Question

In: Operations Management

Consider a project that requires the completion of 7 tasks, as follows: o Tasks A and...

  1. Consider a project that requires the completion of 7 tasks, as follows:

    o Tasks A and B can begin simultaneously at the beginning (“time zero”).

    o Task C can only begin after task B is completed.

    o Task D can only begin after task A is completed.

    o Task E can only begin after task A is completed.

    o Task F can only begin after task E is completed.

    o Task G can only begin after tasks C and D are completed.

    The expected durations (in days) of each task are as follows: A=15; B=20; C=10; D=10; E=30; F=20; G=40.

    What is the expected completion of the whole project?

    50 days

    60 days

    70 days

    75 days

2.Consider the project from the previous question with the added complexity that the actual completion time of each task will be:

Task Completion Time
A 15+RANDBETWEEN(-8,8)
B 20+RANDBETWEEN(-8,8)
C 10+RANDBETWEEN(-8,8)
D 10+RANDBETWEEN(-8,8)
E 30+RANDBETWEEN(-8,8)
F 20+RANDBETWEEN(-8,8)
G 40+RANDBETWEEN(-8,8)

Using PERT, what is the expected completion time of the project?

50

60

70

75

Solutions

Expert Solution

1. A network diagram is drawn satisfying all precedence relationships. Then earliest start time(ES), earliest finish time(EF) , latest start time(LS), latest finish time(LF) for each activities are calculated. Here ES & EF are calculated through a forward pass on the diagram by adding up the expected durations for each activities then LS & LF are calculated through a backward pass and reversing the activity completion times. Critical path is the path which one's delay will leads to delay in the whole project. The duration of critical path will give us expected duration of whole project.

Here expected project duration is found out as 70 days.

2. Here, while estimating the time for a PERT network , we have considered the distribution as beta distribution. and accordingly standard deviation is also calculated. Here as expected durations of each activities are found out to be sames as the values in the previous questions, the overall expected project completion time is also equal that is 70 days with a standard deviation of 7.04 days.

All steps and calculations are given below :

" You can give feedback through the comment option. if you liked the answer please give an Up-Vote. it will be quite encouraging for me. Thank you."


Related Solutions

A tasks completion time is normally distributed with a mean of 200 work days and a...
A tasks completion time is normally distributed with a mean of 200 work days and a SD of 10 work days. What is the probability that: (a) The task finishes within 185 work days. (b) The task takes longer than 212 work days (c) In order to be 99% sure that the task will not be completed late, the contractor must request a completion time of _______ days
Assume that for this project to be completed, five independent tasks must be completed. These tasks...
Assume that for this project to be completed, five independent tasks must be completed. These tasks are proceeding in parallel by five different subcontractors. To keep it simple, let's assume that each task takes between 1 and 5 months to complete (uniformly distributed, i.e. equally likely to take any amount of time between 1 and 5 months). So, the mean time to complete each task is 3 months and the probability of any given task taking 3 months or longer...
A project requires $178,077 of equipment that is classified as 7-year property. What is the book...
A project requires $178,077 of equipment that is classified as 7-year property. What is the book value of this asset at the end of year 5 given the following MACRS depreciation allowances, starting with year one: 14.29, 24.49, 17.49, 12.49, 8.93, 8.92, 8.93, and 4.46 percent? Enter your answer rounded off to two decimal points.
Project K requires an initial investment of $450,000, is expected to last for 7 years, and...
Project K requires an initial investment of $450,000, is expected to last for 7 years, and is expected to produce after-tax net cash flows of $92,000 per year. Project L requires $3000 initial investment and produces a net cash flow of $800 per year. The discount rate for both projects is 8%. a) What is the NPV of each project? b) What is the Profitability Index of each project? c) Which one will you choose?
Consider the following network of a project consisting of 7 activities with a scheduled project duration...
Consider the following network of a project consisting of 7 activities with a scheduled project duration of 36 weeks. Direct cost $12,000 with 36 weeks Indirect cost of $ 150 per week and delay damages of $ 500 per week for project duration beyond 30 weeks, and no incentive plan. the following table of time-cost data. Suppose the project should be completed in 30 weeks, what is the total project cost? Activity Predecessor. Normal Time (weeks) Crash Time (weeks) Normal...
Consider a project that requires an initial investment of $103,000 and will produce a single cash...
Consider a project that requires an initial investment of $103,000 and will produce a single cash flow of $148,000 in 4 years. What is the NVP of this project if the 4 year interest rate is 5.2% (EAR) ? What is the NPV of this project if the 4 year interest rate is 9.8% (EAR)? What is the highest 4 year interest rate such that this project is still profitable?
Consider a project that has a 10% cost of capital that requires an initial investment of...
Consider a project that has a 10% cost of capital that requires an initial investment of $10,000. The year 1 net cash inflow is $2,450; the year 2 net cash inflow is $2,850; the year 3 net cash inflow is $3,350; the year 4 net cash inflow is $3,750; and the year 5 net cash inflow is $5,250. What is the project's discounted payback? NPV? AND IRR?
Discuss the security arrangements regarding project completion and address factors that constitute completion from the lenders...
Discuss the security arrangements regarding project completion and address factors that constitute completion from the lenders perspective; as well, account for explicit safeguards and obligatory assurances. Words 500 - 550 max + References.
Consider a project whose net cash flow streams, Fn , are as follows                               &nbsp
Consider a project whose net cash flow streams, Fn , are as follows                                          n                E(Fn)                 Var(Fn)                                         0                 -$10                    9                                         1                     3                      4                                         2                     8                     16                                         3                    10                    25 In addition, the correlation coefficient among the Fn’s are known to be ρ01 = ρ02 = ρ03 = 0.5 and ρ12 = ρ23 = ρ13 = 1. Assuming i = 10%, compute the mean and variance of the PV for the project.
Consider the following binds Ca-O, C-O, K-O, O-O and N-O a Which bonds are polar covalent...
Consider the following binds Ca-O, C-O, K-O, O-O and N-O a Which bonds are polar covalent ? b Wich bonds are nonpolar Covalent c Which bonds are ionic ? d Arrange the covalent bonds in order of decreasing polarity
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT