Question

In: Operations Management

A developer that specializes in compact urban amusement parks has formulated the following list of activities...

A developer that specializes in compact urban amusement parks has formulated the following list of activities necessary to release a contract for the preparation of a new site. Times are given in weeks.

                                                                                                                               Estimated                                                                                 Immediate            Activity Time

Activity           Description                                                     Predecessors         (weeks)            

A                     Preliminary architectural design                               _                      14

B                     Community impact hearings                                      A                     2

C                     Line up potential financiers                                       A                     12

D                     Permit application                                                      A                       5  

E                      Negotiate com’ity impact details                             B                      6

F                      Final Design                                                                  B                      8

G                     Loan approval                                                             C, F                   3

H                     Permit hearings                                                          D                       2

I                       Permit granting                                                          H                       8

J                      Negotiate contract                                                      G, I                    6

K                     Release contract                                                         E, J                      3

Which activities are on the critical path

Solutions

Expert Solution

Based on the given data, we prepare a project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration

Similarly, LFT & LST are calculated during the backward pass.

There are multiple paths in the diagram:

A-B-E-K

A-B-F-G-J-K

A-C-G-J-K

A-D-H-I-J-K

Out of the above paths, path A-C-G-J-K and A-D-H-I-J-K are the longest paths and have 0 slack for all activities on the path. Hence, these paths are the critical paths.

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!


Related Solutions

2. Following is a list of activities in the acquisition and payment cycle for inventory and...
2. Following is a list of activities in the acquisition and payment cycle for inventory and cost of goods sold. List at least three controls for each activity below and explain how to ensure good amount of control is proceeded. a. Requisition for goods and services b. Purchase of goods and services c. Receipt of, and accounting for, goods and services d. Approval of items for payment e. Cash disbursements 3. Following is a list of substantive tests could be...
2. (15 marks) The following model has been formulated to describe the manufacture of two products...
2. The following model has been formulated to describe the manufacture of two products X and Y. maximize 4X +5Y subject to: X +2Y ≤ 10 (labour in hours) 6X +6Y ≤ 36 (materials used in kg) 8X +4Y ≤ 40 (storage space in m^3 ) X,Y ≥ 0 Using Excel to solve gives the following output and sensitivity report: X Y OFV revenue $4.00 $5.00 $28.00 number 2 4 labour (hrs) 1 2 10 <= 10 material (kilo) 6...
A project manager has compiled a list of major activities that will be required to install...
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. Use standard deviation table. Activity Immediate Predecessor Estimated Times (weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1...
A GC needs to fill and compact a trench that has the following dimensions 150 x...
A GC needs to fill and compact a trench that has the following dimensions 150 x 50 x 1.5 ft.   The sub is going to use a dump truck that can carry 12 CY, and travels at an average speed of 40 mph. The borrow pit is located 45 miles from the construction site. The truck driver makes $50/hr and works 8 hours per day. Loading time for the truck is 30 minutes and unloading time is 5 minutes. The...
A client needs to fill and compact a trench that has the following dimensions 150 x...
A client needs to fill and compact a trench that has the following dimensions 150 x 50 x 1.5 ft. The sub is going to use a dump truck that can carry 12 CY, and travels at an average speed of 40 mph. The borrow pit is located 45 miles from the construction site. The truck driver makes $50/hr and works 8 hours per day. Loading time for the truck is 30 minutes and unloading time is 5 minutes. The...
Consider the following hypothetical scenario: The city council has just approved the construction of an amusement...
Consider the following hypothetical scenario: The city council has just approved the construction of an amusement park in your town. You are responsible for studying the impact of the new amusement park on the local economy and the surrounding community. Write a paper of approximately 500 words that addresses all of the questions below. Include the graphs, where indicated: o Question 1: You know that the amusement park will increase the traffic flow in the streets around the amusement park....
Question 1 (9 marks) A company is building an amusement park and has the following projected...
Question 1 A company is building an amusement park and has the following projected cashflows. Costs consist of building costs and staff salaries:     Year Building costs (assume as being paid at start of each respective year) 1 $100,000 2 $50,000 3 $30,000 4 $45,000 5 $0 for year 5 and all future years for building costs Staff salaries $4,000 for year 1, increasing by a discrete step of $100 at the start of each future year, but paid continuously...
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations....
Draw the PERT and Gantt (calendar) charts for the following list of activities and expected durations. Identify the critical path and list the slack times (if any) for the activities. Activity Immediate Predecessor Duration A - 3 B - 3 C - 4 D A, B 5 E B, C 4 F D, E 2 G E 3 H F, G 5  
List a few entities, attributes, activities, events, and state variables for the following processes: a. Checkout...
List a few entities, attributes, activities, events, and state variables for the following processes: a. Checkout process at a grocery store b. Admission process at hospital c. Insurance claim process
Following is a list of quality-related activities: Mark each activity according to whether it pertains to...
Following is a list of quality-related activities: Mark each activity according to whether it pertains to the internal costs of prevention, appraisal, production, or postsales costs. (Select all that may apply.) 1. Inspection of units when they are 100% complete to remove defective units prevention appraisal production post sales 2. Design of a process with as few parts as possible to reduce the chance of defects prevention appraisal production post sales 3. Warranty costs for defective products returned to the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT