profit, profit with a 100-unit increase or 100-unit decrease, and break-even...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT