In: Other
Explain briefly the difference between a conventional power plant and a combined cycle power plant with the aid of neat diagrams.
In: Other
Develop enzymatic rate expressions for competitive, noncompetitive, uncompetitive inhibitions using rapid equilibrium assumption.
In: Other
One method of exploitation of an ore mine that contains 1 million metric tons of ore will result in a recovery of 70% of the available ore deposit and will cost $25 per ton of material removed. Another method of exploitation will recover 60% and will cost $20 per metric ton of material removed. Subsequent processing of the removed ore recovers 200 kg of metal from each ton of processed ore and cost $50 per metric ton of ore processed. The recovered metal can be sold for $2.0 per kg. Which method for developing the mine is preferred to maximize total profit from the mine?
In: Other
One alternative to accelerate oil well production is to install a booster pump at the wellhead to reduce the pressure drop between the oil reservoir and the oil gathering station (onshore) or production platform (offshore). Make an economic analysis to verify if the production increment (between with and without booster pump) is economically attractive. The following data from an oil well subsea boosting project is available: Subsea equipment installation cost: $ 1.5 million 1 MW (Mega Watts) Pump system unit cost: $ 25.0 million Deep-water vessel rent for pipeline laying: $ 40 million total cost Overhead cost: assume 10% to total investment cost The installation and construction of the boosting system will be performed in one year. The revenue of this project is generated by oil well production increment using the booting system. An increment of 5,000 bopd (barrels of oil per day) in the first year of operation (after one year for installation and construction) is predicted, then, it will decline by 10% every year for a study period of 10 years. For example, 5000 bopd (initial increment), then 4500 bopd (in the next year), 4050 bopd, 3645 bopd, etc. Assume the oil well operates 330 days per year. The remaining 30 days, the well will not produce because it will be in maintenance (also called workover). Assume the well will produce oil only (no water). The market value of this equipment will be negligible at the end of the 10-year study period. Use MARR = 20% Calculate the present worth (PW) for this project assuming an oil-selling price of $40 per barrel and a production cost of $15 per barrel. In addition, add a constant value of $5 million per year for energy cost to run the pump boosting system. Is this project economically attractive? Draw a cash flow diagram for this project
Problem 2 (10%)
Estimate the simple payback period and the discounted payback period of problem 1.
Just answer problem 2 please
In: Other
One alternative to accelerate oil well production is to install a booster pump at the wellhead to reduce the pressure drop between the oil reservoir and the oil gathering station (onshore) or production platform (offshore). Make an economic analysis to verify if the production increment (between with and without booster pump) is economically attractive. The following data from an oil well subsea boosting project is available: Subsea equipment installation cost: $ 1.5 million 1 MW (Mega Watts) Pump system unit cost: $ 25.0 million Deep-water vessel rent for pipeline laying: $ 40 million total cost Overhead cost: assume 10% to total investment cost The installation and construction of the boosting system will be performed in one year. The revenue of this project is generated by oil well production increment using the booting system. An increment of 5,000 bopd (barrels of oil per day) in the first year of operation (after one year for installation and construction) is predicted, then, it will decline by 10% every year for a study period of 10 years. For example, 5000 bopd (initial increment), then 4500 bopd (in the next year), 4050 bopd, 3645 bopd, etc. Assume the oil well operates 330 days per year. The remaining 30 days, the well will not produce because it will be in maintenance (also called workover). Assume the well will produce oil only (no water). The market value of this equipment will be negligible at the end of the 10-year study period. Use MARR = 20% Calculate the present worth (PW) for this project assuming an oil-selling price of $40 per barrel and a production cost of $15 per barrel. In addition, add a constant value of $5 million per year for energy cost to run the pump boosting system. Is this project economically attractive? Draw a cash flow diagram for this project
In: Other
Suggest two methods for making the PStyrene-PButadiene-PStyrene
(polystyrene-polybutadiene-polystyrene)
triblock copolymer in a batch reactor using n-BuLi as an
initiator.
In: Other
The following data are obtained at 0°C in a constant-volume batch reactor using pure gaseous
Time, min |
0 |
2 |
4 |
6 |
8 |
10 |
12 |
14 |
∞ |
Partial pressure of A, mm Hg |
760 |
600 |
475 |
390 |
320 |
275 |
240 |
215 |
150 |
The stoichiometry of the decomposition is A → 2.5 R. Find a rate equation which satisfactorily represents this decomposition.
In: Other
Exchanger
1. Problem Statement & Scope of Work
Ethylbenzene is manufactured by alkylation of benzene with
ethylene. The reaction
products are separated in a series of distillation columns.
Ethylbenzene is obtained as
the distillate from the last column (called the ethylbenzene
column). In a 70 ton per
day ethylbenzene plant, the final product leaves the overhead
condenser at 1350C.
This is required to be cooled to 400C before pumping it to the
storage tank. Cooling
water is available at 300C for cooling. Please provide a proposal
for the design of a
multi-pass counter-current Shell & Tube Heat Exchanger
(Figure-1) that fulfils the
specifications in Section 3 (Process Data) and includes the
following items:
Item 1: Do energy balance and find heat duty (Q) and water flow
rate
Item2: First start trial with 1-1 pass counter current exchanger
and do LMTD
calculation and find out area, assuming overall heat transfer
coefficient
based on outside area, Udo
Item 3: Select tube BWG (i.d, o.d and length) from available market
and number of
tubes required and linear velocity of water (a velocity above 1 m/s
should be
maintained).Do selection of tube side and shell side fluid with
proper
justification
Item 4: Start second trial with suitable tentative selection of
tube passes (say 1-4
pass) and repeat calculation and find out tube specifications and
number of
tubes (You may use Tube-sheet layout and tube count of a shell and
tube
heat exchanger Table which are available in standard data
book)
Item-5: Select 25% cut segmental baffles with 0.15 m (6 inch)
baffle spacing and
shell specification
Item 6: Estimate the tube-side and shell-side heat transfer
coefficient (hi) using any
suitable correlation. Number of correlations are available such as
Dittus-
Boelter equation, Colburn jH factor etc. At this stage there are
number of
decision options on baffle spacing, number of tube passes etc are
available to
get reasonably high local heat transfer coefficients.
Item 7: Calculate the ‘clean’ Overall coefficient, U on the outside
tube area basis.
and repeat the above calculation to get area required, tube
specifications,
number of required tubes. Neglect dirt factor calculation for
U.
Item-8: No need to do pressure-drop calculation exercise but you
may discuss this
variable and its role on design calculation.
N.B. You may be referred for various data from standard data book
or from
Chemical Eng handbook- by Perry if required
2
go through S&T H.E. design calculation from Process Heat
Transfer book by D.
Q. Kern. My expectations are your approaches and method of
calculations
2. Project Report
This is an individual self-study mini-project on Shell & Tube
Heat Exchanger
equipment design. Individual student is to require a report writing
covering all
sections of design items. The report should also include an
executive summary, along
with brief conclusions and recommendations. Your approaches and
method of
calculations are also important and carry significant
weightage
3. Process Data
The allowable pressure drop is 0.15 kg/cm2 on both tube and shell
sides.
Ethylbenzene at the mean liquid temperature (87.50C):
Density: 840 kg/m3
Specific heat: 2.093 kJ/kg.K
Viscosity: 0.33 cp =3.3 x 10-4 kg/m-s
Thermal conductivity: 0.1156 W/m K = 0.0994 kcal/h m K
Water at 350C (mean temperature)
Density: 993 kg/m3
Viscosity: 8 x 10-4 kg/m s
Specific heat: 4.175 kJ/kg K = 1.0 kcal/kg K
Thermal conductivity: 0.623 W/m.K = 0.536 kacl/h m2K
.
In: Other
Explain the meaning of the pour point, flash point for crude oil
In: Other
Explain in details why crude oil requires to be refined and explain how this process is done with suitable diagram.
In: Other
|
|
|
|
|
|
In: Other
In: Other
i) Determine the sedimentation coefficient of sphere particles with 0.1 micrometer size and density of 1200 kg/m^3 in tetrahydrofuran (THF) at 25 degrees celcius which density of THF is 889 kg/m^3 and its viscosity is 0.456 mPa.s. ii) Assume the particle size is doubled, determine the sedimentation coefficient.
In: Other
One of the primary functions of impact testing is to determine whether a material experiences a ductile-to-brittle transition. Clearly explain what it means when a material exhibits “ductile-to-brittle transition” behavior?
In: Other