Question

In: Accounting

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,225,000. During 2021, costs of $2,090,000 were incurred, with estimated costs of $4,090,000 yet to be incurred. Billings of $2,608,000 were sent, and cash collected was $2,340,000.

In 2022, costs incurred were $2,608,000 with remaining costs estimated to be $3,735,000. 2022 billings were $2,858,000, and $2,565,000 cash was collected. The project was completed in 2023 after additional costs of $3,890,000 were incurred. The company’s fiscal year-end is December 31. This project does not qualify for revenue recognition over time.

Required:
1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.

Solutions

Expert Solution

Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Arrow
Particulars 2021 2022 2023 Note
Contract Price           8,225,000          8,225,000           8,225,000 A
Cost Incurred during the year           2,090,000          2,608,000           3,890,000 C
Cost Incurred to date           2,090,000          4,698,000           8,588,000
Estimated cost to complete           4,090,000          3,735,000                         -   D
Estimated total cost           6,180,000          8,433,000           8,588,000 E=C+B
(Cost Incurred to date+ Estimated cost to complete )
Percentage complete 33.82% 55.71% 100.00% F=B/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized           2,781,594          1,800,530           3,642,876 G
Gross Profit/(Loss)              691,594           (807,470)             (247,124) H=G-C
Formula of revenue to be recognized
(Contract Price*Percentage complete)- revenue previously recognized
Year 2021: 33.82% completed. Revenue recognized = 33.82% x $ 8,225,000 = $ 2,781,594.
Year 2022: 55.71% completed. Revenue recognized = 55.71% x $ 8,225,000 – $ 2,781,594 (previously recognized) = $ 1,800,530.
Year 2023: 100% completed. Revenue recognized = 100% x $ 8,225,000 – $ 2,781,594 $ 1,800,530 (previously recognized) = $ 3,642,876.

Related Solutions

On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,330,000. During 2021, costs of $2,110,000 were incurred with estimated costs of $4,110,000 yet to be incurred. Billings of $2,610,000 were sent, and cash collected was $2,360,000. In 2022, costs incurred were $2,610,000 with remaining costs estimated to be $3,765,000. 2022 billings were $2,860,000 and $2,585,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,480,000. During 2021, costs of $2,160,000 were incurred with estimated costs of $4,160,000 yet to be incurred. Billings of $2,660,000 were sent, and cash collected was $2,410,000. In 2022, costs incurred were $2,660,000 with remaining costs estimated to be $3,840,000. 2022 billings were $2,910,000 and $2,635,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,375,000. During 2021, costs of $2,150,000 were incurred, with estimated costs of $4,150,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,400,000. In 2022, costs incurred were $2,680,000 with remaining costs estimated to be $3,825,000. 2022 billings were $2,930,000, and $2,625,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2021, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2022, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2022 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,475,000. During 2021, costs of $2,190,000 were incurred, with estimated costs of $4,190,000 yet to be incurred. Billings of $2,728,000 were sent, and cash collected was $2,440,000. In 2022, costs incurred were $2,728,000 with remaining costs estimated to be $3,885,000. 2022 billings were $2,978,000, and $2,665,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,175,000. During 2021, costs of $2,070,000 were incurred, with estimated costs of $4,070,000 yet to be incurred. Billings of $2,584,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,584,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,834,000, and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT