Question

In: Economics

Required information For four independent projects, the investment limit is $350, and the following project selection...

Required information For four independent projects, the investment limit is $350, and the following project selection restriction applies: project 2 can be selected only if project 3 is selected.

Project Initial Investment, $
1 250
2 150
3 75
4 235

1) Determine all the acceptable mutually exclusive bundles from the following.

2) Determine all the nonacceptable mutually exclusive bundles from the following.

Solutions

Expert Solution

Answer) Let us name project 1 as P1,project 2 as P2 and so on

  1. With P1 only P3 can be selected as other 2 projects exceeds the budget,with P2 only P3 can be selected as adding any other will exceed the budget,with P3 apart from above 2 project bundles,P4 and P3 can be selected as that fulfills both conditions,any other bundle will non possible,so there are 3 acceptable mutually exclusive bundles which are project 1 and project 3;project 2 and project 3;project 3 and project 4
  2. Any bundle which is not acceptable will come under here as non accceptable mutually exclusive bundle,all 4 projects are not possible together,bundle of P1,P2,P3 is not possible and so is bundle of P1,P2,P4 and P1,P3,P4,similarly in bundles of 3 P2,P3,P4 is not possible,for bundles of 2,P1 and P2 is not possible and so is P1 and P4;P2 and P4 is not possible as well,so 8 bundles are non acceptable as mentioned in this part.

Answer is complete.Thank you!


Related Solutions

eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment...
eBook Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 10.75% High B 5 million 13.25 High C 3 million 8.75 Low D 2 million 7.75 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 5.75 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 13.25% High B 5 million 10.75 High C 3 million 8.75 Low D 2 million 8.00 Average E 6 million 11.75 High F 5 million 11.75 Average G 6 million 6.00 Low H 3 million 10.50 Low Ziege's WACC is 9.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.75% High B 5 million 12.25 High C 3 million 10.25 Low D 2 million 9.50 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.50 Low H 3 million 12.75 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.50% High B 5 million 15.00 High C 3 million 10.50 Low D 2 million 9.50 Average E 6 million 13.50 High F 5 million 13.50 Average G 6 million 7.50 Low H 3 million 12.00 Low Ziege's WACC is 11.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.25% High B 5 million 13.75 High C 3 million 9.25 Low D 2 million 9 Average E 6 million 12.25 High F 5 million 12.25 Average G 6 million 7 Low H 3 million 11 Low Ziege's WACC is 9.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 11.50% High B 5 million 14.00 High C 3 million 9.50 Low D 2 million 9.25 Average E 6 million 12.50 High F 5 million 12.50 Average G 6 million 7.25 Low H 3 million 11.50 Low Ziege's WACC is 10.00%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 12.25% High B 5 million 14.75 High C 3 million 10.25 Low D 2 million 9.75 Average E 6 million 13.25 High F 5 million 13.25 Average G 6 million 7.75 Low H 3 million 12.00 Low Ziege's WACC is 10.75%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 9.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 7.75 Low H 3 million 11.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate...
Ziege Systems is considering the following independent projects for the coming year: Project Required Investment Rate of Return Risk A $4 million 14.25% High B 5 million 11.75 High C 3 million 9.75 Low D 2 million 8.75 Average E 6 million 12.75 High F 5 million 12.75 Average G 6 million 6.75 Low H 3 million 12.25 Low Ziege's WACC is 10.25%, but it adjusts for risk by adding 2% to the WACC for high-risk projects and subtracting 2%...
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project...
GeoGrocers is considering the following independent, average-risk investment projects: Project Size of Project Project IRR Project A $1.0 million 12.0% Project B 1.2 million 11.5% Project C 1.2 million 11.0% Project D 1.2 million 10.5% Project E 1.0 million 10.0% The company has a target capital structure that consists of 50 percent debt and 50 percent equity. Its after-tax cost of debt is 8 percent, its cost of equity is estimated to be 13.5 percent, and its net income is...