In: Accounting
Vargis Corporation has a machining capacity of 217,000 hours per year. Utilization of capacity is normally 85%; it has been as low as 30% and as high as 90%. An analysis of the accounting records revealed the following selected costs:
At a 30% Utilization Rate At a 90% Utilization Rate
Cost A:
Total$457,000 $457,000
Per hour$7.20 ?
Cost B:
Total ? $1,961,000
Per hour$12.50 $12.50
Cost C:
Total$765,000 $1,347,000
Per hour$17.00 $9.09
Vargis uses the high-low method to analyze cost behavior.
Required:
Classify each of the costs as being either variable, fixed, or semivariable.
Calculate amounts for the two unknowns in the preceding table. (Round "Cost A" to 2 decimal places.)
Calculate the total amount that Vargis would expect at a 85% utilization rate for Cost A, Cost B, and Cost C. (Do not round intermediate calculations. Round your final answer to the nearest dollar amount.)
Classification and calculation of various costs and figures
Particulers | A | B | C |
Type of Cost | Fixed Cost | Variable Cost | Semivariable cost |
Unknown figures | $2.34/hr | $813750 | nil |
Mechine hours available at different capacity utalizatiion
at 30% = 217000*30% = 65100
at 90% = 217000*90% = 195300
at 85% = 217000*85% =184450
PER HOUR RATE OF COST A AT 90% CAPACITY
Irrespective of capacity utalization fixed cost will remain same
at different capacity utalization cost A is $457000, so that it is Fixed cost
Per hour rate = $457000/195300 hrs
= 2.34 per hour
COST B AT 30% CAPACITY
per hour rate of cost B is remains same in both 30% and 90%
per unit or per hour variable cost will be same at different capacity only if it is Variable cost
So that Cost B at 30% capacity can be calculated as follows
= 12.5*65,100hrs
=$813,750
COSTS THAT WILL INCUR AT 85% CAPACITY UTALIZATION
Cost A = $457,000 (as fixed cost will remain same)
Cost B = $12.5*184450 hrs
= $2,305,625 (as variable cost rate per hour will remain same)
Cost C:
As it sami-variable cost we have to find out fixed cost within that
for that first we have to calculate varibale cost per hour
VC/hr = Change in Variable cost / Change in mechine hours
=(1,347,000-765,000) / (195300-65100)
=582000 / 130200
=$4.47
so variable cost at 30% =4.47*65100
=$290,997
variable cost at 90% = 4.47*195300
= $872,991
So fixed cost of C = Total cost of C - Variable cost of
at 30% capacity = 765000 - 290997
= 474003
( checking correctness) at 90% = 1,347,000 - 872991
=47009 (approx)
So, COST C AT 85% capacity utalization
=variable cost + fixed cost
=(4.47*184450hrs) + 474009
=824491.5 + 474009
=$1,298,500.5
TOTAL COST AT 85% CAPACITY UTALIZATION
=cost A+ cost B+ cost C
=$457,000+$2,305,625+$1,298,500.5
=$4,061,125