Question

In: Finance

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of...

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of 1.5, the market is expected to have a 20% return and the risk-free rate is 5%. The forecasted free cash flows for the next 4 years for this project are $70,000 (FCF1), $100,000(FCF2), 0(FCF3), and $125,000 (FCF4). The project will cease to exist after that. TAMU has a debt/equity ratio of 2/3 and the applicable tax rate is 35%. The cost of debt (before taxes) can be calculated using TAMU’s currently issued bond which has a face value of $1000, yearly paid coupon rate of 10%, 20 years left to maturity and a current price of $1,196.36.

What is the cost of equity for TAMU Inc.?
       12.00%
       18.00%
       21.00%
       27.50%
Question 8. 8. Continued from Question 7, what is the pre-tax cost of debt (before taxes) for TAMU Inc.?
       9.76%
       8.00%
       11.65%
       7.50%
Question 9. 9. Continued from Question 7, what is TAMU’s WACC (after tax)?
       11.65%
       17.55%
       18.58%
       20.12%
Question 10. 10. Continued from Question 7, what is the NVP for this project?
       -$31,629
       -$15,184
       $14,446
       $28,170
Question 11. 11. Continued from Question 7, what is the IRR of the project?
       19.55%
       16.51%
       15.17%
       11.32%
Question 12. 12. Continued from Question 7, what is the MIRR of the project? Assuming that the positive cash inflow from undertaking this project will be reinvested at the after-tax weighted average cost of capital calculated in Question 9.
       14.17%
       17.28%
       19.78%
       20.86%

Solutions

Expert Solution

1)

cost of equity using CAPM model = risk free rate + beta ( expected return on market - risk free rate)

Cost of equity = 0.05 + 1.5 ( 0.2 - 0.05)

Cost of equity = 0.275 or 27.5%

2)

Face value = 1,000

Price = 1196.36

number of periods = 20

Coupon payment = 0.1 * 1000 = 100

Pre tax cost of debt using a financial calculator is 8.00%

Keys to use in a financial calculator: PV = -1196.36, FV = 1000, PMT = 50, N = 20 , CPT I/Y

3)

After tax cost of debt = pre tax cost of debt ( 1 - tax rate)

After tax cost of debt = 0.08 ( 1 - 0.35)

After tax cost of debt = 0.052 or 5.2%

Weight of equity = 1 / 1.66666 = 0.600002

weight of debt = 1 - 0.600002 = 0.399998

WACC = weight of debt * cost of debt + weight of equity * cost of equity

WACC = 0.399998* 0.052 + 0.600002* 0.275'

WACC = 0.0208 + 0.165001

WACC = 0.1858 or 18.58%

4)

NPV = present value of cash inflows - present value of cash outflows

NPV = -225,000 + 70000 / ( 1 + 0.1858)1 + 100,000 / ( 1 + 0.1858)2 + 0 + 125,000 / ( 1 + 0.1858)4

NPV = -$31,629

5)

IRR is the rate of return tha makes NPV equal to 0

-225,000 + 70000 / ( 1 + r)1 + 100,000 / ( 1 + r)2 + 0 + 125,000 / ( 1 + r)4 = 0

From the option let's try 11.32% as a:

-225,000 + 70000 / ( 1 + 0.1132)1 + 100,000 / ( 1 + 0.1132)2 + 0 + 125,000 / ( 1 + 0.1132)4 = 0

0 = 0

Therefore, IRR is 11.32%

5)

Future value of first cash flow = 70000 / ( 1 + 0.1858)3 = 116,716.5328

Future value of 2nd cash flow = 100,000/ ( 1 + 0.1858)2 = 140,612.64

Future value of 3rd cash flow = 0

Future value of 4th cash flow = 125,000 / ( 1 + 0.1858)0 = 125,000

Total future value = 125,000 + 140,612.64 + 116,716.5328 = 382,329.1728

Fv = PV ( 1+ r)n

382,329.1728 = 225,000 ( 1 + r )4

1.699241 = ( 1 + r )4

4th root of 1.699241 is 1.141731

1.141731 = 1 + r

0.141731 = r

MIRR is 14.17%


Related Solutions

7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of...
7. TAMU Inc. is evaluating a project which costs $225,000. Currently, TAMU has a beta of 1.5, the market is expected to have a 20% return and the risk-free rate is 5%. The forecasted free cash flows for the next 4 years for this project are $70,000 (FCF1), $100,000(FCF2), 0(FCF3), and $125,000 (FCF4). The project will cease to exist after that. TAMU has a debt/equity ratio of 2/3 and the applicable tax rate is 35%. The cost of debt (before...
We are evaluating a project that costs $1,950,000, has a life of 7 years, and has...
We are evaluating a project that costs $1,950,000, has a life of 7 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 88,800 units per year. Price per unit is $38.49, variable cost per unit is $23.65, and fixed costs are $842,000 per year. The tax rate is 24 percent, and we require a return of 12 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $870,000, has an 7-year life, and has no salvage...
We are evaluating a project that costs $870,000, has an 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $40, variable cost per unit is $25, and fixed costs are $880,440 per year. The tax rate is 31 percent, and we require a 15 percent return on this project. Requirement 3: Sensitivity of OCF (a) In addition...
We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage...
We are evaluating a project that costs $2,040,000, has a 7-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 89,700 units per year. Price per unit is $38.67, variable cost per unit is $23.80, and fixed costs are $851,000 per year. The tax rate is 22 percent, and we require a return of 10 percent on this project . a. Calculate the base-case operating cash...
3. Sandlewood Inc. has a project which has a beta of 1.24. As a market analyst,...
3. Sandlewood Inc. has a project which has a beta of 1.24. As a market analyst, you find the risk-free rate is 3.8% and the market rate of return is 9.2%. Which one of the below is the project's expected rate of return? a. 15.21% b. 11.41% c. 10.50% d. 14.61%
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000...
You are evaluating a project that costs $61,000 today. The project has an inflow of $132,000 in one year and an outflow of $51,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest %    What discount rate results in the maximum NPV for this...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000...
You are evaluating a project that costs $67,000 today. The project has an inflow of $144,000 in one year and an outflow of $57,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest % What discount rate results in the maximum NPV for this project?
You are evaluating a project that costs $69,000 today. The project has an inflow of $148,000...
You are evaluating a project that costs $69,000 today. The project has an inflow of $148,000 in one year and an outflow of $59,000 in two years. What are the IRRs for the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.)    IRR   Smallest %   Largest %    What discount rate results in the maximum NPV for this...
SafeElectrical is evaluating a project which will increase sales by $50,000 and costs by $30,000. The...
SafeElectrical is evaluating a project which will increase sales by $50,000 and costs by $30,000. The project will cost $150,000 and will be depreciated straight-line to a zero book value over the 10-year life of the project. The applicable tax rate is 34 percent. Net working capital is zero. What is the annual cash flow for this project? $3,300 $17,900 $20,000 $18,300 $28,200
Logic Legal Leverage (LLL) is evaluating a project that has a beta coefficient equal to 1.3....
Logic Legal Leverage (LLL) is evaluating a project that has a beta coefficient equal to 1.3. The risk- free rate is 3 percent and the market risk pre- mium is 6 percent. The project, which requires an investment of $405,000, will generate $165,000 after-tax operating cash flows for the next three years. Should LLL purchase the project? Excuse me, but I am stumped on this and the answer listed feels incorrect to me. Any thoughts?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT