Question

In: Operations Management

A project to build a new bridge seems to be going very well since the project...

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 60 percent complete. The planners were only expecting to be 50 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,420,000 and it was done for only $1,300,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,500,000 but was actually done for $9,000,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,500,000. To date they have spent $5,000,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost index for the project to date. How is the project going?

Solutions

Expert Solution

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****

The following are the detailed specifications of a project to build a new bridge which was going ahead of schedule and incurring low costs.

Activity 1:

Activity 2:

Activity 3:

Using the specifications of the activities, calculate the budgeted cost of the Work Scheduled as shown below:

Calculate the budgeted cost of the Work Performed.

Activity 1:

Activity 2:

Activity 3:

The actual cost of the project is as shown below:

The calculation of schedule variance, schedule performance index, and cost performance index is as shown below:

Therefore, the project looks good because it is both ahead of schedule and within the budgeted cost.

*****Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*****


Related Solutions

A project to build a new bridge seems to be going very well since the project...
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activitieshave been totally completed and the third activity is 60 percent complete. The planners were only expecting to be 50 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected...
The UAE government is going to build a bridge between two of its islands in the...
The UAE government is going to build a bridge between two of its islands in the Arabian Gulf Sea to allow the residences of these two islands to communicate with each other’s and with the rest of the country. The government will sign a long time contract with the biggest international company in this field to be responsible for this project. The government will pay an initial cost of 100,000,000 Dhs, a major re-design to fix any bugs in the...
Even if everything seems to be going well, there is always room for improvement with workplace relationships.
Even if everything seems to be going well, there is always room for improvement with workplace relationships.
The municipality of a major city in Quebec is planning to build a new bridge to...
The municipality of a major city in Quebec is planning to build a new bridge to decrease the traffic load on the existing bridges connecting both sides of the city across the river. Construction is to start in 2020 and is expected to take four years at a cost of $25 million per year. After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year and to increase by 2.8% per...
Hi guys. What’s happening with bitcoin and ripple price nowadays? It’s seems going not that well...
Hi guys. What’s happening with bitcoin and ripple price nowadays? It’s seems going not that well as before. Is it about to bounce back or even higher than last max. Or fall of empire? And also I need some opinions on what Cryptocurrencies i could pay attention as a long term investment and some for quick tradings? Thnx for attention
Suppose you are responsible for a project to build an application that is going to collect...
Suppose you are responsible for a project to build an application that is going to collect all the training opportunities for any summer training program. The purpose of the application is to allow the user to search for the most suitable opportunity for him using different search criteria such as GPA and salary. How you would make a Risk Management plan for such a project? I want a Risk Management plan for this project. thanks.
In estimating terminal value for a company or project, future growth seems to play a very...
In estimating terminal value for a company or project, future growth seems to play a very important role. Why is this case? How can the future growth be determined? Besides growth-related estimations for terminal value, what other approaches might analysts use in their forecasts?
9. A $2,000,000 bond was issued on April 20, 2020 to build a new bridge. The...
9. A $2,000,000 bond was issued on April 20, 2020 to build a new bridge. The bonds carried a 4% interest rate and are due in 10 years. The first bond payment was made on March 31, 2021 for $280,000, which included $80,000 of interest. Required: (A.) Prepare the required journal entry in the Capital Projects Fund on April 20 for the Fund Financial Statements and the entry on March 31 to record the repayment of the bonds. (B.) Prepare...
JAVA PLEASE In this project, we are going to build a tiny database organized as a...
JAVA PLEASE In this project, we are going to build a tiny database organized as a singly linked list for storing and retrieving the information of a group of products on sale. The information of each product includes the following items: Product ID, Name, Seller, Quantity In Stock, Average Shipping Time, Original Price, Current Price. We assume that a node in the linked list should be defined by the following class. class Product {      long ID;      String name;...
A developer is going to build a new commercial building in Kowloon Tong. The features of...
A developer is going to build a new commercial building in Kowloon Tong. The features of the building are described as follows: Number of storey: 25 floors Floor areas: approx. 600m2 (each floor) Core areas: approx. 100m2 (each floor) G/F to 2/F: Restaurant premises (40% of the UFA); Retail establishments (60% of the UFA) 3/F to 25/F: Office premises Note: UFA denotes Usable Floor Area i ) Calculate the total cooling load for a given building. This part fulfills the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT