In: Finance
CAPITAL BUDGETING PROBLEM
Cashman Corp. is considering venturing into the very mysterious Project Z. Information on Project Z follows below. Cashman’s marginal tax rate is 34%. Calculate Project Z’s NPV and IRR. Should Cashman accept Project Z?
? Project Z is a 4?year project; the required return on project Z is 12%.
? Initial (up?front) investment is $1,200,000
? Annual revenues estimated at $4,000,000
? Annual expenses (not including depreciation) estimated at $2,900,000
? Depreciation for tax purposes is based on 6?year life, straight?line, to zero book value at end of 6 years
? At the end of the project (in year 4), will sell Project Z for expected market value of $500,000
? Net Working Capital: initial investment required is $1,100,000 (up?front); after that, NWC levels decrease by $275,000 per year.
Depreciation = 6 year and salvage value = $0
So, Depreciation every year = Initial Investment/no of years = $1200000/6 = $200000
| Particulate | Year0 | Year 1 | Year 2 | Year 3 | Year 4 | 
| Revenue | 4000000 | 4000000 | 4000000 | 4000000 | |
| Expens (minus) | 2900000 | 2900000 | 2900000 | 2900000 | |
| Depreciation (minus) | 200000 | 200000 | 200000 | 200000 | |
| PBT | 900000 | 900000 | 900000 | 900000 | |
| Tax (34%) | 306000 | 306000 | 306000 | 306000 | |
| PAT | 594000 | 594000 | 594000 | 594000 | |
| Depreciation | 200000 | 200000 | 200000 | 200000 | |
| Cash infow | 794000 | 794000 | 794000 | 794000 | |
| Initial investment | -1200000 | 
| Selling value of project | 500000 | ||||
| Net Working capital | -1100000 | 275000 | 275000 | 275000 | 275000 | 
| Net Cash flow | -2300000 | 1069000 | 1069000 | 1069000 | 1069000 | 
| Required return rate(12%) | |||||
| Present value factor | 1 | 0.89 | 0.80 | 0.71 | 0.64 | 
| Present value | -2300000 | 951410 | 855200 | 758990 | 684160 | 
| NPV | 949760 | ||||
| IRR | 16% | ||||
NPV = Cash flow in year 0th year+ 1st year +2nd year+ 3rd Year+4th Year
As NPV = $949760 which is positive. So, Cashman accept Project Z.
IRR is calculated when NPV = 0
IRR
NPV = 0 = -Cash Outflow + Cash inflow
0= -CF0 + CF1/(1+r) + CF2/(1+r)^2 + CF3/(1+r)^3 +CF4/(1+r)^4
0 = -$2300000 + 1069000/(1+r) + 1069000/(1+r)^2 + 1069000/(1+r)^3 + 1069000/(1+r)^4
r =16%