Question

In: Operations Management

Your company produces electronic connectors, which consist of a metal strip with multiple prongs assembled into...

Your company produces electronic connectors, which consist of a metal strip with multiple prongs assembled into a plastic housing. The manufacturing process is divided into four separate departments: 1) Injection molding, where the small plastic housings are produced; 2) Stamping, where the steel strips are punched out of thin coils of steel; 3) Plating, where the steel strips, after being stamped, are plated with tin or gold; and 4) Assembly, where the plated strips are inserted into the plastic housing.

The injection molding machines together have the capacity to produce 4000 plastic housing per hour. The firm's stamping presses can punch out 3000 steel strips per hour. The plating department has two dedicated lines—one for tin-plating and the other for the slower gold-plating process. The tin-plating line has a capacity of 2000 units per hour; the gold-plating line has a capacity of 500 units per hour. In the assembly department, there are six automated assembly machines, each with the capacity to assemble 400 connectors per hour.

Assume that machines never break down, and assume that there is sufficient plastic and steel raw material so that raw material availability never constrains the process. Assume that the plant is only running the tin-plated product—the gold-plating line is completely idle.

1) Assume that hourly demand during work hours for tin-plated connectors is 2200 units/hr and demand for gold-plated connectors is 600 units/hr, and that both processes are active. The plant runs for 8 hours/day, 5 days/week, 50 weeks/yr. Both connector types earn a margin of $0.10 apiece. The plant is considering investing in an additional automated assembly machine, which costs $400,000. What is the payback period for this investment (in years)?

Solutions

Expert Solution

Identification of bottleneck department:

As per the analysis of the case there is no capacity constraint from Injection molding department (4000 units per hour) and Stamping department (3000 units per hour). The only bottleneck is plating department (2500 units per hour).

Plating:

Given that the actual hourly demand for tin – plated connectors      = 2200 units / hr

Actual demand for gold-plated connectors                                        = 600 units / hr

Total demand to be produced and assembled                                   = 2600 units/hr

But as per the information given in the case:

The capacity of tin-plating line                                                           = 2000 units per hour

The gold-plating line has a capacity                                                  = 500 units per hour

Total quantity can be produced and assembled as per capacity = 2500 units per hour

Assembly:

No of machines available for assembly departments (old) = 6 machines

No of machines purchased for assembly departments (new) = 1 machines

Total machines available in assembly department                             = 7 machines

Capacity of each machine as per information given = 400 units / hr

No of connectors can be assembled per hour                                    = 2800 units / hr

Calculation of return from additional machine: Since plating department has capacity constraint with respective to meet the demand.

Maximum output to be produced from plating = 2500 units / hr

Load on old machines of Assembly department = 2400 units / hr

Load on new machine purchased                                                        = 100 units / hr

Margin from output produced by new machine = 100 units / hr * $ 0.10

                                                                                                             = $10 per hour

Margin from new machine per year                                                      = $10 per hour * 8 hrs per day * 5          days per weeks * 50 weeks per year

                                                                                                             = $ 20,000 per year

Investment in additional machine                                                         = $ 400,000

Payback period                                                                                     = value of investment / Return per year

                                                                                                             = $ 400,000 / $ 20,000

                                                                                                             = 20 years

The payback period of investment in new machine if worked as per capacity constraints is 20 years

Suggestion: If the company satisfies the demand by increasing the capacity of the plating department.

Calculation of return from additional machine:

Maximum output demand to be satisfied by plating    = 2800 units / hr

Load on old machines of Assembly department = 2400 units / h

Load on new machine purchased                                                        = 400 units / hr

Margin from output produced by new machine = 400 units / hr * $ 0.10

                                                                                                             = $40 per hour

Margin from new machine per year                                                      = $40 per hour * 8 hrs per day * 5          days per weeks * 50 weeks per year

                                                                                                             = $ 80,000 per year

Investment in additional machine                                                         = $ 400,000

Payback period                                                                                     = value of investment / Return per year

                                                                                                             = $ 400,000 / $ 80,000

                                                                                                             = 5 years

If the company satisfies the existing demand of total 2800 units per hour the payback period is 5 years.

It has to take measures to increase the capacity of bottleneck resource i.e., plating department.

Please like the answer and let us know.


Related Solutions

MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which...
MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2.5 million. Cash inflows of $14 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $12.5 million, payable at the end of Year 2. Plot the project's NPV profile. The correct sketch is . Should the project be accepted if WACC = 10%? Should the project be accepted if WACC...
MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which...
MULTIPLE IRRS AND MIRR A mining company is deciding whether to open a strip mine, which costs $2 million. Cash inflows of $13 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $11 million, payable at the end of Year 2. Plot the project's NPV profile.     The correct sketch is -Select-ABCDItem 1 . Should the project be accepted if WACC = 10%? -Select-YesNoItem 2 Should the...
When a strip of magnesium metal is burned in air (recall Figure 2-1), it produces a
When a strip of magnesium metal is burned in air (recall Figure 2-1), it produces a white powder that weighs more than the original metal. When a strip of magnesium is burned in a flashbulb, the bulb weighs the same before and after it is flashed. Explain the ­difference in these observations.
MajorCables manufactures electrical and electronic components. The company expects to produce 4000 units of coaxial connectors...
MajorCables manufactures electrical and electronic components. The company expects to produce 4000 units of coaxial connectors each month. Budgeted costs are as follows: direct material RM28,000, direct labour RM20,000, variable overhead RM40,000 and fixed overhead RM3000. Actual production for the month of December is 4100 units. Actual costs incurred for December are as follows: direct material RM28,290, direct labour RM22,000, variable overhead RM44,000 and fixed overhead RM,3000. Required: Prepare a flexible budget showing comparisons with actual costs and variances.
Metallic, Inc., produces metal gates in two processes: bending, in which metal is bent to the...
Metallic, Inc., produces metal gates in two processes: bending, in which metal is bent to the correct shape, and welding, in which the bent metal pieces are welded into gates. The bending process has a capacity of 19,500 units per year; welding has a capacity of 24,500 units per year. Demand is strong. At a sales price of $760 per unit, the company can sell whatever output it can produce. Metallic can start only 19,500 units into production in the...
Electrics   Ltd   is   a   Sydney-based   public   company   which   produces   electronic equipment. Popper is the managing director...
Electrics   Ltd   is   a   Sydney-based   public   company   which   produces   electronic equipment. Popper is the managing director and the other directors are Jones and Brown. Popper, through his holding of proxies for several institutions, is in a position to control 51% of the shares in Electrics. Popper's daughter wishes to sell a large block of land she owns in Newcastle as she is in urgent need of cash. A proposal that Electrics acquire the land is put to the board by...
Command Company produces two types of electronic products, Product A and Product B. Electronic gaming products...
Command Company produces two types of electronic products, Product A and Product B. Electronic gaming products are hot products now and either product A or product b could be sold to keep the manufacturing facility operating a full capacity. The constraint is direct labour hours and it is insufficient to meet the combined demand for both.   Both products are processed through the same production departments. The relevant information is as follows: Product A Product B Sales Price $ $250 $140...
5. A company produces metal pipes of a standard length, and claims that the variance of...
5. A company produces metal pipes of a standard length, and claims that the variance of the length is 1.44 cm. One of its clients decide to test this claim by taking a sample of 25 pipes and checking their lengths. They found that the standard deviation of the sample is 2.4 cm. Does this undermine the company’s claim? A. State the hypotheses b. Find the calculated value of the test statistic c. Find the critical value at α =...
Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers:...
Hammer Company produces a variety of electronic equipment. One of its plants produces two laser printers: the deluxe and the regular. At the beginning of the year, the following data were prepared for this plant: Deluxe Regular Quantity 100,000 800,000 Selling price $900 $750 Unit prime cost $529 $483 In addition, the following information was provided so that overhead costs could be assigned to each product: Activity Name Activity Driver Deluxe Regular Activity Cost Setups Number of setups 300 200...
Howard Company produces a variety of electronic equipment. One of its plants produces two dot matrix...
Howard Company produces a variety of electronic equipment. One of its plants produces two dot matrix printers, the superior and the regular. At the beginning of the year 2013, the following data were prepared for this plant:                                                                         Superior                       Regular                         Quantity                                   50,000                         400,000                         Selling price                            $475.00                           $300.00                         Unit prime cost*                      $180.00                           $110.00                         Unit overhead cost                     $20.00                          $130.00                         Prime cost equals direct materials and direct labor.                                 The unit overhead...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT