Question

In: Finance

Questions all relate to the following information: YEAR PROJECT A PROJECT B t=0 -$1,000,000 -$1,350,000 t=1...

Questions all relate to the following information:

YEAR

PROJECT A

PROJECT B

t=0

-$1,000,000

-$1,350,000

t=1

$350,000

$470,000

t=2

$400,000

$550,000

t=3

$320,000

$450,000

t=4

$40,000

$60,000

t=5

$550,000

$550,000

6)   Although flawed, the IRR is widely used. Which of the following is the best explanation for that phenomenon?

A.   It is easy to calculate.

B.    People like to compare percentages.

C.   It is less flawed than the alternative, i.e. the NPV.

D.   One still arrives at profitable investment decisions, just not at the most profitable investment decisions.

E.    Both A and D are correct.

7)   Hindelang Inc. is considering a project that has the following cash flow and WACC data. What is the project's MIRR?

WACC:

12.50%

Year

0   

1

2

3

4

Cash flows

-$850

$300

$320

$340

$360


a.

15.00%

b.

12.83%

c.

16.67%

d.

13.33%

e.

20.66%

8)There are analysts who believe that when using the MIRR one should use the T-bill rate as the discount/compound rate. This

A.   makes no sense at all.

B.    would lead to higher IRRs.

C.   would result in a more conservative (risk-averse) approach to investing.

D.   only makes sense for companies dealing with government projects.

E.    would have no impact investment decisions.

9)   The so-called “Reinvestment Rate Problem” leads to

A.    the use of the MIRR.

B.     an overstatement of the return using the IRR.

C.    a lower NPV.

D.    two or more IRRs.

E.  choosing low risk/low return investments.

10) The MIRR is a better and more accurate financial tool than the NPV.

True/False

Solutions

Expert Solution

6) IRR is still widely used because of its reporting simplicity. Hence Option A is the answer that IRR is easy to calculate,

7) Terminal Value of Cash Inflow = 300/1.125^3 + 320/1.125^2 +340/1.125+360 = 210.67+252+302.22+360=1124.89 PV of cash outflow = 850/1.125^0 = 850; Hence MIRR = 1.32^0.25 - 1 =.0718 = 7.18%

8) Using T Bill rate will lead to a more conservative risk averse way of investing. Hence option C is the correct answer.

9) In the MIRR the Reinvestment rate is assumed at the cost of capital whereas in the IRR method the reinvestment rate is the IRR rate only. IRR had only the single discount rate. Hence the Reinvestment rate problem lead to the use of MIRR. Thus, option A is the answer.

10) Yes, the MIRR is a better and more accurate financial tool than the NPV. The MIRR is more realistic in approach whereas NPV shows increased potential of projects.

So the above discussed statement in Problem 10) is TRUE.


Related Solutions

This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1...
This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1 300 240 2 300 240 3 300 240 4 300 240 5 300 240 For above project, the interest rate is 10% Q1 what is NPV of project A
This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1...
This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1 300 240 2 300 240 3 300 240 4 300 240 5 300 240 For above project, interest rate is 10% Q1 what is NPV of project A 2) q2 what is IRR of project b 3) NPV for A is higher than NPV for project B True False
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
This table will cover information for Q7-Q8 year CF project A CF project B 0 -1000...
This table will cover information for Q7-Q8 year CF project A CF project B 0 -1000 -800, 1 600 300, 2 700 300, 3 300, 4 400 With discount rate 7%. Q7: what is project B's NPV? Q8: what is annualized EAC (annualized  NPV) for project A?
Problems 1-2 are based on the information given in the following table: Year A B 0...
Problems 1-2 are based on the information given in the following table: Year A B 0 -2,500 -6,000 1 746 1,664 2 746 1,664 3 746 1,664 4 746 1,664 5 746 1,664 IRR 15% 12% The internal rate of return on the incremental cash flows is closest to _________. A. 4% B. 6% C. 8% D. 10% E. 12%
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT