In: Operations Management
A system has five workstations (A, B, C, D, and E) connected in sequence, with process times of 5, 10, 4, 9, and 8 seconds per unit each, respectively. Each workstation contains a single machine.
1. which workstation is the bottleneck of the system:
a. Workstation A
b. Workstation B
c. Workstation C
d. Workstation D
2. the system process time of this process is:
a. 5.1 seconds
b. 10 seconds
c. 15 seconds
d. 36 seconds
3. assume Workstation B now contains two machines, each of which can process a 1 unit every 10 seconds. What is the throughput time of this process?
a. 9 seconds
b. 10 seconds
c. 36 seconds
d. 46 seconds
Answer:1
workstation B is the bottleneck with
the lowest per-minute process capacity of 6 units
Workstation (Step) | time in Seconds per unit | No. of machines | process capacity (units per second)= No. of workers/task time | process capacity per minute= 60/(process time) | |
A | 5 | 1 | 0.20 | 12.00 | |
B | 10 | 1 | 0.10 | 6.00 | Bottleneck |
C | 4 | 1 | 0.25 | 15.00 | |
D | 9 | 1 | 0.11 | 6.67 | |
E | 8 | 1 | 0.13 | 7.50 | |
Total | 36 |
Bottleneck = Process with the least Capacity per minute
Answer 2
Process cycle time =slowest of all processes =
10 seconds
Answer 3
Workstation (Step) | time in Seconds per unit | No. of machines | process capacity (units per second)= No. of workers/task time | process capacity per minute= 60/(process time) | |
A | 5 | 1 | 0.20 | 12.00 | |
B | 10 | 2 | 0.20 | 12.00 | |
C | 4 | 1 | 0.25 | 15.00 | |
D | 9 | 1 | 0.11 | 6.67 | Bottleneck |
E | 8 | 1 | 0.13 | 7.50 | |
Total | 36 |
Throughput time is the sum of all workstation times
=A+B+C+D+E = 36 seconds
And it remains the same, although a new workstation has been added,
but the total time the product takes from A to reach E remains the
same.