Question

In: Accounting

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 78 % 74 % 71 % 68 %
Total sales (units) 3780 3618 3433 3304

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)
1 2 3 4
Move time per unit 0.7 0.5 0.6 0.6
Process time per unit 2.3 2.2 2.1 2.0
Wait time per order before start of production 25.0 27.4 30.0 32.4
Queue time per unit 4.9 5.6 6.4 7.3
Inspection time per unit 0.4 0.5 0.5 0.4


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

Solutions

Expert Solution

Part 1-a

Throughput time

Month 1

8.3

days

Month 2

8.8

days

Month 3

9.6

days

Month 4

10.3

days

Explanation:

1

2

3

4

Throughput time in days:

Process time

2.3

2.2

2.1

2.0

Inspection time

0.4

0.5

0.5

0.4

Move time

0.7

0.5

0.6

0.6

Queue time

4.9

5.6

6.4

7.3

Total throughput time

8.3

8.8

9.6

10.3

Part 1-b

Delivery cycle time

Month 1

33.3

days

Month 2

36.2

days

Month 3

41.6

days

Month 4

42.7

days

Explanation:

1

2

3

4

Delivery cycle time in days:

Wait time

25.0

27.4

32.0

32.4

Total throughput time

8.3

8.8

9.6

10.3

Total delivery cycle time

33.3

36.2

41.6

42.7

Part 1-c

Manufacturing cycle efficiency (MCE):

Process time ÷ Throughput time

Month 1

(2.3/8.3) = 27.7%

%

Month 2

(2.2/8.8)=25.0%

%

Month 3

(2.1/9.6)=21.9%

%

Month 4

(2.0/10.3)=19.4%

%

Part 2

DataSpan, Inc’s both throughtput time and delivery cycle time are increasing over the period of time. Due to increase in throughtput time, there is decrease in manufacturing cycle efficiency is decreasing constantly over the period of time.

Part 3-a

Month 5

Throughput Time

3.0

days

Manufacturing cycle efficiency (MCE)

66.7

%

Part 3-b

Month 6

Throughput Time

2.6

days

Manufacturing cycle efficiency (MCE)

76.9

%

Explanation for 3-a and 3-b:

5

6

Throughput time in days

Process time

2.0

2.0

Inspection time

0.4

0

Move time

0.6

0.6

Queue time

0.0

0.0

Total throughput time

3.0

2.6

5

6

Manufacturing cycle efficiency (MCE):Process time ÷ Throughput time

66.7%

(2.0/3.0)

76.9%

(2.0/2.6)


Related Solutions

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT