35) The following data has been assembled for John Company. Use the high-low method.
Month Cost Hours
January $24,400 2,000
February $39,000 2,200
March $35,280 2,750
April $36,400 3,500
May $40,000 4,000
The expected total cost at an operating level of 1,900 hours is ________.
A) $23,180
B) $23,620
C) $24,000
D) $24,400
Correct answer---(B) $23620
Months |
Units |
Cost |
|
High Level |
May |
4,000 |
$ 40,000.00 |
Low Level |
January |
2,000 |
$ 24,400.00 |
Difference |
2,000 |
$ 15,600.00 |
Difference in Cost |
$ 15,600.00 |
Difference in units |
2,000 |
Variable cost per unit |
$ 7.80 |
Working |
High Level |
Low Level |
|
A |
Total Cost |
$ 40,000.00 |
$ 24,400.00 |
B |
Total Units |
4000 |
2000 |
C |
Variable cost per unit |
$ 7.80 |
$ 7.80 |
D = B x C |
Total Variable cost |
$ 31,200.00 |
$ 15,600.00 |
E = A - D |
Total Fixed Cost |
$ 8,800.00 |
$ 8,800.00 |
Number of Hours |
Variable cost per unit |
Total Variable cost |
Fixed Cost total |
Total COST |
1900 |
$ 7.80 |
$ 14,820.00 |
$ 8,800.00 |
$ 23,620.00 |