In: Finance
| Project | A | B | |||||||||
| Pay Back Period (years) | 3.74 | 1.76 | |||||||||
| Discounted Pay Back (years) | 4.69 | 2.75 | |||||||||
| NPV $ | 478592 | 463480 | |||||||||
| IRR | 19.77% | 24.03% | |||||||||
| Profitability Index | 1.1276 | 1.1287 | |||||||||
| Modified IRR | 18.82% | 18.84% | |||||||||
| 1) | whenever an entrepreneur invest into a project the first and foremost criteria to recover the initial investment at earliest | ||||||||||
| for this purpose the payback is calculated . Further scientific approach is to calculated discounted payback . | |||||||||||
| Project A has longer Payback as Compared to Project B. Thus here, considering the market risk and technical risk into consideration, | |||||||||||
| thus the before any market competition and or before the technology becomes obsolete the initial investment is recovered. | |||||||||||
| not only this the other techniques of the capital budgeting shows that project B is better than project A. | |||||||||||
| therefore Project B should be chosen | |||||||||||
| 2) | Majorly 4 techniques are use d to make capital budgeting decision | ||||||||||
| Pay Back Period (years) | |||||||||||
| it refers to the period by which the project recovers it initial investments. Its basic method and does not consider the time value | |||||||||||
| of investment and cash flow. Hence the better version of this is discounted pay back period. | |||||||||||
| here both, pay back period and discounted payback period is better for project B | |||||||||||
| Net Present Value | |||||||||||
| Its the most preferred method while making decision as it take into consideration the time value of money and | |||||||||||
| thus helps entrepreneur to project the net discounted cash flow from the project. Since the project is yet to come into | |||||||||||
| existence the cashflow is based on certain assumptions wherein the time value of money is one of the most important factor. | |||||||||||
| Project with Higher NPV is Preferred ..in this case Project A has higher NPV than Project B | |||||||||||
| IRR | |||||||||||
| Its the most complex method of capital budgeting. | |||||||||||
| its a rate when present value of cash inflow equal to cash outflow. | |||||||||||
| the project where IRR is greater than cost of project then that option is considered as viable | |||||||||||
| Profitabilty Index | |||||||||||
| Its a ratio between present value of discounted future cash inflow to cash outflow at investment stage. | |||||||||||
| the project is considered better if the ratio is greater than 1. | |||||||||||
| In the given case both the projects have Profitability Index of greater than 1. but comparatively Project B has better Profitabilty index | |||||||||||
| 3 a) | Project | A | Rank | B | Rank | ||||||
| Pay Back Period (years) | 3.74 | 2 | 1.76 | 1 | |||||||
| Discounted Pay Back (years) | 4.69 | 2 | 2.75 | 1 | |||||||
| NPV $ | 478592 | 1 | 463480 | 2 | |||||||
| IRR | 19.77% | 2 | 24.03% | 1 | |||||||
| Profitability Index | 1.1276 | 2 | 1.1287 | 1 | |||||||
| Modified IRR | 18.82% | 2 | 18.84% | 1 | |||||||
| most of the criteria are majorly fulfilled by project B. Hence project B should be given acceptance | |||||||||||
| 3 b) | as discussed in point 2 above regarding various methods of capital budgeting, its not NPV but the other parameter also should be considered | ||||||||||
| while making the decision. From the Matrix given its clear that project A ranks marginally better than project B in NPV criteria. | |||||||||||
| but as an entrepreneur one has to consider all pros and cons of project. The Project should be able to recover investment and generate profit | |||||||||||
| in time value of money also should be considered. | |||||||||||
| if we take weighted criteria then Project B weights better than Project A . | |||||||||||
| 4 a) | Will select Project B as it fullfills majority of the criteria of the capital budgeting techniques. | ||||||||||
| 4 b) | every technique has its own pros and cons. | ||||||||||
| the project is yet to come into existence and get expose to market volatality , consumer preference, market competition, government polices and other unforeseen factors. | |||||||||||
| hence time value of money and recovery of investment in this parlance is the basic aim of the investor and further to earn profit. | |||||||||||
| since the project has many embedded motives only one technique can not be considered in isolation for decision making. | |||||||||||
| hence the decision should be based on weighted ranking based on the parameters given in the matrix. | |||||||||||