Question

In: Accounting

***PLEASE SHOW WORK*** % of Completion On May 1, 2013, Chapin Construction Company entered into a...

***PLEASE SHOW WORK***

% of Completion

On May 1, 2013, Chapin Construction Company entered into a $4,000,000 fixed-price contract to build an apartment building.Expected completion date is November, 2014.Assume a zero balance in the cash account as of 5/1/2013.

Please fill in Journal Entries and the Financial Statements below.Data pertaining to the construction period are as follows:

2013

2014

2015

Total

Contract price

4,000,000

Costs incurred to date

           800,000

        2,550,000

           3,500,000

Estimated costs to complete

        2,400,000

           850,000

                      -  

Progress Billings during year

           850,000

        2,100,000

        1,050,000

4,000,000

Collections during year

           700,000

        2,000,000

        1,300,000

4,000,000

PART 1

2013 2014 2015

% Complete

Rev. Recog

GP Recog

PART 2

Journal Entries

2013

2014

2015

CIP

Cash,Mtls, A/P, etc.

A/R

Billings

Cash

A/R

Billings

Revenue

Construction Expense

CIP

PART 3

Balance Sheet:

Current Assets

A/R

Costs &GP in Excess of Billings

Current Liabilities

Billings in Excess of Costs & GP

Income Statement

Revenue from Contract

Construction Expense

Gross Profit on Contract

Solutions

Expert Solution

  • All working forms part of the answer
  • Working---

2013

2014

2015

Contract Price

$    4,000,000.00

$ 4,000,000.00

$    4,000,000.00

Cost Incurred to Date

$        800,000.00

$ 2,550,000.00

$    3,500,000.00

Estimated cost yet to be incurred to complete the contract

$    2,400,000.00

$      850,000.00

$                          -  

Total Cost

$    3,200,000.00

$ 3,400,000.00

$    3,500,000.00

% of Completion

25.00%

75.00%

100.00%

Revenue to date

$    1,000,000.00

$ 3,000,000.00

$    4,000,000.00

Revenue of Previous year

$                          -  

$ 1,000,000.00

$    3,000,000.00

Net Revenue this year

$    1,000,000.00

$ 2,000,000.00

$    1,000,000.00

Cost to date

$        800,000.00

$ 2,550,000.00

$    3,500,000.00

Cost to date of previous year

$                          -  

$      800,000.00

$    2,550,000.00

Net Cost for the year

$        800,000.00

$ 1,750,000.00

$        950,000.00

Gross Profits

$        200,000.00

$      250,000.00

$          50,000.00

  • Answers

2013

2014

2015

% Complete

25.00%

75.00%

100.00%

Rev. Recog

$    1,000,000.00

$ 2,000,000.00

$    1,000,000.00

GP Recog

$        200,000.00

$      250,000.00

$          50,000.00

Journal Entries

2013

2014

2015

CIP

$        800,000.00

$ 1,750,000.00

$        950,000.00

Cash,Mtls, A/P, etc.

$        800,000.00

$ 1,750,000.00

$        950,000.00

A/R

$        850,000.00

$ 2,100,000.00

$    1,050,000.00

Billings

$        850,000.00

$ 2,100,000.00

$    1,050,000.00

Cash

$        700,000.00

$ 2,000,000.00

$    1,300,000.00

A/R

$        700,000.00

$ 2,000,000.00

$    1,300,000.00

Billings

$        850,000.00

$ 2,100,000.00

$    1,050,000.00

Revenue

$        850,000.00

$ 2,100,000.00

$    1,050,000.00

Construction Expense

$        800,000.00

$ 1,750,000.00

$        950,000.00

CIP

$        200,000.00

$      250,000.00

$          50,000.00

Revenue

$    1,000,000.00

$ 2,000,000.00

$    1,000,000.00

Balance Sheet:

2013

2014

2015

Current Assets

A/R

$        150,000.00

$      250,000.00

$                          -  

Costs &GP in Excess of Billings

$                          -  

$                        -  

$                          -  

Current Liabilities

Billings in Excess of Costs & GP

$          50,000.00

$      350,000.00

$                          -  

Income Statement

2013

2014

2015

Revenue from Contract

$    1,000,000.00

$ 2,000,000.00

$    1,000,000.00

Construction Expense

$        800,000.00

$ 1,750,000.00

$        950,000.00

Gross Profit on Contract

$        200,000.00

$      250,000.00

$          50,000.00


Related Solutions

Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a...
Cullumber Construction Company uses the percentage-of-completion method of accounting. In 2020, Cullumber began work under a non-cancellable contract #E2-D2, which provided for a contract price of $2,178,000. Other details follow: 2020 2021 Costs incurred during the year $706,640 $1,422,000 Estimated costs to complete, as at December 31 899,360 0 Billings during the year (non-refundable) 420,000 1,713,600 Collections during the year 352,000 1,481,000 How much revenue should be recognized in 2020 and in 2021? 2020 2021 Revenue to be recognized $enter...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract...
Nash Construction Company uses the percentage-of-completion method of accounting. In 2017, Nash began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 –0– Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 Prepare a complete set of journal entries for 2017 (using the percentage-of-completion method). (Credit account titles are automatically indented when amount is...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,075,000. During 2018, costs of $2,030,000 were incurred, with estimated costs of $4,030,000 yet to be incurred. Billings of $2,536,000 were sent, and cash collected was $2,280,000. In 2019, costs incurred were $2,536,000 with remaining costs estimated to be $3,645,000. 2019 billings were $2,786,000, and $2,505,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000. In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT