Question

In: Finance

Given the following information about the cash flows of a project that lasts for 6 years,...

Given the following information about the cash flows of a project that lasts for 6 years, answer the next 3 questions. The initial outlay is $100,000 , incremental cash flows for the next 6 years are $20,000 , $30,000 , $40,000 , $40,000 , $70,000 , $70,000. The discount rate is 13%.

1. What is the pay back period of the project?

2. What is the NPV of the project?

3. What is the IRR of the project?

Solutions

Expert Solution

1) Payback Period 3.25
Working:
Payback Period is the time within which cost of project is recovered back.
Year Cash flow Cumulative Cash flow
0 $       -1,00,000 $ -1,00,000
1                 20,000         -80,000
2                 30,000         -50,000
3                 40,000         -10,000
4                 40,000           30,000
5                 70,000       1,00,000
6                 70,000       1,70,000
Payback = 3+(10000/40000)
= 3.25
2) NPV $       65,063.76
Working:
Year Cash flow Discount factor Present Value
a b c=1.13^-a d=b*c
0 $       -1,00,000           1.0000 $ -1,00,000.00
1                 20,000           0.8850           17,699.12
2                 30,000           0.7831           23,494.40
3                 40,000           0.6931           27,722.01
4                 40,000           0.6133           24,532.75
5                 70,000           0.5428           37,993.20
6                 70,000           0.4803           33,622.30
NPV $       65,063.76
3) IRR 29.51%
Working:
Year Cash flow
0 $       -1,00,000
1                 20,000
2                 30,000
3                 40,000
4                 40,000
5                 70,000
6                 70,000
IRR =irr(C38:C44) C38:C44 is the range of cash flow from year 0 to year 6.
29.51%

Related Solutions

Given the following information, estimate the cash flows of this project and then compute the NPV...
Given the following information, estimate the cash flows of this project and then compute the NPV of this project. Estimated Sales: 50,000 units per year for each of the next 3 years Estimate Sale Price: $1,050 per unit Variable Cost: $1,000 per unit Fixed Costs: $1,500,000 per year Initial Investment in Plant and Machinery: $1,500,000 to be depreciated to a salvage value of $0 over the next three years. We sell the machine at $45000 in the market at the...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as...
Project A has the following Cash Flows: Cost = $1,200,000; Cash flows the following years as follows: Year 1 = $274,600; Year 2 = $298,000; Year 3 = $303,950; Year 4 = $312,875; and Year 5 = $374,600. Calculate the Traditional Payback. Assume cash flows are even throughout the year. Calculate the Net Present Value using the WACC = 8.28%.
Use the following information to calculate: A) Annual Cash Flows for years 1-6; B) the Initial...
Use the following information to calculate: A) Annual Cash Flows for years 1-6; B) the Initial Outlay; C) Depreciable Base; D) Depreciation Expense; E) Proceeds from Sale of Equipment (aka Cash Flow from Sale); F) the CF Total from the Terminal Year 6; G) the Net Present Value (NPV) of the Cash Flows for years 1-6; and H) the IRR (Internal Rate of Return) The answers to this question should be listed from A to H, with their corresponding values...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1...
Waste Industries is evaluating a $55,500 project with the following cash flows. Years Cash Flows 1 $ 9,120 2 20,200 3 26,600 4 16,300 5 26,300 The coefficient of variation for the project is 0.475. Coefficient of Variation Discount Rate 0 − 0.25 7 % 0.26 − 0.50 9 % 0.51 − 0.75 13 % 0.76 − 1.00 16 % 1.01 − 1.25 19 % Use Appendix B for an approximate answer but calculate your final answer using the formula...
Waste Industries is evaluating a $56,900 project with the following cash flows. Years Cash Flows 1...
Waste Industries is evaluating a $56,900 project with the following cash flows. Years Cash Flows 1 $ 9,710 2 19,200 3 26,500 4 19,800 5 27,300 The coefficient of variation for the project is 0.443. Coefficient of Variation Discount Rate 0 − 0.25 7 % 0.26 − 0.50 9 % 0.51 − 0.75 13 % 0.76 − 1.00 16 % 1.01 − 1.25 19 % Use Appendix B for an approximate answer but calculate your final answer using the formula...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a)...
A project that provides annual cash flows of $13,500 for 6 years costs $57,112 today. (a) If the required return is 13 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a....
A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
An investment project costs $17,400 and has annual cash flows of $4,400 for 6 years. If...
An investment project costs $17,400 and has annual cash flows of $4,400 for 6 years. If the discount rate is zero percent, the discounted payback period is __x__ years. If the discount rate is 4 percent, the discounted payback period is __y__ years. If the discount rate is 22 percent, the discounted payback period is __z__ years. (Enter 0 when there is no payback period. Round your answers to 2 decimal places. (e.g., 32.16)) What are the values for x,...
A capital project has an initial investment of $100,000 and cash flows in years 1-6 of...
A capital project has an initial investment of $100,000 and cash flows in years 1-6 of $25,000, $15,000, $50,000, $10,000, $10,000, and $60,000, respectively. Given a 15 percent cost of capital, (a) compute the net present value. (b) compute the internal rate of return (c) should the project be accepted? Why or why not?
1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1&
1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1            C2            C3            C4               C5          -$7000    +$3,000   +$4,000   +$6,000     +$2,500      +$2,000 _________________________________________________________ Calculate the following:     (a) NPV (Net Present Value) at 12% discount rate                                                (b) IRR (Internal Rate of Return)                                                (c) The payback period for Project (Z)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT