In: Finance
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%.
0 | 1 | 2 | 3 | 4 | ||||||
Project A | -1,150 | 690 | 350 | 240 | 290 | |||||
Project B | -1,150 | 290 | 285 | 390 | 740 |
What is Project A's NPV? Round your answer to the nearest cent.
Do not round your intermediate calculations.
$
What is Project B's NPV? Round your answer to the nearest cent.
Do not round your intermediate calculations.
$
If the projects were independent, which project(s) would be
accepted?
-Select-NeitherProject AProject BBoth projects A and BCorrect 1 of
Item 3
If the projects were mutually exclusive, which project(s) would be
accepted?
-Select-Neither Project AProject BBoth projects A and BCorrect 2 of
Item 3
Project A | |||||
Discount rate | 0,08 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1150 | 690 | 350 | 240 | 290 |
Discounting factor | 1 | 1,08 | 1,1664 | 1,259712 | 1,360489 |
Discounted cash flows project | -1150 | 638,8889 | 300,0686 | 190,5197 | 213,15866 |
NPV = Sum of discounted cash flows | |||||
NPV Project A = | 192,64 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Project B | |||||
Discount rate | 0,08 | ||||
Year | 0 | 1 | 2 | 3 | 4 |
Cash flow stream | -1150 | 290 | 285 | 390 | 740 |
Discounting factor | 1 | 1,08 | 1,1664 | 1,259712 | 1,360489 |
Discounted cash flows project | -1150 | 268,5185 | 244,3416 | 309,5946 | 543,92209 |
NPV = Sum of discounted cash flows | |||||
NPV Project B = | 216,38 | ||||
Where | |||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | ||||
Discounted Cashflow= | Cash flow stream/discounting factor | ||||
Accept both projects if independent as both have positive NPV
Accept project B if mutually exclusive as it has higher NPV