In: Finance
This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1 300 240 2 300 240 3 300 240 4 300 240 5 300 240 For above project, the interest rate is 10% Q1 what is NPV of project A
NPV of project A
=-1000+300/(1+10%)^1+300/(1+10%)^2+300/(1+10%)^3+300/(1+10%)^4+300/(1+10%)^5
=137.24