Question

In: Operations Management

4. Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental...

4. Environment Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. Some of the activities can be crashed. The tasks, durations (in days), costs, predecessor relationships, the crash times, and costs associated with performing the activities at their original (normal) times and for the crash times are shown as follows:

Activity

Immediate Predecessor

Normal Time (days)

Normal Cost ($)

Crash Time

Crash Cost ($)

A

--

6

1,000

5

1,200

B

--

4

800

2

2,000

C

A, B

3

600

2

900

D

B

2

1,500

1

2,000

E

C, D

6

900

4

1,200

F

E

3

1,300

1

1,400

G

E

4

900

4

900

H

G

4

500

2

900

a. Find the total project completion time. (Show all work including finding the critical path).

b. Find the lowest cost solution if the state wants to complete the project two days early. State which activities need to be crashed and calculate the crashing cost for the total project.

Solutions

Expert Solution

(a) Total Project Completion time = 23 weeks

(b) Crash Activity E by 2 weeks.

Crashing cost = $ 300


Related Solutions

4. What triggers environmental impact assessment for major projects under Australian State and Commonwealth laws? Briefly...
4. What triggers environmental impact assessment for major projects under Australian State and Commonwealth laws? Briefly explain three weaknesses in these laws from an environmental protection perspective.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT