Question

In: Finance

Kay Construction has the following mutually exclusive projects available. The company has historically used a three...

Kay Construction has the following mutually exclusive projects available. The company has historically used a three year cutoff for projects. The required return is 12 percent.

Year. Project A Project B

0. -$126,000. -$196,000

1. 64500. 44500

2. 45500. 59500

3. 55500. 85500

4. 50500. 115500

5. 45500. 130500

a. Calculate the payback period for both projects.

b. Calculate the NPV for both projects.

c. Which project, if any, should the company accept?

Solutions

Expert Solution

a
Project A
Year Cash flow stream Cumulative cash flow
0 -126000 -126000
1 64500 -61500
2 45500 -16000
3 55500 39500
4 50500 90000
5 45500 135500
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 2 and 3
therefore by interpolation payback period = 2 + (0-(-16000))/(39500-(-16000))
2.29 Years
Accept project as payback period is less than 3 years
Project B
Year Cash flow stream Cumulative cash flow
0 -196000 -196000
1 44500 -151500
2 59500 -92000
3 85500 -6500
4 115500 109000
5 130500 239500
Payback period is the time by which undiscounted cashflow cover the intial investment outlay
this is happening between year 3 and 4
therefore by interpolation payback period = 3 + (0-(-6500))/(109000-(-6500))
3.06 Years
Reject project as payback period is more than 3 years
b
Project A
Discount rate 0.12
Year 0 1 2 3 4 5
Cash flow stream -126000 64500 45500 55500 50500 45500
Discounting factor 1 1.12 1.2544 1.404928 1.5735194 1.762342
Discounted cash flows project -126000 57589.29 36272.32 39503.8 32093.663 25817.92
NPV = Sum of discounted cash flows
NPV Project A = 65277
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Accept project as NPV is positive
Project B
Discount rate 0.12
Year 0 1 2 3 4 5
Cash flow stream -196000 44500 59500 85500 115500 130500
Discounting factor 1 1.12 1.2544 1.404928 1.5735194 1.762342
Discounted cash flows project -196000 39732.14 47433.04 60857.21 73402.338 74049.2
NPV = Sum of discounted cash flows
NPV Project B = 99473.93
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Accept project as NPV is positive

c

Accept project A as NPV is positive and payback meets cutoff


Related Solutions

Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 14 percent. Year          Project F         Project G 0 –$133,000    –$203,000    1 61,000    41,000    2 49,000    56,000    3 59,000    89,000    4 54,000    119,000    5 49,000    134,000    a. Calculate the payback period for both projects. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Calculate the NPV for...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 10 percent. Year Project F Project G 0 −$195,000 −$298,000 1 98,400 71,600 2 86,300 94,500 3 81,600 123,600 4 72,000 166,800 5 64,800 187,200 Calculate the payback period for both projects. Calculate the NPV for both projects. Which project, if any, should the company accept?
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a...
Kaleb Konstruction, Inc., has the following mutually exclusive projects available. The company has historically used a three-year cutoff for projects. The required return is 11 percent. Year   Project F   Project G 0 –$ 139,000      –$ 209,000      1 58,000      38,000      2 52,000      53,000      3 62,000      92,000      4 57,000      122,000      5 52,000      137,000      Required: (a) Calculate the payback period for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Payback period   Project F...
King, Inc. has the following mutually exclusive projects available. The company has historically used a 4-year...
King, Inc. has the following mutually exclusive projects available. The company has historically used a 4-year cut-off for projects. The required return is 11 percent. Year Cash Flow (Project X) Cash Flow (Project Y) 0 -$82,000 -$125,000 1 15,700 38,600 2 18,300 33,400 3 23,900 31,200 4 26,200 27,500 5 32,100 24,000 (a) Calculate the Payback period of both projects. (b) State two advantages and two disadvantages of Payback period rule? (c) Calculate the IRR of both projects. (d) Under...
Strand Plc has the following two mutually exclusive projects available to invest in. the discount rate...
Strand Plc has the following two mutually exclusive projects available to invest in. the discount rate is 10%. Each project can be undertaken only once. Cash flows Project Initial cost Year 1    Year 2 Year 3 1 (500) 400    200    100 2 (1000) 500    400 500 Required: (a) Calculate the payback period for each of the projects. Based upon the payback criterion which project should be chosen? (b) Calculate the net present value (NPV) of each...
Seether inc has the following two mutually exclusive projects available. What is the crossover rate for...
Seether inc has the following two mutually exclusive projects available. What is the crossover rate for these two projects? What is the NPV of each project at the crossover rate? Year Project R Project S 0 -45000 -76000 1 17000 20000 2 19000 20000 3 21000 35000 4 9000 30000 5 7000 10000
Suppose a company has two mutually exclusive projects, both of which are three years in length....
Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $6,000 and has expected cash flows of $4,000 in year 1, $5,000 in year 2, and $5,000 in year 3. Project B has an initial outlay of $9,000 and has expected cash flows of $2,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 10% for projects at...
Suppose a company has two mutually exclusive projects, both of which are three years in length....
Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $7,000 and has expected cash flows of $3,000 in year 1, $4,000 in year 2, and $4,000 in year 3. Project B has an initial outlay of $10,000 and has expected cash flows of $2,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 12% for projects at...
Suppose a company has two mutually exclusive projects, both of which are three years in length....
Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $8,000 and has expected cash flows of $3,000 in year 1, $4,000 in year 2, and $6,000 in year 3. Project B has an initial outlay of $7,000 and has expected cash flows of $4,000 in year 1, $5,000 in year 2, and $6,000 in year 3. The required rate of return is 13% for projects at...
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available...
QUESTION TWO [30] The following 2 mutually exclusive projects (Project A and Project B) are available to Simonsbosch Farm. They are producers of Rooi Bos tea. The initial cash outlay and cash flows are shown below and Simonsbosch will use straight line depreciation over each of the assets 4 year life and there will be no residual value on either investment. Years Cash Flows (A) Cash Flows (B) 0 (Investment) -240 000 -90 000 1 28 000 40 000 2...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT