Question

In: Finance

Compute the NPV for Project M if the appropriate cost of capitalis 8 percent. (Negative...

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project M





Time:012345
Cash flow:–$2,900$650$780$820$900$400

NPV:

Should the project be accepted or rejected?

  • rejected

  • accepted

Solutions

Expert Solution

- Computing the Net Present value(NPV) for Project M:-

Year Cash Flow of Project M ($) (a) PV Factor @8% (b) Present Value of Proj ect M ($)  (a)*(b)
0                                       (2,900.00) 1.00000 (2,900.0)
1                                             650.00 0.92593 601.852
2                                             780.00 0.85734                          668.724
3                                             820.00 0.79383                          650.942
4                                             900.00 0.73503                          661.527
5                                             400.00 0.68058                          272.233
                           (44.72)

So, NPV for Project M is -$44.72

- As the NPV for Project M is negative the Project should not be accepted as it will provide negative returns.

Thus, it should be Rejected

Note- PV Factor@8% can be taken from PVAF Table or calculated using this formula which is = 1/(1+0.08)^n

where, n = Respective year.

For example, PV Factor@8% of 2nd year = 1/(1+0.08)^2 = 1/1.1664 = 0.85734


Related Solutions

Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: –$1,200 $390 $520 $560 $640 $140 NPV? Should it be accepted or rejected
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Should the project be accepted or rejected? Project M Time: 0 1 2 3 4 5 Cash flow: –$1,500 $450 $580 $620 $700 $200 How do you come up with the NPV? And Should the project be accepted or rejected?
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 11 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$8,100 $3,370 $4,200 $1,540 $320
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do...
Compute the IRR static for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) What is the IRR? Should it be accepted or rejected?        Project E   Time: 0 1 2 3 4 5   Cash flow –$1,000 $350 $480 $520 $300 $100
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT