Question

In: Finance

The NPV criterion is considered the best approach to evaluating projects. Why do some firms still...

The NPV criterion is considered the best approach to evaluating projects. Why do some firms still rely on the IRR rule instead?

Solutions

Expert Solution

What is Net Present Value:

NPV is expressed in a dollar figure. It is the difference between a company's present value of cash inflows and its present value of cash outflows over a specific period of time.

What is Internal Rate of Return (IRR) :

IRR stands for internal rate of return. When used, it estimates the profitability of potential investments using a percentage value rather than a dollar amount. It is also referred to as the discounted flow rate of return or the economic rate of return. It excludes outside factors such as capital costs and inflation.

Differences between NPV and IRR :

1. The NPV method results in a dollar value that a project will produce, while IRR generates the percentage return that the project is expected to create. Purpose. The NPV method focuses on project surpluses, while IRR is focused on the breakeven cash flow level of a project.

2. When you are analyzing a single conventional project, both NPV and IRR will provide you the same indicator about whether to accept the project or not. However, when comparing two projects, the NPV and IRR may provide conflicting results. It may be so that one project has higher NPV while the other has a higher IRR.

3. If a discount rate is not known, or cannot be applied to a specific project for whatever reason, the IRR is of limited value. In cases like this, the NPV method is superior. If a project's NPV is above zero, then it's considered to be financially worthwhile.

4. Everything points to the net present value decision method being superior to the internal rate of return decision method. One issue that business owners also have to consider is the reinvestment rate assumption. IRR is sometimes wrong because it assumes that cash flows from the project are reinvested at the project's IRR. However, net present value assumes cash flows from the project are reinvested at the firm's cost of capital, which is correct.

Conclusion: Based on above points, in most of the cases, using NPV method is beneficial than IRR method. But in the following situation IRR method is more useful than NPV method. So even though NPV criterion is considered best approach to evaluating projects, some firm still rely on the IRR rule in the following situation.

IRR is the best criterion to accept or reject or rank mutually exclusive projects as well as independent projects.

In the case of mutually exclusive projects, selecting projects based on NPV at hurdle rate is misleading. A project selected based on higher NPV at hurdle rate ends-up with negative NPV when discounted by the higher IRR achieved by the counterpart project (with lower NPV). In the case of counterpart project, the NPV is not negative but zero at that higher IRR as the discount rate. This weakness of NPV is not exposed as NPV is a static point estimate (at hurdle rate). The NPV is not an appropriate criterion.

In capital budgeting, mutually-exclusive projects refer to a set of projects out of which only one project can be selected for investment. A decision to undertake one project from mutually exclusive projects excludes all other projects from consideration.


Related Solutions

Why is the NPV considered to be the best method for capital budgeting? What does the...
Why is the NPV considered to be the best method for capital budgeting? What does the NPV tell you? What are the limitations of the payback period as an investment decision criterion? What are its advantages? Why do you think it is used so frequently? When a firm finances a new investment, it often borrows part of the funds required, so the interest and principal payments this creates are incremental to the project’s acceptance. Why are these expenditures not included...
Critique why incremental process models are considered by many to be the best approach to the...
Critique why incremental process models are considered by many to be the best approach to the software application development in a modern context?
Critique why incremental process models are considered by many to be the best approach to the...
Critique why incremental process models are considered by many to be the best approach to the software application development in a modern context?
Monopolistically competitive firms do not earn profit in the long-run but still they are considered inefficient....
Monopolistically competitive firms do not earn profit in the long-run but still they are considered inefficient. Explain briefly.
Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one...
Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Happy Dog Soap Company is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $600,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $350,000 Year 2 $475,000 Year 3 $425,000 Year 4...
Why is FIFO considered a balance sheet approach and LIFO is considered an income statement approach?...
Why is FIFO considered a balance sheet approach and LIFO is considered an income statement approach? Please make your explanation as clear as possible thanks.
Costco is evaluating three projects and will select the one with the highest NPV. The company's...
Costco is evaluating three projects and will select the one with the highest NPV. The company's cost of capital is 14.5%. Which project should Costco choose? IRR Investment CF - Y1 CF - Y2 CF - Y3 Project A 11.00% 75,000 35,000 40,000 45,000 Project B 15.00% 90,000 55,000 50,000 43,000 Project C 15.00% 50,000 40,000 25,000 11,000 a. Project A b. Project B c. Project C d. None of the above
Answer the following questions: Why do some firms practice price discrimination? Why do other firms practice...
Answer the following questions: Why do some firms practice price discrimination? Why do other firms practice price non-discrimination? Describe the differences between price non-discrimination and (i) first degree price discrimination, (ii) second degree price discrimination, (iii) third degree price discrimination, and (iv) peak load pricing. Provide a supporting example in each of these four cases. Note the market structure conditions in which each can apply, and explain the expected welfare outcomes in each case.
How do IRR and NPV interact to evaluate capital projects? What are some difficulties in estimating...
How do IRR and NPV interact to evaluate capital projects? What are some difficulties in estimating cash flows?
Analyze the reasons why a short-term project might be ranked higher under the NPV criterion if...
Analyze the reasons why a short-term project might be ranked higher under the NPV criterion if the cost of capital is high, while a long-term project might be deemed better if the cost of capital is low. Determine whether or not changes in the cost of capital could ever cause a change in the internal rate of return (IRR) ranking of two (2) projects.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT