Question

In: Finance

We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage...

We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent.

Calculate the best-case and worst-case NPV figures.

Solutions

Expert Solution

We first need to find the depreciation for each year. The depreciation is:

Depreciation = $1,160,000/10

Depreciation = $116,000 per year

We will use the tax shield approach to calculate the OCF for the best- and worst-case scenarios. For thebest-case scenario, the price and quantity increase by 10 percent, so we will multiply the base case numbers by 1.1, a 10 percent increase. The variable and fixed costs both decrease by 10 percent, so wewill multiply the base case numbers by 0.9, a 10 percent decrease. Doing so, we get:

OCFbest= {[($45)(1.1) – ($20)(0.9)](44,000)(1.1) – $1,160,000(0.9)}(0.65) + 0.35($116,000)

OCFbest= $352,990.00

The best-case NPV is:

NPVbest= –$1,160,000 + $352,990.00(PVIFA20%,10)

NPVbest= –$1,160,000 + $352,990.00*4.1925

NPVbest= $319,910.575

For the worst-case scenario, the price and quantity decrease by 10 percent, so we will multiply the base case numbers by 0.9, a 10 percent decrease. The variable and fixed costs both increase by 10 percent,so we will multiply the base case numbers by 1.1, a 10 percent increase. Doing so, we get:

OCFworst= {[($45)(0.9) – ($20)(1.1)](44,000)(0.9) – $1,160,000(1.1)}(0.65) + 0.35($116,000)

OCFworst= -$312,610

The worst-case NPV is:

NPVworst= –$1,160,000 – $312,610.00(PVIFA20%,10)

NPVworst= –$1,160,000 – $312,610.00*4.1925

NPVworst= -$2,470,617.425


Related Solutions

We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage...
We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $22, and fixed costs are $645,000 per year. The tax rate is 24 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage...
We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. Suppose the projections given for price, quantity,...
1) We are evaluating a project that costs $1,160,000, has a ten-year life, and has no...
1) We are evaluating a project that costs $1,160,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $20, and fixed costs are $696,000 per year. The tax rate is 35 percent, and we require a return of 20 percent on this project. a. Calculate the accounting break-even point....
We are evaluating a project that costs $1,080,000, has a ten-year life, and has no salvage...
We are evaluating a project that costs $1,080,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $48, variable cost per unit is $27, and fixed costs are $756,000 per year. The tax rate is 25 percent, and we require a return of 15 percent on this project. a. Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $1,180,000, has a ten-year life, and has no salvage...
We are evaluating a project that costs $1,180,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 66,000 units per year. Price per unit is $36, variable cost per unit is $25, and fixed costs are $750,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. Suppose the projections given for price, quantity,...
We are evaluating a project that costs $1,080,000, has a ten-year life, and has no salvage...
We are evaluating a project that costs $1,080,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $756,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. a. Calculate the accounting break-even point. (Do...
We are evaluating a project that costs $1,160,000, has a life of 10 years, and has...
We are evaluating a project that costs $1,160,000, has a life of 10 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 44,000 units per year. Price per unit is $45, variable cost per unit is $20, and fixed costs are $645,000 per year. The tax rate is 24 percent and we require a return of 13 percent on this project. Suppose the projections given for...
We are evaluating a project that costs $1,920,000, has a 6 year life, and no salvage...
We are evaluating a project that costs $1,920,000, has a 6 year life, and no salvage value. Assume that depreciation is staright-line to zero over the life of the project. Sales are projected at 94,000 units per year. Price per unit is $38.43, variable cost per unit is $23.60 and fixed costs are $839,000 per year. The tax rate is 23 percent and we require a return of 12 percent on this project. Suppose the projections given for the price,...
We are evaluating a project that costs $972,000, has a 4 year life, and no salvage...
We are evaluating a project that costs $972,000, has a 4 year life, and no salvage value. Assume that depreciation is staright-line to zero over the life of the project. Sales are projected at 88,000 units per year. Price per unit is $35.15, variable cost per unit is $21.40 and fixed costs are $768,000 per year. The tax rate is 35 percent and we require a return of 13 percent on this project. A) Calculate the best case operating cash...
we are evaluating a project that costs $690,000, has a five year life, and no salvage...
we are evaluating a project that costs $690,000, has a five year life, and no salvage value. Assume that straightline to zero over the life of the project. sales are projected at 71,000 units per year. price per unit is $75, variable cost per unit is $38 and fixed costs are $790,000 per year. The tax rate is 35%, and we require a return of 15% on this project Calculate the best case and wore case npv figures
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT