Question

In: Accounting

When comparing Activity-based costing (ABC) and the Theory of Constraints (TOC), the approach each method takes...

When comparing Activity-based costing (ABC) and the Theory of Constraints (TOC), the approach each method takes toward profitability analysis is:

Multiple Choice

  • Both TOC and ABC take a short-term approach.

  • TOC takes a long-term approach and ABC takes a short-term approach.

  • Both TOC and ABC take a long-term approach.

  • TOC takes a short-term approach and ABC takes a long-term approach.

Solutions

Expert Solution

Solution : Option D ( TOC takes short term approach and ABC takes long term approach)is the correct answer.

When comparing both TOC and ABC methods it is purely based on cost paradigms based on time period. The concept of short term and long term is based on capacity of production requirements.

It is assumed that in long term approach costs become more variable especially when spending and consumption are brought into alignment which makes activity based costing (ABC) more suitable.

It is assumed that in short term approach the production requirements are fixed and cannot be changed, due to which it creates bottlenecks which makes theory of constraints(TOC) more suitable.

This makes very much clear that the type of method to be used at various time horizons to assess towards profitability analysis.

Conclusion : From the above we can understand that OPTION D satisfies the given requirement in the question whereas remaining options A,B,C do not satisfy the given requirement in question.

Please do rate if my answer was found helpful. Thankyou !!!!!!


Related Solutions

Describe the Theory of Constraints (TOC). How might the TOC be used to explain operating conditions...
Describe the Theory of Constraints (TOC). How might the TOC be used to explain operating conditions at a business organization you frequently visit. supermarket, theater, children's school, local gasoline service station.,airport, department store, etc0
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $270,000 Other overheard $2,304,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $322,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $420,000 Other overheard $5,208,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 5,600 1,400 Oven hours 4,200 29,400 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $720,000 Other overheard $2,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 1,800 12,600 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $870,000 Other overheard $5,800,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 12,000 3,000 Oven hours 5,000 35,000 Required: Round your answers to the...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller...
Comparing ABC and Plantwide Overhead Cost Assignments Wellington Chocolate Company uses activity-based costing (ABC). The controller identified two activities and their budgeted costs: Setting up equipment $230,000 Other overheard $1,160,000 Setting up equipment is based on setup hours, and other overhead is based on oven hours. Wellington produces two products, Fudge and Cookies. Information on each product is as follows: Fudge Cookies Units produced 8,000 445,000 Setup hours 4,000 1,000 Oven hours 1,000 7,000 Required: Round your answers to the...
Explain the purpose of Activity-Based Costing(ABC).
Explain the purpose of Activity-Based Costing(ABC).
Describe an application of some element of TOC (theory of constraints) that you have observed in...
Describe an application of some element of TOC (theory of constraints) that you have observed in the current Carona virus crisis. This could be something you read about. Could be something your employer or university has done. Could be something you've done yourself. How effective was this application of TOC? (What could have been done more effectively? What was done poorly? etc.)
Answer the following questions about the Activity Based Costing method. a) When is the method used...
Answer the following questions about the Activity Based Costing method. a) When is the method used and what information does it provide managers? b) Explain the benefits of using this method versus traditional costing methods. c) Explain some disadvantages of using this method.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT