Question

In: Accounting

The Hayes Chemical company produces a chemical used in dry cleaning. Its accounting system uses standard...

The Hayes Chemical company produces a chemical used in dry cleaning. Its accounting system uses standard costs. The standard per .5-gallon can of chemical call for 1.20 gallons of material and 1.50 hours of labor. (1.20 gallons of material are needed to produce a .5-gallon can of product due to evaporation.) The standard cost per gallon of material is $6.00. The standard cost per hour for labor $9.00. Overhead is applied at the rate of $7.75 per can. Expected production is 20,000 cans with fixed overhead per year of $55,000 and variable overhead of $5.00 per unit (a .5-gallon can)

During 2021, 23,000 cans were produced; 35,000 gallons of material were purchased at a cost of $250,000; 30,000 gallons of material were used in production. The cost of direct labor incurred in 2021 was $290,000 based on an average actual wage rate of $8.25 per hour. Actual overhead for 2021 was $220,000.

A. Determine the standard cost per unit

B. calculate material, labor, and overhead variances

C. List a possible cause for each variance

Solutions

Expert Solution

Ans: 1. Standard Cost per Unit= Material Cost Per Unit+ Direct Labor Cost per Unit+ Overhead Cost

=> 1.20*6+1.5*9+7.75

=> 7.20+ 13.50+7.75

=> $28.45

2. Materials Purchase Variance= Actual purchase Cost- { Actual Quantity Purchase* Standard Cost}

=> 250,000-{35,000*6}

=> 250,000-210,000

=> 40,000 Unfavorable

Cause for this is As Actual Cost is less than Standard Cost

Materials Quantity Variance= Standard Price*(Actual Quantity used-Standard Quantity Allowed for Actual Production)

=> $6*(30,000-23,000*1.20)

=> $6*(30,000-27,600)

=> $6*2,400

=> $14,400 Unfavorable

Labor Variance

Labor Rate Variance= Actual Labor Cost- { Actual Hours*Standard rate)

=> 290,000-(290,000/8.25*9)

=> 290,000- 313,364

=> 23,364 Favorable.

Labor Efficiency Variance= Standard rate*(Actual Hours-Standard Hours for Actual Production)

=> 9*(290,000/8.25-23,000*1.50)

=> 9*(35,152-34,500)

=> 9*652

=> 5,868 Unfavorable

Overhead Variance:

Standard Overhead cost= Standard variable cost+Fixed Overhead cost

=> 5*23,000+55,000

=> 115,000+55,000

=> 170,000

Controllable Overhead Variance= Actual overhead- Standard Overhead cost

=> 220,000-170,000

=> 50,000 Unfavorable

Overhead Volume Variance= Budgeted Fixed Overhead- Standard Fixed Overhead cost for Actual output

=> 55,000-{23,000*(7.75-6)}

=> 55,000-{23,000*1.75}

=> 55,000- 40,250

=> 14,750 Unfavorable.


Related Solutions

Hayes Chemical Company produces a chemical used in dry cleaning. Its accounting system uses standard costs....
Hayes Chemical Company produces a chemical used in dry cleaning. Its accounting system uses standard costs. Standards for each 0.5-gallon can of chemical and actual data for Hayes Chemical follow: Standards and budgeted information:    Gallons of material per can of chemical 1.20    Hours of labor per can of chemical 1.50    Standard cost per gallon of material $6.00    Standard cost per hour of labor $9.00    Overhead application rate per can $7.75    Expected production - cans...
Problem 11-5 The Hayes Chemical Company produces a chemical used in dry cleaning. Its accounting system...
Problem 11-5 The Hayes Chemical Company produces a chemical used in dry cleaning. Its accounting system uses standard costs. The standards per 0.40-gallon can of chemical call for 1.20 gallons of material and 1.50 hours of labor. (1.20 gallons of material are needed to produce a 0.40-gallon can of product due to evaporation.) The standard cost per gallon of material is $6.00. The standard cost per hour for labor is $8.00. Overhead is applied at the rate of $8.03 per...
West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for...
West Manufacturing Company uses a standard cost system in its accounting records. The standard costs for its one product are as follows:                      Materials                                    8 pounds at $1.00 =   $ 8.00                      Direct labor                              1.2 hours at $14.00 =     16.80                      Variable overhead     1.2 direct-labor hours at $4.00 =       4.80                      Fixed overhead         1.2 direct-labor hours at $6.00 =       7.20                      Total standard cost                                                      $36.80             The standard costs per unit are based on normal capacity of 3,600 direct-labor...
Ferry Chemical uses a standard cost system to account for the costs of its production of...
Ferry Chemical uses a standard cost system to account for the costs of its production of Chemical X. Standards are 3.0 gallons of materials at $121 per gallon and 26 hours of labor at a standard wage rate of $28. During September, Ferry Chemical produced 3,250 gallons of Chemical X. Ferry Chemical purchased and used totaled 3,730 gallons at a total cost of $455,180. Payroll totaled $318,730 for 26,230 hours worked. a. Calculate the direct materials price variance. (Do not...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,200,000 $ 1,440,000 $ 1,680,000 Fixed overhead costs 612,000 612,000 612,000 Total overhead $ 1,812,000 $ 2,052,000 $ 2,292,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 684,000 684,000 684,000 Total overhead $ 1,734,000 $ 1,944,000 $ 2,154,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 630,000 630,000 630,000 Total overhead $ 1,530,000 $ 1,710,000 $ 1,890,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 702,000 702,000 702,000 Total overhead $ 1,602,000 $ 1,782,000 $ 1,962,000 The expected volume is 180,000 direct...
a Kansas Company uses a job costing accounting system for its production costs. The company uses...
a Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 594,000 594,000 594,000 Total overhead $ 1,644,000 $ 1,854,000 $ 2,064,000 The expected volume is 180,000...
The Rogers Company uses a standard cost accounting system and estimates production for the year to...
The Rogers Company uses a standard cost accounting system and estimates production for the year to be 60,000 units. At this volume, the company's variable overhead costs are $0.50 per direct labor hour. The company's single product has a standard cost of $30.00 per unit. Included in the $30.00 is $13.20 for direct materials (3 yards) and $12.00 of direct labor (2 hours). Production information for the month of March follows: Number of units produced 6,000 Materials purchased (18,500 yards)...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT