In: Finance
Given the following information about the cash flows of a project that lasts for 6 years, answer the next 3 questions. The initial outlay is $100,000 , incremental cash flows for the next 6 years are $20,000 , $30,000 , $40,000 , $40,000 , $70,000 , $70,000. The discount rate is 13%.
1. What is the pay back period of the project?
2. What is the NPV of the project?
3. What is the IRR of the project?
1) | Payback Period | 3.25 | ||||
Working: | ||||||
Payback Period is the time within which cost of project is recovered back. | ||||||
Year | Cash flow | Cumulative Cash flow | ||||
0 | $ -1,00,000 | $ -1,00,000 | ||||
1 | 20,000 | -80,000 | ||||
2 | 30,000 | -50,000 | ||||
3 | 40,000 | -10,000 | ||||
4 | 40,000 | 30,000 | ||||
5 | 70,000 | 1,00,000 | ||||
6 | 70,000 | 1,70,000 | ||||
Payback | = | 3+(10000/40000) | ||||
= | 3.25 | |||||
2) | NPV | $ 65,063.76 | ||||
Working: | ||||||
Year | Cash flow | Discount factor | Present Value | |||
a | b | c=1.13^-a | d=b*c | |||
0 | $ -1,00,000 | 1.0000 | $ -1,00,000.00 | |||
1 | 20,000 | 0.8850 | 17,699.12 | |||
2 | 30,000 | 0.7831 | 23,494.40 | |||
3 | 40,000 | 0.6931 | 27,722.01 | |||
4 | 40,000 | 0.6133 | 24,532.75 | |||
5 | 70,000 | 0.5428 | 37,993.20 | |||
6 | 70,000 | 0.4803 | 33,622.30 | |||
NPV | $ 65,063.76 | |||||
3) | IRR | 29.51% | ||||
Working: | ||||||
Year | Cash flow | |||||
0 | $ -1,00,000 | |||||
1 | 20,000 | |||||
2 | 30,000 | |||||
3 | 40,000 | |||||
4 | 40,000 | |||||
5 | 70,000 | |||||
6 | 70,000 | |||||
IRR | =irr(C38:C44) | C38:C44 is the | range of cash flow | from year 0 | to year 6. | |
29.51% | ||||||